223 chapters · 1,791 sections in this title.
Ind. Code § 32-28-7-1 Actions to foreclose or enforce
0.5K chars
Sec. 1. An action may not be brought or maintained in Indiana to foreclose or enforce a mechanic's lien filed under Indiana law when the debt secured by the lien, as shown by the record of the lien, has been due more than one (1) year. If the record of the lien does not show when…
Ind. Code § 32-28-7-2 Record; notice of lien
0.4K chars
Sec. 2. A mechanic's lien filed under Indiana law expires one (1) year after the debt secured by the lien becomes due, as shown by the record of the lien. If the record of the mechanic's lien does not show when the debt secured by the lien becomes due, the mechanic's lien expires…
Ind. Code § 32-28-7-3 Public improvement assessments; expiration of liens
1.1K chars
Sec. 3. (a) Except as provided in subsection (b), the lien of an assessment for a: (1) street; (2) sewer; (3) sidewalk; (4) ditch; or (5) other public improvement; expires five (5) years after the assessment (including any installment payments) is due and payable, as shown by the…
Ind. Code § 32-28-7-4 Action to foreclose or enforce liens
0.3K chars
Sec. 4. If an action to enforce a lien to which this chapter applies was commenced in Indiana before the lien expired, the lien as it existed at the time the action commenced may be enforced. [Pre-2002 Recodification Citation: 32-8-7-4.] As added by P.L.2-2002, SEC.13.