16-1907. Provisions waiving right to collect damages for delays, void, unenforceable. Any provision in a contract that purports to waive the rights of a party to the contract to collect damages for delays caused by another party to the contract shall be void, unenforceable and against public policy. This provision is not intended to create a contract between parties where a contract did not otherwise exist. History: L. 2007, ch. 163, § 7; July 1. Previous | Next LEGISLATIVE COORDINATING COUNCIL General Policies 2026 Archived LCC Documents Archived LCC Meetings REVISOR OF STATUTES Archived Session Documents Archived School Finance Documents USEFUL LINKS Session Laws Kansas Administrative Regulations OTHER LEGISLATIVE SITES Kansas Legislature Administrative Services Division of Post Audit Research Department Contact Us PDF Help www.ksrevisor.gov 2026