21,718 sections across 817 New Hampshire regulatory chapters.
He-Hea 300-He-Hea 301.11 Effective Date of a Certificate of Need
0.6K chars
(a) The effective date of a certificate of need shall be the date the board renders its decision to approve, or approve with condition, the project under consideration. (b) In cases where the board rehears an application upon request pursuant to RSA 151-C:9, IV, the effective dat…
He-Hea 300-He-Hea 301.12 Project Commencement and Completion Dates
1.3K chars
(a) Pursuant to RSA 151-C:12, I, the following project commencement and completion dates shall apply to a CON that has been granted pursuant to He-Hea 214:(1) Projects involving the acquisition and installation of equipment shall be completed within 2 years of the issuance of the…
He-Hea 300-He-Hea 301.13 Change of Scope
1.9K chars
(a) Pursuant to RSA 151-C:12, IV-a, the board shall require an applicant for a CON to file for a change of project scope if: (1) The total project cost will exceed the CON approved amount by more than 15% plus inflation; (2) The financing method of the application will differ due…