R.17.9.569-17.9.569.6 OBJECTIVE
0.2K chars
The purpose of this rule is to set forth common interconnection requirements for the interconnection of generating facilities with a rated capacity greater than 10 MW in a safe and reliable manner.
R.17.9.569-17.9.569.7 DEFINITIONS
2.1K chars
Terms used in this rule 17.9.569 NMAC shall have the following meanings. A. Business day means Monday through Friday, excluding holidays observed by the utility. B. Generating facility means the interconnection customer's device for the production of electricity identified in the…
R.17.9.569-17.9.569.8 GENERAL PROVISIONS FOR INTERCONNECTION APPLICATIONS FOR FACILITES WITH RATED CAPACITIES GREATER THAN 10 MW
10.0K chars
A. A utility shall interconnect with any interconnection customer that: (1) is in its service area; (2) qualifies for the interconnection procedures in this rule 17.9.569 NMAC; (3) files an interconnection application in accordance with Subsection B of 17.9.569.8 NMAC; (4) meets …