Ohio Rev. Code Ann. § 4928.64 Electric distribution utility to provide electricity from qualifying renewable energy resources
11.8K chars
(A)(1) As used in this section, "qualifying renewable energy resource" means a renewable energy resource, as defined in section 4928.01 of the Revised Code that: (a) Has a placed-in-service date on or after January 1, 1998; (b) Is any run-of-the-river hydroelectric facility that …
Ohio Rev. Code Ann. § 4928.641 Costs being recovered through bypassable charge
0.9K chars
(A) If an electric distribution utility has executed a contract before April 1, 2014, to procure renewable energy resources and there are ongoing costs associated with that contract that are being recovered from customers through a bypassable charge as of September 12, 2014, that…
Ohio Rev. Code Ann. § 4928.643 Baselines for compliance with qualified renewable energy resource requirements
1.6K chars
(A) Except as provided in division (B) of this section and section 4928.644 of the Revised Code, the baseline for an electric distribution utility's or an electric services company's compliance with the qualified renewable energy resource requirements of section 4928.64 of the Re…
Ohio Rev. Code Ann. § 4928.644 Adjustments to baselines
1.1K chars
(A) The public utilities commission may reduce either baseline described in section 4928.643 of the Revised Code to adjust for new economic growth in the electric distribution utility's certified territory or in the electric services company's service area in this state. (B) To f…