Section 13. Bucks County.
(a) Local Bridges
(1) Solesbury Township, Reeder Road, Bridge Rehabilitation
175,000
(Base Construction Allocation - $175,000)
(2) Solesbury Township, Covered Bridge Road, Bridge Rehabilitation
95,000
(Base Construction Allocation - $95,000)
(3) Solesbury Township, Cuttalossa Road, Bridge Replacement
200,000
(Base Construction Allocation - $200,000)
(4) Solesbury Township, Sugan Road, Bridge Replacement
300,000
(Base Construction Allocation - $300,000)
(5) Solesbury Township, Lower Mountain Road, Bridge Rehabilitation
95,000
(Base Construction Allocation - $95,000)
(b) State Bridges
(1) SR 2038 over Southampton Creek, Upper Southampton Township, Bridge Replacement
148,000
(Base Construction Allocation - $92,000)
(Land Allocation - $28,000)
(Design and Contingencies - $28,000)
(2) SR 2053 over Queen Anne Creek, Falls Township, Bridge Replacement
132,000
(Base Construction Allocation - $82,000)
(Land Allocation - $25,000)
(Design and Contingencies - $25,000)
(3) SR 2063 over Mill Creek, Lower Southampton Township, Bridge Replacement
138,000
(Base Construction Allocation - $86,000)
(Land Allocation - $26,000)
(Design and Contingencies - $26,000)
(4) SR 2089 over Little Neshaminy Creek, Warwick Township, Bridge Replacement
400,000
(Base Construction Allocation - $250,000)
(Land Allocation - $75,000)
(Design and Contingencies - $75,000)
(5) SR 4025 over Deep Run, Bedminster Township, Bridge Replacement
101,000
(Base Construction Allocation - $63,000)
(Land Allocation - $19,000)
(Design and Contingencies - $19,000)
(6) SR 8071 over Rock Run, Falls Township, Bridge Replacement
72,000
(Base Construction Allocation - $46,000)
(Land Allocation - $13,000)
(Design and Contingencies - $13,000)
(7) SR 0013 over Branch of Martins Creek, Falls Township, Bridge Replacement
247,000
(Base Construction Allocation - $155,000)
(Land Allocation - $46,000)
(Design and Contingencies - $46,000)
(8) SR 1014 over Branch of Swamp Creek, Tinicum Township, Bridge Replacement
76,000
(Base Construction Allocation - $47,000)
(Land Allocation - $14,000)
(Design and Contingencies - $14,000)
(9) SR 2006 over Branch of Martins Creek, Falls Township, Bridge Replacement
130,000
(Base Construction Allocation - $81,000)
(Land Allocation - $24,000)
(Design and Contingencies - $24,000)
(10) SR 2018 over Branch of Queen Anne Creek, Seg.0060, Middletown Township, Bridge Replacement
132,000
(Base Construction Allocation - $83,000)
(Land Allocation - $25,000)
(Design and Contingencies - $25,000)
(11) SR 2018 over Mill Creek, Seg.0030, Middletown Township, Bridge Replacement
138,000
(Base Construction Allocation - $86,000)
(Land Allocation - $26,000)
(Design and Contingencies - $26,000)
(12) SR 2025 over Ironworks Creek, Northampton Township, Bridge Replacement
115,000
(Base Construction Allocation - $72,000)
(Land Allocation - $22,000)
(Design and Contingencies - $22,000)
(13) SR 2033 over Queen Anne Creek, Middletown Township, Bridge Replacement
453,000
(Base Construction Allocation - $283,000)
(Land Allocation - $85,000)
(Design and Contingencies - $85,000)
(14) SR 2043 over Neshimany Creek, Lower Southampton Township, Bridge Replacement
521,000
(Base Construction Allocation - $325,000)
(Land Allocation - $98,000)
(Design and Contingencies - $98,000)
(15) SR 0263, Warwick Township, Bridge Rehabilitation
100,000
(Base Construction Allocation - $100,000)