Erie County

Act 103 of 2006, § 29, under HIGHWAY-RAILROAD AND HIGHWAY BRIDGE CAPITAL BUDGET SUPPLEMENTAL ACT FOR 2005-2006.

Act 103 of 2006, § 29

Section 29. Erie County.

(a) Local Bridges

(1) North East Township, T-743, West Law Road over Twelve Mile Creek, Bridge Replacement

450,000

(Base Construction Allocation - $450,000)

(2) North East Township, Bort Road over Railroad, Bridge Replacement

1,000,000

(Base Construction Allocation - $1,000,000)

(3) McKean Township, T-661 over Tributary of Elk Creek, Reichart Road No.2, Bridge Replacement

515,000

(Base Construction Allocation - $515,000)

(4) McKean Township, T-450, Rick Road over Elk Creek, Bridge Replacement

1,650,000

(Base Construction Allocation - $1,650,000)

(5) Springfield Township, T-338, McKee Road over Conneaut Creek, Bridge Replacement

600,000

(Base Construction Allocation - $600,000)

(6) McKean Township, Old Route 99 over Lamson Run, Bridge Replacement

600,000

(Base Construction Allocation - $500,000)

(Land Allocation - $25,000)

(Design and Contingencies - $75,000)

(7) Washington Township, T-349, Conneaut Road over Little Conneaut Creek, Bridge Replacement

400,000

(Base Construction Allocation - $350,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(8) McKean Township, Old Route 99 over Lamson Run, Bridge Replacement

600,000

(Base Construction Allocation - $500,000)

(Land Allocation - $25,000)

(Design and Contingencies - $75,000)

(9) Harborcreek Township, T-628, Depot Street over Seven Mile Creek, Bridge Replacement

560,000

(Base Construction Allocation - $560,000)

(10) McKean Township, T-480, Old Route 99 over Lamson Run, Bridge Replacement

600,000

(Base Construction Allocation - $500,000)

(Land Allocation - $25,000)

(Design and Contingencies - $75,000)

(11) Summit Township, T-619, Jackson Station Road over Le Boeuf Creek, Bridge Replacement

500,000

(Base Construction Allocation - $500,000)

(12) Union City Borough, Pleasant Street over Tributary of French Creek, Bridge Replacement

600,000

(Base Construction Allocation - $500,000)

(Land Allocation - $25,000)

(Design and Contingencies - $75,000)

(13) Washington Township, T-349, Conneaut Road over Little Conneaut Creek, Bridge Replacement

545,000

(Base Construction Allocation - $500,000)

(Design and Contingencies - $45,000)

(14) Washington Township, T-508, Perry Lane over Conneaut Creek, Bridge Replacement

450,000

(Base Construction Allocation - $450,000)

(15) Waterford Borough, South Hazel Street over Le Boeuf Creek, Bridge Replacement

570,000

(Base Construction Allocation - $570,000)

(16) Waterford Borough, South Hazel Street over Le Boeuf Creek, Bridge Replacement

43,000

(Base Construction Allocation - $25,000)

(Land Allocation - $8,000)

(Design and Contingencies - $10,000)

(17) Waterford Borough, South Hazel Street over Le Boeuf Creek, Bridge Replacement

540,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(18) Waterford Borough, T-596, Flatts Road over Le Boeuf Creek, Bridge Replacement

650,000

(Base Construction Allocation - $650,000)

(19) Wayne Township, T-826, Mill Road over Brokenstraw Creek, Bridge Replacement

750,000

(Base Construction Allocation - $750,000)

(20) Harborcreek Township, T-640, Bartlett Road over Elliotts Run, Bridge Replacement

560,000

(Base Construction Allocation - $560,000)

(21) Mill Village Borough, Depot Street over Tributary of French Creek, Bridge Replacement

250,000

(Base Construction Allocation - $200,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(22) Washington Township, T-518, Beason Road over Conneaut Creek, Bridge Replacement

445,000

(Base Construction Allocation - $400,000)

(Land Allocation - $5,000)

(Design and Contingencies - $40,000)

(23) City of Erie, T-7302, West 38th Street over Mill Creek, Bridge Replacement

700,000

(Base Construction Allocation - $700,000)

(24) North East Township, T-780, Bort Road over Tributary of Lake Erie, Bridge Replacement

500,000

(Base Construction Allocation - $500,000)

(25) Greenfield Township, T-994, Ashton Road over West Branch of French Creek, Bridge Replacement

500,000

(Base Construction Allocation - $500,000)

(26) City of Erie, Norman Way over Mill Creek, Bridge Replacement

1,110,000

(Base Construction Allocation - $800,000)

(Land Allocation - $10,000)

(Design and Contingencies - $300,000)

(27) City of Erie, State Street over Railroad, Bridge Replacement

902,000

(Base Construction Allocation - $800,000)

(Land Allocation - $2,000)

(Design and Contingencies - $100,000)

(28) Concord Township, T-387, Mitchell Road over Lilley Run, Bridge Replacement

450,000

(Base Construction Allocation - $400,000)

(Land Allocation - $5,000)

(Design and Contingencies - $45,000)

(29) Conneaut Township, T-883, Akerley Road over Ashtabula Creek, Bridge Replacement

450,000

(Base Construction Allocation - $400,000)

(Land Allocation - $5,000)

(Design and Contingencies - $45,000)

(30) Conneaut Township, T-301, Boyce Road over Stone Run, Bridge Replacement

670,000

(Base Construction Allocation - $600,000)

(Land Allocation - $10,000)

(Design and Contingencies - $60,000)

(31) Conneaut Township, T-330, Porkey Road over West Branch of Conneaut Creek, Bridge Replacement

470,000

(Base Construction Allocation - $400,000)

(Land Allocation - $10,000)

(Design and Contingencies - $60,000)

(32) Conneaut Township, T-300, State Line Road over Ashtabula Creek, Bridge Replacement

470,000

(Base Construction Allocation - $400,000)

(Land Allocation - $10,000)

(Design and Contingencies - $60,000)

(33) Conneaut Township, T-883, Akerley Road over Ashtabula Creek, Bridge Replacement

470,000

(Base Construction Allocation - $470,000)

(34) Conneaut Township, T-301, Boyce Road over Stone Run, Bridge Replacement

670,000

(Base Construction Allocation - $600,000)

(Land Allocation - $10,000)

(Design and Contingencies - $60,000)

(35) Conneaut Township, T-330, Porkey Road over West Branch of Conneaut Creek, Bridge Replacement

470,000

(Base Construction Allocation - $400,000)

(Land Allocation - $10,000)

(Design and Contingencies - $60,000)

(36) Greene Township, T-664, Jones Road over Six Mile Creek, Bridge Replacement

350,000

(Base Construction Allocation - $350,000)

(37) Franklin Township, T-424, Falls Road over Falk Run, Bridge Replacement

450,000

(Base Construction Allocation - $450,000)

(38) Greenfield Township, T-711, Wilson Road over Darrow Brook, Bridge Replacement

400,000

(Base Construction Allocation - $400,000)

(39) Greenfield Township, T-974, Old Route 89 over Tributary of West Branch of French Creek, Bridge Replacement

400,000

(Base Construction Allocation - $400,000)

(40) Greene Township, T-609, Kane Hill Road over Four Mile Creek, Bridge Replacement

500,000

(Base Construction Allocation - $500,000)

(41) Greene Township, T-646, Bliley Road over Branch of Le Boeuf Creek, Bridge Replacement

350,000

(Base Construction Allocation - $350,000)

(42) City of Corry, Shady Avenue over Hare Creek, Bridge Replacement

116,000

(Base Construction Allocation - $50,000)

(Land Allocation - $16,000)

(Design and Contingencies - $50,000)

(43) Girard Township, T-400, Gudgeonville Road over Elk Creek, Bridge Replacement

100,000

(Base Construction Allocation - $100,000)

(44) Girard Township, T-544, Elk Park Road over Elk Creek, Bridge Replacement

995,000

(Base Construction Allocation - $995,000)

(45) Greenfield Township, T-974, Old Route 89 over Tributary of French Creek, Bridge Replacement

400,000

(Base Construction Allocation - $350,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(46) Conneaut Township, Ore Docks Road over Ashtabula Creek, Bridge Replacement

585,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $75,000)

(47) Franklin Township, Carbury Road over Cussewago Creek, Bridge Replacement

585,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $75,000)

(48) North East Township, Brickyard Road over Twelve Mile Creek, Bridge Replacement

585,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $75,000)

(49) Venango Township, Hardscrabble Road over French Creek, Bridge Replacement

585,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $75,000)

(50) North East Township, Brickyard Road over Twelve Mile Creek, Bridge Replacement

585,000

(Base Construction Allocation - $500,000)

(Land Allocation - $10,000)

(Design and Contingencies - $75,000)

(51) City of Erie, State Street over Canal Basin, Bridge Replacement

1,335,000

(Base Construction Allocation - $1,075,000)

(Land Allocation - $10,000)

(Design and Contingencies - $250,000)

(52) City of Erie, East Avenue over Railroad, Bridge Replacement

520,000

(Base Construction Allocation - $500,000)

(Design and Contingencies - $20,000)

(53) City of Erie, Norman Way over Mill Creek, Bridge Replacement

1,110,000

(Base Construction Allocation - $800,000)

(Land Allocation - $10,000)

(Design and Contingencies - $300,000)

(54) City of Erie, Baternan Avenue over Conneaut Creek, Bridge Rehabilitation

25,000

(Base Construction Allocation - $20,000)

(Design and Contingencies - $5,000)

(55) Springfield Township, McKee Road over Conneaut Creek, Bridge Replacement

750,000

(Base Construction Allocation - $500,000)

(Design and Contingencies - $250,000)

(56) McKean Township, T-480, approximately .2 Miles West of Route 99 south of South Hill Road over Lamson Run, Bridge Replacement

530,000

(Base Construction Allocation - $400,000)

(Land Allocation - $10,000)

(Design and Contingencies - $120,000)

(57) McKean Township, T-480, Old Route 99 just North of East and West Stancliff Roads over Lamson Run, Bridge Replacement

630,000

(Base Construction Allocation - $480,000)

(Land Allocation - $10,000)

(Design and Contingencies - $140,000)

(58) McKean Township, T-480, approximately .3 Miles West of Route 99 North of East Stancliff Road over Lamson Run, Bridge Replacement

630,000

(Base Construction Allocation - $480,000)

(Land Allocation - $10,000)

(Design and Contingencies - $140,000)

(b) State Bridges

(1) I-79 and I-90 over Elk Creek, McKean Township, Bridge Rehabilitation

156,000

(Base Construction Allocation - $156,000)

(2) Various Bridges over I-90, Girard Township, Bridge Rehabilitation

255,000

(Base Construction Allocation - $200,000)

(Land Allocation - $5,000)

(Design and Contingencies - $50,000)

(3) SR 0018, Platea Railroad Bridge, Platea Borough, Bridge Rehabilitation

220,000

(Base Construction Allocation - $140,000)

(Land Allocation - $20,000)

(Design and Contingencies - $60,000)

(4) SR 0090 over PA 97 Eastbound, Summit Township, Bridge Rehabilitation

400,000

(Base Construction Allocation - $340,000)

(Land Allocation - $10,000)

(Design and Contingencies - $50,000)

(5) SR 8009, Ramp B over I-79, City of Erie, Bridge Rehabilitation

960,000

(Base Construction Allocation - $820,000)

(Land Allocation - $20,000)

(Design and Contingencies - $120,000)

(6) SR 0090 over Tributary No.5 of Walnut Creek, Summit Township, Bridge Rehabilitation

200,000

(Base Construction Allocation - $160,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(7) SR 0018 over Conneaut Creek Bridge, Conneaut Township, Bridge Rehabilitation

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(8) SR 0090 over Tributary No.1 of Turkey Creek, Springfield Township, Bridge Rehabilitation

160,000

(Base Construction Allocation - $120,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(9) SR 0008 over Mill Creek, Millcreek Township, Bridge Rehabilitation

130,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(10) SR 0020 over Branch of Turkey Creek, Springfield Township, Bridge Rehabilitation

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(11) SR 0020 over Cascade Creek, Millcreek Township, Bridge Rehabilitation

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(12) SR 0020 over Crooked Creek Bridge, Girard Township, Bridge Rehabilitation

200,000

(Base Construction Allocation - $160,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(13) SR 3013 over Conneaut Creek Bridge, Conneaut Township, Bridge Rehabilitation

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(14) SR 3025, Cummings Creek Bridge, Washington Township, Bridge Replacement

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(15) SR 0505 over Branch of Mill Creek, Millcreek Township, Bridge Rehabilitation

120,000

(Base Construction Allocation - $80,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(16) SR 3025 over Little Conneaut Creek, Washington Township, Bridge Rehabilitation

130,000

(Base Construction Allocation - $90,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(17) SR 0006, Mill Village Railroad Underpass, SR 0006 at Seg.0100 in Mill Village Borough, Removal and Replacement

330,000

(Base Construction Allocation - $200,000)

(Land Allocation - $50,000)

(Design and Contingencies - $80,000)

(18) SR 1005 over Le Boeuf Creek, Greene Township, Bridge Replacement

112,000

(Base Construction Allocation - $70,000)

(Land Allocation - $21,000)

(Design and Contingencies - $21,000)

(19) SR 2022 over Beaver Creek, Wayne Township, Bridge Replacement

84,000

(Base Construction Allocation - $52,000)

(Land Allocation - $16,000)

(Design and Contingencies - $16,000)

(20) SR 2024 over Hubbel Run, Amity Township, Bridge Replacement

84,000

(Base Construction Allocation - $52,000)

(Land Allocation - $16,000)

(Design and Contingencies - $16,000)

(21) SR 4024 over Walnut Creek, Summit Township, Bridge Replacement

80,000

(Base Construction Allocation - $50,000)

(Land Allocation - $15,000)

(Design and Contingencies - $15,000)