Itemization of public improvement projects

Act 113 of 1988, § 3, under CAPITAL BUDGET PROJECT ITEMIZATION ACT - 1987/1988.

Act 113 of 1988, § 3

Section 3. Itemization of public improvement projects.

Additional capital projects in the category of public improvement projects to be constructed or acquired by the Department of General Services, its successors or assigns, and to be financed by the incurring of debt, are hereby itemized, together with their respective estimated financial costs, as follows:

Total

Project

Project

Allocation

(1) Department of Agriculture

$556,000

(i) Farm Show Complex - Harrisburg

(A) Parking areas and hard stand improvements

556,000

(Base Project Allocation - $463,000)

(Design and Contingencies - $93,000)

(2) Department of Corrections

$156,991,000

(Amount amended July 11, 1989, P.L.320, No.54)

(i) State Correctional Institution - Camp Hill

(A) Life safety code improvements

4,290,000

(Base Project Allocation - $3,575,000)

(Design and Contingencies - $715,000)

(ii) State Correctional Institution - Dallas

(A) Additional funds for DGS 578-11, guard towers

157,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $26,000)

(B) Additional funds for DGS 578-10, security and lighting

792,000

(Base Project Allocation - $660,000)

(Design and Contingencies - $132,000)

(C) Construction and installation of a water line

795,000

(Base Project Allocation - $663,000)

(Design and Contingencies - $132,000)

(iii) State Correctional Institution - Graterford

(A) Additional funds for DGS 577-10, sewage treatment system

1,734,000

(Base Project Allocation - $1,445,000)

(Design and Contingencies - $289,000)

(B) Life safety code improvements

9,720,000

(Base Project Allocation - $8,100,000)

(Design and Contingencies - $1,620,000)

(C) Installation of waterline and storage tank

2,544,000

(Base Project Allocation - $2,120,000)

(Design and Contingencies - $424,000)

This project is a replacement for project DGS 577-21 authorized in the act of July 10, 1986 (P.L.1285, No.118).

((C) added July 11, 1989, P.L.320, No.54)

(iv) State Correctional Institution - Huntingdon

(A) Security fence and lighting

330,000

(Base Project Allocation - $275,000)

(Design and Contingencies - $55,000)

(B) Life safety code improvements

3,498,000

(Base Project Allocation - $2,915,000)

(Design and Contingencies - $583,000)

(v) State Regional Correctional Facility - Mercer County

(A) Construction of a chapel for use of inmates

400,000

(Base Project Allocation - $400,000)

(vi) State Correctional Institution - Philadelphia

(A) ((A) deleted by amendment July 11, 1989, P.L.320, No.54)

(B) Construction of new detention facility for the City of Philadelphia

50,000,000

(Base Project Allocation - $50,000,000)

(vii) State Correctional Institution - Retreat

(A) Additional funds for DGS 1575-1, conversion of Retreat State Hospital to a State Correctional Institution

4,304,000

(Base Project Allocation - $3,587,000)

(Design and Contingencies - $717,000)

(B) Rehabilitate entrance bridge

792,000

(Base Project Allocation - $660,000)

(Design and Contingencies - $132,000)

(C) Renovations to boiler plant

700,000

(Base Project Allocation - $583,000)

(Design and Contingencies - $117,000)

This project is a replacement for project DGS 1575-2 authorized in the act of July 10, 1986 (P.L.1285, No.118).

((C) added July 11, 1989, P.L.320, No.54)

(viii) State Correctional Institution - Rockview

(A) Restricted housing unit

4,802,000

(Base Project Allocation - $3,960,000)

(Design and Contingencies - $842,000)

(B) Second perimeter fence and lighting

942,000

(Base Project Allocation - $785,000)

(Design and Contingencies - $157,000)

(ix) State Correctional Institution - Smithfield

(A) Bake shop

792,000

(Base Project Allocation - $660,000)

(Design and Contingencies - $132,000)

(B) Cell block

6,864,000

(Base Project Allocation - $5,720,000)

(Design and Contingencies - $1,144,000)

(x) State Correctional Institution - Waynesburg

(A) Emergency generator

198,000

(Base Project Allocation - $165,000)

(Design and Contingencies - $33,000)

(B) Perimeter lighting and electronic type perimeter detection system

257,000

(Base Project Allocation - $257,000)

(C) Educational/Visitors Center

480,000

(Base Project Allocation - $480,000)

(xi) State Correctional Institution - City of Chester, Pennsylvania

(A) Construction of a new prison facility to house and provide treatment for drug offenders, including land acquisition

50,000,000

(Base Project Allocation - $41,667,000)

(Design and Contingencies - $8,333,000)

((xi) added July 11, 1989, P.L.320, No.54)

(xii) State Correctional Institution - Farview

(A) Conversion of parts of Farview State Hospital into a correctional institution

12,600,000

(Base Project Allocation - $12,600,000)

((xii) added July 11, 1989, P.L.320, No.54)

(3) Department of Education

$442,003,000

(Amount amended July 11, 1989, P.L.320, No.54)

(i) Lincoln University

(A) Fire protection improvements

460,000

(Base Project Allocation - $383,000)

(Design and Contingencies - $77,000)

(B) Construction of Living-Learning Center

17,100,000

(Base Project Allocation - $17,100,000)

(ii) Scranton State School for the Deaf

(A) Renovation to school properties

2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(iii) Scotland School for Veterans' Children

(A) Campus fire alarm system

726,000

(Base Project Allocation - $605,000)

(Design and Contingencies - $121,000)

(B) Replacement of PCB transformers

462,000

(Base Project Allocation - $385,000)

(Design and Contingencies - $77,000)

(iv) Thaddeus Stevens State School of Technology

(A) Conversion of cottages "A" and "B" and construction of an addition for a learning resource center

4,000,000

(Base Project Allocation - $3,300,000)

(Design and Contingencies - $700,000)

(B) Resurface roads and parking area

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Repairs to athletic field

210,000

(Base Project Allocation - $175,000)

(Design and Contingencies - $35,000)

(D) Replacement of sidewalks and curbing

157,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $26,000)

(E) Landscaping and fencing

168,000

(Base Project Allocation - $140,000)

(Design and Contingencies - $28,000)

(F) Energy conservation: Installation of storm windows and install automatic temperature control

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(G) Utility repairs and improvements: Replace various sewer and water lines; replace steam lines and improve boiler room instrumentation

372,000

(Base Project Allocation - $310,000)

(Design and Contingencies - $62,000)

(H) Painting, glazing and roof repairs: Miscellaneous slate, tin and spout repairs, all buildings as required; also roof repairs Hartzell classroom building

441,000

(Base Project Allocation - $369,000)

(Design and Contingencies - $72,000)

(I) Rehabilitation and Safety Equipment: Installation of smoke detectors; replace fire escape; replace fire alarm activator; renovate Canteen building; repair floors and doors in Brenner Hall and the Administration Building; expand master lock system

547,000

(Base Project Allocation - $457,000)

(Design and Contingencies - $90,000)

(J) Additional funds for DGS 417-15

217,000

(K) Renovation of two dormitories

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(L) Construction of a new dormitory

4,750,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $750,000)

(M) Additional boiler

900,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $150,000)

(N) 28,000 sq. ft. addition to Building #3 for vocational-technical training

646,000

(Base Project Allocation - $538,000)

(Design and Contingencies - $108,000)

(v) Pennsylvania State University

(A) University Park

(I) Construction of addition to the east wing of Pattee Library

19,800,000

(Base Project Allocation - $16,500,000)

(Design and Contingencies - $3,300,000)

(II) Construction of new research center

17,700,000

(Base Project Allocation - $14,750,000)

(Design and Contingencies - $2,950,000)

(III) Removal of asbestos from Eisenhower Auditorium

4,500,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $750,000)

(IV) Construction of a new general purpose classroom

5,000,000

(Base Project Allocation - $4,167,000)

(Design and Contingencies - $833,000)

(V) Renovation of storm water management system

3,200,000

(Base Project Allocation - $2,667,000)

(Design and Contingencies - $533,000)

(VI) ((VI) repealed Oct. 10, 1997, P.L.392, No.47)

(VII) Improvements and additions to central energy plant and distribution systems (Hershey Medical Center)

12,000,000

(Base Project Allocation - $12,000,000)

(VIII) Construction of a convocation center in State College

28,800,000

(Base Project Allocation - $24,000,000)

(Design and Contingencies - $4,800,000)

(IX) Addition to DGS 800-194 for construction of agricultural science and industry building

5,000,000

(Base Project Allocation - $5,000,000)

(X) ((X) deleted by amendment July 11, 1989, P.L.320, No.54)

(XI) ((XI) deleted by amendment July 11, 1989, P.L.320, No.54)

(XII) ((XII) deleted by amendment July 11, 1989, P.L.320, No.54)

(XIII) ((XIII) deleted by amendment July 11, 1989, P.L.320, No.54)

(XIV) ((XIV) deleted by amendment July 11, 1989, P.L.320, No.54)

(XV) ((XV) deleted by amendment July 11, 1989, P.L.320, No.54)

(XVI) ((XVI) deleted by amendment July 11, 1989, P.L.320, No.54)

(B) Altoona Campus

(I) Electrical distribution system

1,600,000

(Base Project Allocation - $1,600,000)

(II) ((II) deleted by amendment July 11, 1989, P.L.320, No.54)

(C) Beaver Campus

(I) Construction of a new learning center

2,850,000

(Base Project Allocation - $2,850,000)

(D) Berks Campus

(I) Acquisition of land and development of an agricultural instruction center

5,500,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $1,000,000)

(E) Capital College

(I) Electrical distribution system

3,500,000

(Base Project Allocation - $3,500,000)

(II) Installation of distribution and heating systems for various campus buildings

1,367,000

(Base Project Allocation - $1,139,000)

(Design and Contingencies - $228,000)

(F) Delaware County Campus

(I) Construction of classroom building

4,000,000

(Base Project Allocation - $4,000,000)

(G) Fayette Campus

(I) Construction of a multipurpose technological-cultural "Southwest Institute" to support regional socioeconomic development

4,000,000

(Base Project Allocation - $3,350,000)

(Design and Contingencies - $650,000)

(II) Construction of an agricultural sciences classroom/laboratory building to support new programming efforts

2,850,000

(Base Project Allocation - $2,375,000)

(Design and Contingencies - $475,000)

(III) Replace HVAC library building

300,000

(Base Project Allocation - $300,000)

(H) New Kensington Campus

(I) Construction of a science and technology center

1,650,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $150,000)

(II) Addition to Academic Building

1,650,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $150,000)

(I) Ogontz Campus - Renovations of Sutherland and Lares Buildings

4,500,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $750,000)

(J) Schuylkill Campus - Construction of a new library

1,600,000

(Base Project Allocation - $1,333,000)

(Design and Contingencies - $267,000)

(K) Shenango Campus - Construction of student activities and classroom complex

4,000,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $500,000)

(L) Wilkes-Barre Campus - Construction of Technology Center

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(M) Projects covering all branches

(I) PCB electrical system project

3,100,000

(Base Project Allocation - $2,583,000)

(Design and Contingencies - $517,000)

(II) Storm water management systems - Phase I

4,300,000

(Base Project Allocation - $4,300,000)

(N) Erie Campus - Construction of multipurpose facility for student activities

10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(vi) University of Pittsburgh

(A) Main Campus

(I) Acquisition and renovation of the Bellefield Annex

12,000,000

(Base Project Allocation - $10,000,000)

(Design and Contingencies - $2,000,000)

(II) Renovation and addition to Alumni Hall and chemistry building

13,000,000

(Base Project Allocation - $10,833,000)

(Design and Contingencies - $2,167,000)

(III) Renovation of the Trees Pool and Gymnasium Complex

5,000,000

(Base Project Allocation - $4,167,000)

(Design and Contingencies - $833,000)

(IV) Phase II, multipurpose building

12,800,000

(Base Project Allocation - $10,667,000)

(Design and Contingencies - $2,133,000)

(V) Construction of addition to Victoria Hall

7,200,000

(Base Project Allocation - $7,200,000)

(VI) Replacement of the steam distribution system - Phase II

2,000,000

(Base Project Allocation - $2,000,000)

(VII) Acquisition, construction and renovation of faculty offices and conference space for Pediatric Department of Medical School

16,800,000

(Base Project Allocation - $14,000,000)

(Design and Contingencies - $2,800,000)

(VIII) Construction of a convocation and fieldhouse complex

30,000,000

(Base Project Allocation - $25,000,000)

(Design and Contingencies - $5,000,000)

(IX) Additional funds for DGS1103-32, Salk Hall and Dental Clinic renovation

4,900,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $400,000)

(B) Bradford Campus

(I) Renovations to Swartz Hall DGS 1103-A, Fisher Hall DGS 1103-20, and common facilities building DGS 1103-30

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(II) Moveable equipment for library administration building

150,000

(Base Project Allocation - $130,000)

(Design and Contingencies - $20,000)

(C) Greensburg Campus

(I) Construction of library/administration building

6,600,000

(Base Project Allocation - $5,200,000)

(Design and Contingencies - $1,400,000)

(D) Johnstown Campus

(I) Construction of a new boiler with multifuel capacity

4,500,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $750,000)

(II) Renovation and addition to student union

2,226,000

(Base Project Allocation - $2,226,000)

(III) Construction of an administration building

7,000,000

(Base Project Allocation - $7,000,000)

(E) Titusville Campus

(I) Construction of a new science center

10,625,000

(Base Project Allocation - $8,500,000)

(Design and Contingencies - $2,125,000)

(vii) Temple University

(A) Main Campus

(I) Kardon Building Academic Center - that portion of total project consisting of replacement of elevators and mechanical and electrical systems, exterior repairs as required, and interior renovations of four floors as required for academic uses

21,600,000

(Base Project Allocation - $18,000,000)

(Design and Contingencies - $3,600,000)

(B) Rehabilitation, recreation and convocation center

33,600,000

(Base Project Allocation - $28,000,000)

(Design and Contingencies - $5,600,000)

(C) Atlantic Building on Science and Technology Campus

7,200,000

(Base Project Allocation - $6,000,000)

(Design and Contingencies - $1,200,000)

(D) Fire and safety renovations to comply with High Rise Fire Code and other standards, including installation of sprinkler, fire detection and alarm systems and associated facilities, to DGS Project Nos. 1104-03, 1104-05, 1104-08, 1104-12, 1104-13, 1104-16, 1104-17, 1104-21, 1104-22, 1104-24 and 1104-30

19,740,000

(Base Project Allocation - $16,450,000)

(Design and Contingencies - $3,290,000)

(E) Acquisition and renovation of Seltzer Hall

7,200,000

(Base Project Allocation - acquisition - $3,000,000)

(Base Project Allocation - renovation - $3,000,000)

(Design and Contingencies - $1,200,000)

(F) Classroom and laboratory building

14,400,000

(Base Project Allocation - $12,000,000)

(Design and Contingencies - $2,400,000)

(G) Additional funds for Dental School DGS 1104-32 - Phase II - including retransfer of $1,100,000 to DGS 1104-34

2,000,000

((G) added July 11, 1989, P.L.320, No.54)

(viii) Butler County Community College

(A) For the maintenance of heating and ventilation for the library and applied science building

350,000

(Base Project Allocation - $350,000)

(ix) Lehigh University

(A) Renovation and rehabilitation for Homer Research Facility

3,000,000

(Base Project Allocation - $3,000,000)

(x) Philadelphia College of Textiles and Science

(A) Building of new library

7,200,000

(Base Project Allocation - $6,000,000)

(Design and Contingencies - $1,200,000)

(xi) Williamson Free School of Mechanical Trades

(A) Renovation of student infirmary

136,000

(Base Project Allocation - $114,000)

(Design and Contingencies - $22,000)

(4) Emergency Management Agency

$3,056,000

(i) Lackawanna County

(A) Construction of a volunteer firefighter training facility in Abington Township

180,000

(Base Project Allocation - $180,000)

(ii) Mifflin County

(A) Centralization of emergency communications center

500,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $50,000)

(iii) State Fire Academy

(A) Residence hall

2,376,000

(Base Project Allocation - $1,980,000)

(Design and Contingencies - $396,000)

(5) Department of Environmental Resources

$457,612,000

(Amount amended July 11, 1989, P.L.320, No.54)

(i) Bald Eagle State Park

(A) Resurface roads and boat launch

491,000

(Base Project Allocation - $409,000)

(Design and Contingencies - $82,000)

(B) Water and sewer improvements and addition to Park Office

220,000

(Base Project Allocation - $183,000)

(Design and Contingencies - $37,000)

(C) Installation of lights, restroom rehabilitation and construction, dust control

126,000

(Base Project Allocation - $105,000)

(Design and Contingencies - $21,000)

(D) Marina and dock repairs and replacement

2,568,000

(Base Project Allocation - $2,140,000)

(Design and Contingencies - $428,000)

(E) Remove railroad grade, playground equipment, air conditioning for park office, curbing at beach area, overhead doors for maintenance building, rebuild road

167,000

(Base Project Allocation - $139,000)

(Design and Contingencies - $28,000)

(F) Park superintendent residence

153,000

(Base Project Allocation - $127,000)

(Design and Contingencies - $26,000)

(ii) Bendigo State Park

(A) Rehabilitate latrines and bathhouse

312,000

(Base Project Allocation - $260,000)

(Design and Contingencies - $52,000)

(B) Pool supplies, concession building

128,000

(Base Project Allocation - $106,000)

(Design and Contingencies - $22,000)

(C) Rehabilitate roads and parking lots, repairs to office, residence and maintenance building, dam and bridge repair

143,000

(Base Project Allocation - $119,000)

(Design and Contingencies - $24,000)

(iii) Black Moshannon State Park

(A) Renovate washhouses, changehouses and lifeguard shack

330,000

(Base Project Allocation - $275,000)

(Design and Contingencies - $55,000)

(B) Road and parking facility repair and construction

440,000

(Base Project Allocation - $367,000)

(Design and Contingencies - $73,000)

(C) Water and sewer construction and repair

228,000

(Base Project Allocation - $190,000)

(Design and Contingencies - $38,000)

(D) Windows, trail renovation, heating system and electrical work, construct boat docks and storage shed

122,000

(Base Project Allocation - $101,000)

(Design and Contingencies - $21,000)

(E) Construct contact station and comfort station, roof replacements

219,000

(Base Project Allocation - $182,000)

(Design and Contingencies - $37,000)

(iv) Blue Knob State Park

(A) Improve roads, dining hall, latrines, basketball courts

1,400,000

(Base Project Allocation - $1,400,000)

(v) Chapman State Park

(A) Replace park office and maintenance building

288,000

(Base Project Allocation - $240,000)

(Design and Contingencies - $48,000)

(B) Road and parking lot paving and repair

426,000

(Base Project Allocation - $355,000)

(Design and Contingencies - $71,000)

(C) Water and sewer repair and replacement

228,000

(Base Project Allocation - $190,000)

(Design and Contingencies - $38,000)

(D) Desilt lake, dam maintenance, beach and dock repair

402,000

(Base Project Allocation - $335,000)

(Design and Contingencies - $67,000)

(E) Trail rehabilitation, heating system, playground equipment and renovation, construct ice skating lagoon, replace roof and partition

154,000

(Base Project Allocation - $128,000)

(Design and Contingencies - $26,000)

(vi) Cherry Springs State Park

(A) Construct shed and comfort station, repair road, extend water system

119,000

(Base Project Allocation - $99,000)

(Design and Contingencies - $20,000)

(vii) Colton Point State Park

(A) Repair road, replace latrine, replace water line, construct new chlorinator building

563,000

(Base Project Allocation - $469,000)

(Design and Contingencies - $94,000)

(viii) Denton Hill State Park

(A) Resurface road, energy conservation, re-roof buildings

92,000

(Base Project Allocation - $76,000)

(Design and Contingencies - $16,000)

(ix) Elk State Park

(A) Rehabilitation of parking lots, dock area and camping area

190,000

(Base Project Allocation - $158,000)

(Design and Contingencies - $32,000)

(x) Hills Creek State Park

(A) Dam rehabilitation

1,205,000

(Base Project Allocation - $1,004,000)

(Design and Contingencies - $201,000)

(B) Water, bathhouse, sewage projects

137,000

(Base Project Allocation - $114,000)

(Design and Contingencies - $23,000)

(C) Repair of roads, heating system, bathhouses, phone system, building maintenance, replace sewage plant equipment

268,000

(Base Project Allocation - $223,000)

(Design and Contingencies - $45,000)

(xi) Hyner Run State Park

(A) Pool repairs

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(B) Restroom repairs

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(C) Road, building, campground, picnic area repairs, stream improvements, playground and telephone equipment

293,000

(Base Project Allocation - $244,000)

(Design and Contingencies - $49,000)

(xii) Hyner View State Park

(A) Repair of road, parking area, pavilion, wall and toilets

212,000

(Base Project Allocation - $176,000)

(Design and Contingencies - $36,000)

(xiii) Kettle Creek State Park

(A) Road rehabilitation

132,000

(Base Project Allocation - $110,000)

(Design and Contingencies - $22,000)

(B) Rehabilitation of nature center, renovate toilets, redesign maintenance building, boat dock and mooring area

172,000

(Base Project Allocation - $143,000)

(Design and Contingencies - $29,000)

(xiv) Kinzua Bridge State Park

(A) New campground and facilities

660,000

(Base Project Allocation - $550,000)

(Design and Contingencies - $110,000)

(B) Improve overlook area and parking lot, replace bridge planks, concession stand, new maintenance building

218,000

(Base Project Allocation - $181,000)

(Design and Contingencies - $37,000)

(xv) Leonard Harrison State Park

(A) Latrine replacement

540,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $90,000)

(B) Renovate main overlook walkway

198,000

(Base Project Allocation - $165,000)

(Design and Contingencies - $33,000)

(C) Replace furnace, flagpole base and sidewalk; rehabilitation of concession stand; visitors center and trail; repave parking lot; construct pavilion and new maintenance building

173,000

(Base Project Allocation - $144,000)

(Design and Contingencies - $29,000)

(xvi) Little Pine State Park

(A) Water and sewer upgrade

255,000

(Base Project Allocation - $212,000)

(Design and Contingencies - $43,000)

(B) Desilt dam

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(C) Renovation of office, campground pads, group tenting area and foot bridge in campground

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(D) Repair buildings, roads, drainage ditches; purchase front end loader; new beach sand; riprap on dam; renovate picnic area, shooting range, restrooms, dam, visitors center, play area, concession area, stream, beach, boat mooring areas, gates; barge to work with flood debris

714,000

(Base Project Allocation - $595,000)

(Design and Contingencies - $119,000)

(xvii) Lyman Run State Park

(A) Rehabilitation of dam

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(B) New garage and storage building; repave roads

188,000

(Base Project Allocation - $156,000)

(Design and Contingencies - $32,000)

(C) Comfort stations; changehouses; concession; camping area rehabilitation

174,000

(Base Project Allocation - $145,000)

(Design and Contingencies - $29,000)

(xviii) McCall's Dam State Park

(A) Rehabilitation of latrine and group tent camping area

32,000

(Base Project Allocation - $26,000)

(Design and Contingencies - $6,000)

(xix) Mt. Pisgah State Park

(A) Road, dam and parking lot repairs; renovate boat dock

126,000

(Base Project Allocation - $105,000)

(Design and Contingencies - $21,000)

(B) Residence, pool, pumphouse repair; burglar alarms, landscaping; water and sewer repairs, building repairs; road work; equipment purchases; replace gas and oil tanks; trail repair

314,000

(Base Project Allocation - $261,000)

(Design and Contingencies - $53,000)

(xx) Ole Bull State Park

(A) Renovate trails, toilets, buildings, water system; re-roof beach house; rehabilitate maintenance building; electrical work

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(B) Resurface roads

156,000

(Base Project Allocation - $130,000)

(Design and Contingencies - $26,000)

(xxi) Parker Dam State Park

(A) Rehabilitate roads

473,000

(Base Project Allocation - $394,000)

(Design and Contingencies - $79,000)

(B) Water, sewer and dam projects

123,000

(Base Project Allocation - $102,000)

(Design and Contingencies - $21,000)

(C) Rehabilitation of cabins, maintenance building, nature center, pavilion and playground; campsite electrical hookups; campsite markers

390,000

(Base Project Allocation - $325,000)

(Design and Contingencies - $65,000)

(xxii) Patterson State Park

(A) Drill new well; resurface road; replace latrine; re-roof pavilions

53,000

(Base Project Allocation - $44,000)

(Design and Contingencies - $9,000)

(xxiii) Poe Paddy State Park

(A) Renovate campgrounds, latrines, trails, drinking water system; replace fire rings, grills, picnic tables and garbage cans

162,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $27,000)

(xxiv) Poe Valley State Park

(A) Campground renovation

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(B) Beachhouse renovation

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(C) Water and sewer projects; comfort station replacement

356,000

(Base Project Allocation - $296,000)

(Design and Contingencies - $60,000)

(D) Renovation of concession stand, nature center, park entrance, shale pit, fuel dispensing system, storage building, trail system, hand pump; replace picnic tables, garbage cans, grills, fire rings; pit vault cleaning; roof work; rehabilitation of office, maintenance area, day-use area; landscaping; dead limb removal; concession boat docking facility; survey boundary

562,000

(Base Project Allocation - $468,000)

(Design and Contingencies - $94,000)

(E) Sand beach renovation; park entrance bridge renovation; resurface roads; dam control; boat mooring

135,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $23,000)

(xxv) Prouty Place State Park

(A) Construct comfort station; regravel dirt road

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(xxvi) R. B. Winter State Park

(A) Restroom and bathhouse repair

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(B) Road, bridge and parking lot repairs

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(C) Rehabilitation of old maintenance building, visitors center, camping area restroom, playground and campground; replace beach sand, garbage cans, picnic tables, grills, charcoal dumps; landscaping; install fence of maintenance yard

290,000

(Base Project Allocation - $241,000)

(Design and Contingencies - $49,000)

(xxvii) Ravensburg State Park

(A) Install fence, signs and new entrance; replace picnic tables; rehabilitation of restrooms; restroom and shower in campground

372,000

(Base Project Allocation - $310,000)

(Design and Contingencies - $62,000)

(xxviii) Reed's Gap State Park

(A) Water and sewer projects

237,000

(Base Project Allocation - $197,000)

(Design and Contingencies - $40,000)

(B) Road and bridge repair

213,000

(Base Project Allocation - $177,000)

(Design and Contingencies - $36,000)

(C) Replace residence; renovate campground, maintenance building, fuel dispensing system, trails and park buildings; replace garbage cans, fire rings, grills, picnic tables; boundary survey

431,000

(Base Project Allocation - $359,000)

(Design and Contingencies - $72,000)

(xxix) S. B. Elliott State Park

(A) Rehabilitation of campground restroom; campsite markers; campsite electric hookup

32,000

(Base Project Allocation - $26,000)

(Design and Contingencies - $6,000)

(xxx) Sand Bridge State Park

(A) Building rehabilitation

27,000

(Base Project Allocation - $22,000)

(Design and Contingencies - $5,000)

(xxxi) Shikellamy State Park

(A) Replace docks

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(B) Road repairs; recondition roof; riprap; sewage system extension; rehabilitation of restroom; recaulk bulkheads; replace windows

246,000

(Base Project Allocation - $205,000)

(Design and Contingencies - $41,000)

(xxxii) Sinnemahoning State Park

(A) Repair service gate, conduit and spillway

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(B) Trash boom replacement

581,000

(Base Project Allocation - $484,000)

(Design and Contingencies - $97,000)

(C) Road and bridge repairs

322,000

(Base Project Allocation - $268,000)

(Design and Contingencies - $54,000)

(D) Desilt lake

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(E) Water and sewer projects

306,000

(Base Project Allocation - $255,000)

(Design and Contingencies - $51,000)

(F) Rehabilitation of trails, water supply, beach and emergency gate wells; replace roofs; heating systems, cable barrier, residence, park office, guide rail; debris cleanup; fuel storage tank; stream stabilization; vegetation control; security fence; beach sand; amphitheater renovations; play equipment; construct nature center, storage area, comfort station and two pavilions; carpenter shop addition

1,341,000

(Base Project Allocation - $1,117,000)

(Design and Contingencies - $224,000)

(xxxiii) Sizerville State Park

(A) Road repairs

522,000

(Base Project Allocation - $435,000)

(Design and Contingencies - $87,000)

(B) Water and sewer projects

404,000

(Base Project Allocation - $336,000)

(Design and Contingencies - $68,000)

(C) Pool repairs

129,000

(Base Project Allocation - $107,000)

(Design and Contingencies - $22,000)

(D) Rehabilitation of electric system, amphitheater, grills, footbridges, baskets, park office, maintenance building; replace barn fencing, heating oil tanks, signs, waterlines, walkways, grills, benches, play equipment, heating systems, gutters, pavilion supports; enlarge campground; paint and roof all buildings; install two footbridges; enlarge maintenance building and kitchen of residence; resurface driveways and garage area

616,000

(Base Project Allocation - $513,000)

(Design and Contingencies - $103,000)

(xxxiv) Region II Central Office

(A) Cabin maintenance

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(xxxv) Clear Creek State Park

(A) Repair heating systems; repair roofing; repair vaults; repair wells; repair cabins, install siding on park office; fence reservoir; repair toilets; repair parking lot and roads; prune trees; desilt lake

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(xxxvi) Cook Forest State Park

(A) Paint swimming pool; repair cabins; re-roof and repair restrooms, Toms Run Dam; repair trails; repair sawmill and water tank; replace doors, repair roads; motor protection; install drainage; landscape river cabs; install fencing; rehabilitation of long shed; replace blower filter

312,000

(Base Project Allocation - $260,000)

(Design and Contingencies - $52,000)

(B) Pave roads

569,000

(Base Project Allocation - $474,000)

(Design and Contingencies - $95,000)

(C) Rehabilitation of Firetower Road

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(xxxvii) Hillman State Park

(A) Fire damage pavilion

36,000

(Base Project Allocation - $30,000)

(Design and Contingencies - $6,000)

(xxxviii) Keystone State Park

(A) Drawdown channel; beach repair water tower; repair and install toilets

396,000

(Base Project Allocation - $330,000)

(Design and Contingencies - $66,000)

(B) Parking lots

496,000

(Base Project Allocation - $413,000)

(Design and Contingencies - $83,000)

(xxxix) Kooser State Park

(A) Rehabilitation of main roads

212,000

(Base Project Allocation - $176,000)

(Design and Contingencies - $36,000)

(B) Rehabilitation of buildings and cabins; smoke detectors; storm windows

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(C) Mighty Oak Pavilion; fire rings; master key locks; tree removal; repair bridges; dam trash rack; extend water line; rehabilitation of latrine area; Van Dyke toilet; drinking fountains

166,000

(Base Project Allocation - $138,000)

(Design and Contingencies - $28,000)

(xl) Laurel Hill State Park

(A) Replace water lines

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Pave roads; expand and repair parking areas; rehabilitation of bath area

1,119,000

(Base Project Allocation - $932,000)

(Design and Contingencies - $187,000)

(C) Landscape beach area

210,000

(Base Project Allocation - $175,000)

(Design and Contingencies - $35,000)

(D) Camp lease; replace locks; replace fire extinguishers; desilt dams; install electric; repair woodshop equipment; re-roof buildings; install siding and insulation on buildings; repair buildings; install fire rings; install ball fields; repair sewage treatment plant; replace road construction; trail and bridge repair; stain buildings; post and gate repairs; dam boat launch area; convert camp office; sign replacement; park bound maintenance

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(xli) Laurel Ridge State Park

(A) Repair trails, trail shelters, chimney; park boundary maintenance; windows and insulation in residence; locks-master keying

210,000

(Base Project Allocation - $175,000)

(Design and Contingencies - $35,000)

(xlii) Linn Run State Park

(A) Road and parking lot repair; pit rehabilitation

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(B) Re-roof cabins; trail repair; rehabilitation of playground; rehabilitation maintenance, building and pavilion; replace wiring, windows and fuel tank

137,000

(Base Project Allocation - $114,000)

(Design and Contingencies - $23,000)

(xliii) M. K. Goddard State Park

(A) Road, sidewalk and trail repair

135,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $23,000)

(B) Launch and dock repair; marina tree work; lift station repairs, toilet partitions; well repair; office repair; replace floatation; remove electric service; boundary line maintenance; sign repair; lights; tower repair; restaurant fan

207,000

(Base Project Allocation - $172,000)

(Design and Contingencies - $35,000)

(xliv) McConnell's Mill State Park

(A) Repair dam, roads, trail; repair residence; replace comfort station

77,000

(Base Project Allocation - $64,000)

(Design and Contingencies - $13,000)

(xlv) Moraine State Park

(A) Road repair

125,000

(Base Project Allocation - $104,000)

(Design and Contingencies - $21,000)

(B) Rehabilitate sewage system, marina, beach changing building, boat launches residence; replace water main, furnace and restaurant roof

322,000

(Base Project Allocation - $268,000)

(Design and Contingencies - $54,000)

(xlvi) Ohiopyle State Park

(A) Construct restroom facilities

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(B) Bridge removal

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(C) Construct cabin colony

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(D) Construct group camping area

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(E) Repair office, construct restroom; construct pole barn; building maintenance; building repairs; park boundary work; radio replacement; rehabilitate water and sewer plant; electrical repairs; bridge repair

620,000

(Base Project Allocation - $516,000)

(Design and Contingencies - $104,000)

(F) Construct changing room facility

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(xlvii) Oil Creek State Park

(A) Route 8 entrance relocation

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(B) Bike trail repair and rehabilitation of bike rental building

377,000

(Base Project Allocation - $314,000)

(Design and Contingencies - $63,000)

(C) Cemetery rehabilitation, water system repair, gate repairs, storage building repair, vehicle repair, hiking trail rehabilitation, residence rehabilitation, park office addition, roof for maintenance building, electric service

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(xlviii) Point State Park

(A) Replace park benches and site maintenance

304,000

(Base Project Allocation - $253,000)

(Design and Contingencies - $51,000)

(B) Rehabilitate belgium block, rehabilitate walk; landscaping

156,000

(Base Project Allocation - $130,000)

(Design and Contingencies - $26,000)

(C) Lighting, lawn sprinkling system, fountain repairs

285,000

(Base Project Allocation - $237,000)

(Design and Contingencies - $48,000)

(xlix) Presque Isle State Park

(A) Road, parking lot and marina lift paving

342,000

(Base Project Allocation - $285,000)

(Design and Contingencies - $57,000)

(B) Rehabilitation of ferry slip

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Marina construction, highway line painting, resurfacing pier cart, pipe gates, fuel storage, screen park residence, dredging, marina gas dock, sign replacement toilets, ice rescue crosses

258,000

(Base Project Allocation - $215,000)

(Design and Contingencies - $43,000)

(l) Pymatuning State Park

(A) Pave and seal roads

1,744,000

(Base Project Allocation - $1,453,000)

(Design and Contingencies - $291,000)

(B) Rehabilitation of buildings, docks and storage buildings, toilet repair, tuttle drainage, dumpster pads, spillway fence, traffic sign replacement

203,000

(Base Project Allocation - $169,000)

(Design and Contingencies - $34,000)

(li) Raccoon Creek State Park

(A) Water and sewer, dam repairs

152,000

(Base Project Allocation - $126,000)

(Design and Contingencies - $26,000)

(B) Lodge roof, cabin repairs, dam repairs, trail repairs, park gates, beach house repairs, fence, lodge furnace

294,000

(Base Project Allocation - $245,000)

(Design and Contingencies - $49,000)

(lii) Region II Regional Office

(A) Motorized equipment, engineer, hydraulic lift, maintenance building heating system, office rehabilitation

221,000

(Base Project Allocation - $184,000)

(Design and Contingencies - $37,000)

(liii) Ryerson State Park

(A) Desilt lake

322,000

(Base Project Allocation - $268,000)

(Design and Contingencies - $54,000)

(B) Asbestos removal, pool repairs, rehabilitation of roofs, rehabilitation of playground, office addition, replace chimneys, road maintenance, trail drainage

228,000

(Base Project Allocation - $190,000)

(Design and Contingencies - $38,000)

(liv) Yellow Creek State Park

(A) Dam repair

135,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $23,000)

(B) Road rehabilitation, paving

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(C) Rehabilitation of maintenance building, rehabilitation of beachfront, lift station panel, electric motor repair, spillway repairs, replace boat docks, furnace replacement, boat launch rehabilitation; painting

146,000

(Base Project Allocation - $121,000)

(Design and Contingencies - $25,000)

(lv) Blue Knob State Park

(A) Reconstruct basketball courts, ball field; repair latrines; reconstruct campground/picnic play area and dining hall

183,000

(Base Project Allocation - $152,000)

(Design and Contingencies - $31,000)

(B) Rehabilitation of administration complex road system and other roads

299,000

(Base Project Allocation - $249,000)

(Design and Contingencies - $50,000)

(C) Open field management; repair park gates and kitchen equipment; insulate water heater; install water supply park pool/picnic area and run electric lines underground

112,000

(Base Project Allocation - $93,000)

(Design and Contingencies - $9,000)

(D) Rehabilitation of park facilities

1,080,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $180,000)

(lvi) Buchanan's Birthplace State Park

(A) Replace restroom

23,000

(Base Project Allocation - $19,000)

(Design and Contingencies - $4,000)

(lvii) Caledonia State Park

(A) Repair pool and facilities

242,000

(Base Project Allocation - $201,000)

(Design and Contingencies - $41,000)

(B) Pave, paint and repair roads and parking lots; rehabilitation of park facilities

645,000

(Base Project Allocation - $537,000)

(Design and Contingencies - $108,000)

(C) Restore and paint restrooms and sewer lines; replace water heaters; repair pool facilities; repair well sewage plant

303,000

(Base Project Allocation - $252,000)

(Design and Contingencies - $51,000)

(D) Construct ice skating rink; rehabilitation of trail system, play field, campground; and replace food concession building

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(E) Replace roofs; repair garage and amphitheater; install woodburner, furnace solar panels in residences; construct main gate; renovate office, group game area; expand storage facilities; paint buildings, bridges, gates, rails and fencing; install trails

273,000

(Base Project Allocation - $227,000)

(Design and Contingencies - $46,000)

(lviii) Canoe Creek State Park

(A) Replace maintenance building, lot curbs, warning markers, beach sand, siding on buildings and boat mooring walls; reseal walls; construct sidewalks; pave roads; rehabilitation of heating system

204,000

(Base Project Allocation - $170,000)

(Design and Contingencies - $34,000)

(B) Restore limestone kilns

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(lix) Codorus State Park

(A) Rehabilitation of docks

1,250,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $250,000)

(B) Pave roads and lots

114,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $19,000)

(C) Paint water tank; rehabilitation of roads, pool tanks and filters; replace pool showers; construct barn and pool storage; electric lines, and install furnace; cedar siding for office

311,000

(Base Project Allocation - $259,000)

(Design and Contingencies - $52,000)

(lx) Colonel Denning State Park

(A) Rehabilitation of roads, lots, kitchen; construct maintenance building

238,000

(Base Project Allocation - $198,000)

(Design and Contingencies - $40,000)

(lxi) Cowan's Gap State Park

(A) Rehabilitation of parking lots

251,000

(Base Project Allocation - $209,000)

(Design and Contingencies - $42,000)

(B) Desilt lake

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Park rehabilitation

1,281,000

(Base Project Allocation - $1,067,000)

(Design and Contingencies - $214,000)

(D) Rehabilitation of charcoal units, storage buildings, restrooms, sewage plants; repair and paint restrooms; eliminate erosion in group tent area; expand storage

156,000

(Base Project Allocation - $130,000)

(Design and Contingencies - $26,000)

(lxii) Gifford Pinchot State Park

(A) Construct maintenance storage area

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Dredge lake

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(C) Construct filter drying beds

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(D) Pave roads; construct latrines

226,000

(Base Project Allocation - $188,000)

(Design and Contingencies - $38,000)

(E) Replace windows, furnace, latrines; extend sewage system; rehabilitation of gas valve; expand handicap access

246,000

(Base Project Allocation - $205,000)

(Design and Contingencies - $41,000)

(lxiii) Greenwood Furnace State Park

(A) Picnic and camping facilities

1,080,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $180,000)

(B) Reconstruct furnace building

214,000

(Base Project Allocation - $178,000)

(Design and Contingencies - $36,000)

(C) Rehabilitation of park administration/support structures

1,080,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $180,000)

(D) Rehabilitation of washhouse interior; sewage system extension; replace drinking fountains

214,000

(Base Project Allocation - $178,000)

(Design and Contingencies - $36,000)

(E) Pave Roads

188,000

(Base Project Allocation - $156,000)

(Design and Contingencies - $32,000)

(F) Rehabilitation of camping area, pavilions and structures

147,000

(Base Project Allocation - $122,000)

(Design and Contingencies - $25,000)

(G) Rehabilitation of buildings; replace playgrounds; construct barn; shoreline erosion control; replace siding and roofs

212,000

(Base Project Allocation - $176,000)

(Design and Contingencies - $36,000)

(lxiv) Little Buffalo State Park

(A) Repair water system; reroof bridge; replace fence, new carpet and wood burners; repair pool; enlarge visitors' center; replace grills; paving; painting water and sewer repairs; replace guide rail; repair boat docks

165,000

(Base Project Allocation - $137,000)

(Design and Contingencies - $28,000)

(B) Construct overnight facilities

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(lxv) Mont Alto State Park

(A) Paint grills; stain foot bridges and bank pavilion; replace playground equipment; replace foot bridge; water and sewer repairs; landscaping; paint pavilion; rehabilitation of park facilities

182,000

(Base Project Allocation - $151,000)

(Design and Contingencies - $31,000)

(lxvi) Penn Roosevelt State Park

(A) Rehabilitation of monument, latrines, camp roads, pavilion, dam, day use and camp area; replace water system; install gates

294,000

(Base Project Allocation - $245,000)

(Design and Contingencies - $49,000)

(B) Dam and picnic facilities

720,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $120,000)

(lxvii) Pine Grove Furnace State Park

(A) Construction of water and sewer systems

2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(B) Dredge lake

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(C) Rehabilitation of camp store building

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(D) Develop ice house, day-use area

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(E) Repair mansion house; extend maintenance building; develop visitor center; construct pavilion; pole barn and fence; revamp buildings and gate key system; paint buildings; install storm windows

255,000

(Base Project Allocation - $212,000)

(Design and Contingencies - $43,000)

(F) Pave roads and parking lots; pave bicycle trail

123,000

(Base Project Allocation - $102,000)

(Design and Contingencies - $21,000)

(G) Water and sewer projects

147,000

(Base Project Allocation - $122,000)

(Design and Contingencies - $25,000)

(lxviii) Prince Gallitzin State Park

(A) Improve and renovate marina decks

881,000

(Base Project Allocation - $734,000)

(Design and Contingencies - $147,000)

(B) Reconstruct Beaver Valley marina

480,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $80,000)

(C) Reconstruct washhouse

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(D) Rehabilitate contact station

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(E) Addition to maintenance shop

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(F) Improve sewage treatment plant

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(G) Stabilize shoreline

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(H) Major rehabilitation of marina docks

480,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $80,000)

(I) Road, trail and parking lot repair

177,000

(Base Project Allocation - $147,000)

(Design and Contingencies - $30,000)

(J) Stabilize lake shoreline; dredge and dam; replace siding and paint buildings; replace docks; replace beach sand; replace playground equipment; replace buoy floats

112,000

(Base Project Allocation - $93,000)

(Design and Contingencies - $19,000)

(K) Water and sewer projects

194,000

(Base Project Allocation - $161,000)

(Design and Contingencies - $33,000)

(L) Seal floors; replace lights; woodstove and fireplace insert; storm windows; replace locks; enclose office entrance; replace campsite markers; solar chamber; winterize main shop; rehabilitate amphitheater; replace furnace; replace fire rings and grills; rehabilitate fence; rehabilitate visitors center, repair roof; construct pedestrian walkway

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(lxix) Region III Regional Office

(A) Paint office and two residences; office and equipment repairs

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(lxx) Shawnee State Park

(A) Replace latrine; extend sewage

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(B) Construct new office

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(C) Replace pit latrines; water and sewage projects

224,000

(Base Project Allocation - $186,000)

(Design and Contingencies - $38,000)

(D) Rehabilitate boat rental and dock facilities

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(E) Repair dam and roads; replace restroom partition; replace beach sand and beach drainage; paint building; furnace for residence

214,000

(Base Project Allocation - $178,000)

(Design and Contingencies - $36,000)

(lxxi) Susquehannock State Park

(A) Reconstruct Landis House

162,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $27,000)

(lxxii) Trough Creek State Park

(A) Paving

410,000

(Base Project Allocation - $341,000)

(Design and Contingencies - $69,000)

(B) Construct three restrooms

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Rehabilitate iron furnace; restore railroad bridge; addition to maintenance building; replace playground equipment; re-roof residence

155,000

(Base Project Allocation - $129,000)

(Design and Contingencies - $26,000)

(D) Rehabilitate guardrail posts; install walls; replace restrooms; rehabilitate water system; replace windows; tractor shed addition, construct picnic pavilion

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(lxxiii) Warrior's Path State Park

100,000

(A) Replace culvert and playground equipment, rehabilitation of water system, construct picnic latrine, paving

100,000

(Base Project Allocation - $83,000)

(Design and Contingencies - $17,000)

(lxxiv) Whipple Dam State Park

(A) Lake, picnic area

840,000

(Base Project Allocation - $700,000)

(Design and Contingencies - $140,000)

(B) Desilt lake

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(C) Construct water system

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(D) Rehabilitation of day use area

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(E) Replace gate, parking lot wall, dressing stockade, rehabilitation of picnic areas, pavilions, refreshment building, ranger station cabin, bridge and latrines

263,000

(Base Project Allocation - $219,000)

(Design and Contingencies - $44,000)

(lxxv) Beltzville State Park

(A) Parking lot repair, bulletin board replacement, superintendent's residence repair, repair storage barn, repair sewer line, replace comfort station

219,000

(Base Project Allocation - $182,000)

(Design and Contingencies - $37,000)

(lxxvi) Big Pocono State Park

(A) Repair picnic areas, repair trails, repair and re-roof buildings, replace drain pipes; install guardrails and remove vegetation on scenic drive, rehabilitation of bus turnaround; boundary work

164,000

(Base Project Allocation - $136,000)

(Design and Contingencies - $28,000)

(lxxvii) Evansburg State Park

(A) Repair buildings

348,000

(Base Project Allocation - $290,000)

(Design and Contingencies - $58,000)

(B) Repair storage buildings, paint residence; demolish building, remove hazards, repair softball fields, repair visitors center, replace bridge, survey boundary, repair road, replace picnic facilities

209,000

(Base Project Allocation - $174,000)

(Design and Contingencies - $35,000)

(C) Paint comfort stations and office, repair water and waste systems, repair water tower

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(lxxviii) Fort Washington State Park

(A) Repair park building and pave roads

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(lxxix) Frances Slocum State Park

(A) Pool repairs, kitchen repairs, dam repairs, comfort station repair, pave roads and parking lots, repair maintenance building and office, repair sewage line and replace tank cover, repair signs and walkways

209,000

(Base Project Allocation - $174,000)

(Design and Contingencies - $35,000)

(lxxx) French Creek State Park

(A) Repair bathhouse, latrines and shower buildings

274,000

(Base Project Allocation - $228,000)

(Design and Contingencies - $46,000)

(B) Repair roads and parking lots

323,000

(Base Project Allocation - $269,000)

(Design and Contingencies - $54,000)

(C) Repair spillway, repair docks and repair boat mooring

312,000

(Base Project Allocation - $291,000)

(Design and Contingencies - $21,000)

((C) amended July 11, 1989, P.L.320, No.54)

(D) Build fencing, vehicle storage building, rebuild lodge, replace fire ring, repair and replace storage buildings, repair residences, campground renovations, repair cabin, boundary survey, safety rail, picnic area, lumber, gates, construct pavilions, repair quarry, repair playground and replace equipment, construct chapel and amphitheater, repair swimming pool

764,000

(Base Project Allocation - $636,000)

(Design and Contingencies - $128,000)

(lxxxi) Gouldsboro State Park

(A) Repair picnic areas and hiking trails, repair beach and swimming areas, repair roads and parking lot, repair various buildings, repair boat launch and watercraft rental facilities

162,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $27,000)

(lxxxii) Hickory Run State Park

(A) Repair roads and parking lots

344,000

(Base Project Allocation - $286,000)

(Design and Contingencies - $58,000)

(B) Repair water treatment units, repair dams and drawdown gates, repair and paint showers, bathhouses and latrines, repair sewer lines, replace swimming pool filter, electric service to various buildings, repair campsites and picnic areas, paint maintenance building, repair workshop, repair trail, clear boundary lines

196,000

(Base Project Allocation - $163,000)

(Design and Contingencies - $33,000)

(lxxxiii) Lehigh Gorge State Park

(A) Historic hotel repair

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Repair main access road and install parking area

142,000

(Base Project Allocation - $118,000)

(Design and Contingencies - $24,000)

(C) Repair bridge, improve trail, repair/replace gates, repair water system

173,000

(Base Project Allocation - $144,000)

(Design and Contingencies - $29,000)

(lxxxiv) Locust Lake State Park

(A) Resurface road, repair washhouse, pave boat launch area, renovate playground equipment

146,000

(Base Project Allocation - $121,000)

(Design and Contingencies - $25,000)

(lxxxv) Marsh Creek State Park

(A) Repair and replace roofing, repair park office, install fire rings and grates, brushout aerial electric lines, repair swimming pool, install playground area

176,000

(Base Project Allocation - $146,000)

(Design and Contingencies - $30,000)

(lxxxvi) Memorial Lake State Park

(A) Pave parking lots, repair dam, construct deck and latrine, construct addition to maintenance building

208,000

(Base Project Allocation - $173,000)

(Design and Contingencies - $35,000)

(lxxxvii) Neshaminy State Park

(A) Pave parking areas, walkways and roads

270,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $45,000)

(B) Repair swimming pool, repair shower and restroom plumbing, repair roofing, purchase schramm for bubbler, electrical maintenance, install fire hydrants and curb stops, repair barn and comfort station

183,000

(Base Project Allocation - $152,000)

(Design and Contingencies - $31,000)

(C) Re-deck full pier, replace gangways on piers

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(lxxxviii) Nockamixon State Park

(A) Repair parking lot lines, road and parking lot repair

213,000

(Base Project Allocation - $177,000)

(Design and Contingencies - $36,000)

(B) Repair water tower, repair sewage system, repair sewage line infiltration, install skylights in comfort stations

160,000

(Base Project Allocation - $133,000)

(Design and Contingencies - $27,000)

(C) Replace floatation on marina docks

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(D) Repair bulletin boards, repair pool, repair decking and siding, install gutters and drainage system, replace water lines, replace dead shrubbery and trees, demolish silo and stone walls, repair boundaries, pave bicycle trail, repair dam fence, replace locks throughout park, install chlorine gas detector

164,000

(Base Project Allocation - $136,000)

(Design and Contingencies - $28,000)

(E) Control shoreline erosion

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(lxxxix) Promised Land State Park

(A) Road and parking lot rehabilitation, campground rehabilitation

143,000

(Base Project Allocation - $119,000)

(Design and Contingencies - $24,000)

(B) Playground equipment rehabilitation, boat mooring, rehabilitation of picnic area, hiking trails, family cabins, lodge, landscaping, paint water tower, rehabilitation of dump station tower

148,000

(Base Project Allocation - $123,000)

(Design and Contingencies - $25,000)

(xc) Ralph Stover State Park

(A) Footbridge, winterize cabins

14,000

(Base Project Allocation - $11,000)

(Design and Contingencies - $3,000)

(xci) Region IV Regional Office

(A) Replace boiler, porch steps, repair equipment, rehabilitation of boathouse, emergency contingency funds, vinyl siding

81,000

(Base Project Allocation - $67,000)

(Design and Contingencies - $14,000)

(xcii) Ricketts Glen State Park

(A) Paving and resurface roads, water tank fall prevention system

135,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $23,000)

(xciii) Ridley Creek State Park

(A) Rehabilitation of historical structures

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(B) Boundary survey

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Rehabilitation of electric and water at residence, rehabilitation comfort station, stone gutter, bridle trail and park office electric, gate replacement, park office heating system repair and pave parking lots

136,000

(Base Project Allocation - $113,000)

(Design and Contingencies - $23,000)

(xciv) Roosevelt State Park

(A) Masonry repair, pave maintenance area, aqueduct and bridge repair, re-roof buildings, towpath erosion control, parking lot drainage and modify heating system

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(B) Bridge repairs

455,000

(Base Project Allocation - $379,000)

(Design and Contingencies - $76,000)

(xcv) Swatara State Park

(A) Furnace replacement, sewage system at maintenance building, vinyl siding

24,000

(Base Project Allocation - $20,000)

(Design and Contingencies - $4,000)

(xcvi) Tobyhanna State Park

(A) Rehabilitation of boat mooring area, rehabilitation of beach area, rehabilitation of watercraft rental docks, increase parking, launching and mooring

134,000

(Base Project Allocation - $111,000)

(Design and Contingencies - $23,000)

(B) Road repairs

132,000

(Base Project Allocation - $110,000)

(Design and Contingencies - $22,000)

(C) Residence repairs, boundary line work, rehabilitation of picnic areas, rehabilitation of trails, erosion control, repair buildings and dam, rehabilitation of campsites, replace heating system, install new gas and oil tanks, install security fence, relocate loading ramp, rehabilitation of water system and construct storage areas

269,000

(Base Project Allocation - $224,000)

(Design and Contingencies - $45,000)

(xcvii) Tuscarora State Park

(A) Renovate road, pave boat launch area, replace showers, renovate residence, rehabilitation of beach, roof replacement, renovate office parking lot

186,000

(Base Project Allocation - $155,000)

(Design and Contingencies - $31,000)

(xcviii) Tyler State Park

(A) Resurface bike trail, repoint stone barn, dam repair, roof and floor repair, road and parking lot repair, rehabilitation of docks, replace comfort station partitions

148,000

(Base Project Allocation - $123,000)

(Design and Contingencies - $25,000)

(xcix) White Clay Creek State Park

(A) Rehabilitation of residence, replace windows, renovate water system, paint exterior of residence

16,000

(Base Project Allocation - $13,000)

(Design and Contingencies - $3,000)

(c) World's End State Park

(A) Rehabilitation of maintenance building

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Rehabilitation of office

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(C) Replace beach dressing stockade

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(D) Road repair and paving

419,000

(Base Project Allocation - $349,000)

(Design and Contingencies - $70,000)

(E) Cabin rehabilitation, pavilion repair, rehabilitation of day-use area, rehabilitation of concession stand

140,000

(Base Project Allocation - $116,000)

(Design and Contingencies - $24,000)

(F) Latrine repair and replacement

312,000

(Base Project Allocation - $260,000)

(Design and Contingencies - $52,000)

(ci) EEI Environmental Education Center

(A) Flagpole, visitor center development

50,000

(Base Project Allocation - $41,000)

(Design and Contingencies - $9,000)

(cii) Jacobsburg Environmental Education Center

(A) Replace roof, residence repair, rehabilitation of maintenance and storage buildings

22,000

(Base Project Allocation - $18,000)

(Design and Contingencies - $4,000)

(ciii) Jennings Environmental Education Center

(A) Center extension

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(B) Road and parking repairs, entrance walk and lighting, maintenance building extension, storage shed, boundary survey, water systems, fuel tanks, loading ramp, WTS visitor integration system

225,000

(Base Project Allocation - $187,000)

(Design and Contingencies - $38,000)

(civ) Kings Gap Environmental Education Center

(A) Renovate carriage house

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(B) Replace water tower

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(C) Replace heating system, painting, plumbing and curtains, paving

168,000

(Base Project Allocation - $140,000)

(Design and Contingencies - $28,000)

(cv) Nolde Forest Environmental Education Center

(A) Convert barn

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(B) Mansion repairs, handicapped walk, road repairs, painting, rebuild stone walls, dam repair, replace roof

324,000

(Base Project Allocation - $270,000)

(Design and Contingencies - $54,000)

(cvi) Delaware Canal Improvement Program

(A) Repair locks, aqueducts, stop and waste gates, overflows, bridge crossing and canal wall/liner dredging

38,280,000

(Base Project Allocation - $31,900,000)

(Design and Contingencies - $6,380,000)

(cvii) State Park Bridge Repair Program

(A) Bendigo State Park

36,000

(Base Project Allocation - $30,000)

(Design and Contingencies - $6,000)

(B) Hills Creek State Park

86,000

(Base Project Allocation - $71,000)

(Design and Contingencies - $15,000)

(C) Hyner Run State Park

195,000

(Base Project Allocation - $162,000)

(Design and Contingencies - $33,000)

(D) Little Pine State Park

339,000

(Base Project Allocation - $282,000)

(Design and Contingencies - $57,000)

(E) Parker Dam State Park

159,000

(Base Project Allocation - $132,000)

(Design and Contingencies - $27,000)

(F) Poe Valley State Park

12,000

(Base Project Allocation - $10,000)

(Design and Contingencies - $2,000)

(G) R. B. Winter State Park

80,000

(Base Project Allocation - $66,000)

(Design and Contingencies - $14,000)

(H) Reed's Gap State Park

141,000

(Base Project Allocation - $117,000)

(Design and Contingencies - $24,000)

(I) Reed's Gap State Park

40,000

(Base Project Allocation - $33,000)

(Design and Contingencies - $7,000)

(J) Sinnemahoning State Park

87,000

(Base Project Allocation - $72,000)

(Design and Contingencies - $15,000)

(K) Sizerville State Park

62,000

(Base Project Allocation - $51,000)

(Design and Contingencies - $11,000)

(L) Sizerville State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(M) Clear Creek State Park

105,000

(Base Project Allocation - $87,000)

(Design and Contingencies - $18,000)

(N) Cook Forest State Park

190,000

(Base Project Allocation - $158,000)

(Design and Contingencies - $32,000)

(O) Keystone State Park

69,000

(Base Project Allocation - $57,000)

(Design and Contingencies - $12,000)

(P) Kooser State Park

84,000

(Base Project Allocation - $70,000)

(Design and Contingencies - $14,000)

(Q) Kooser State Park

113,000

(Base Project Allocation - $94,000)

(Design and Contingencies - $19,000)

(R) Laurel Hill State Park

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(S) Laurel Hill State Park

112,000

(Base Project Allocation - $94,000)

(Design and Contingencies - $18,000)

(T) Laurel Hill State Park

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(U) Laurel Hill State Park

201,000

(Base Project Allocation - $167,000)

(Design and Contingencies - $34,000)

(V) Laurel Hill State Park

112,000

(Base Project Allocation - $93,000)

(Design and Contingencies - $19,000)

(W) Linn Run State Park

128,000

(Base Project Allocation - $106,000)

(Design and Contingencies - $22,000)

(X) Linn Run State Park

122,000

(Base Project Allocation - $101,000)

(Design and Contingencies - $21,000)

(Y) Ohiopyle State Park

212,000

(Base Project Allocation - $176,000)

(Design and Contingencies - $36,000)

(Z) Raccoon Creek State Park

81,000

(Base Project Allocation - $67,000)

(Design and Contingencies - $14,000)

(AA) Raccoon Creek State Park

182,000

(Base Project Allocation - $151,000)

(Design and Contingencies - $31,000)

(BB) Raccoon Creek State Park

124,000

(Base Project Allocation - $103,000)

(Design and Contingencies - $21,000)

(CC) Raccoon Creek State Park

64,000

(Base Project Allocation - $53,000)

(Design and Contingencies - $11,000)

(DD) Raccoon Creek State Park

132,000

(Base Project Allocation - $110,000)

(Design and Contingencies - $22,000)

(EE) Raccoon Creek State Park

102,000

(Base Project Allocation - $85,000)

(Design and Contingencies - $17,000)

(FF) Raccoon Creek State Park

69,000

(Base Project Allocation - $57,000)

(Design and Contingencies - $12,000)

(GG) Raccoon Creek State Park

121,000

(Base Project Allocation - $101,000)

(Design and Contingencies - $20,000)

(HH) Raccoon Creek State Park

122,000

(Base Project Allocation - $101,000)

(Design and Contingencies - $21,000)

(II) Raccoon Creek State Park

107,000

(Base Project Allocation - $89,000)

(Design and Contingencies - $18,000)

(JJ) Ryerson Station State Park

408,000

(Base Project Allocation - $340,000)

(Design and Contingencies - $68,000)

(KK) Blue Knob State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(LL) Blue Knob State Park

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(MM) Blue Knob State Park

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(NN) Blue Knob State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(OO) Blue Knob State Park

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(PP) Blue Knob State Park

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(QQ) Blue Knob State Park

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(RR) Blue Knob State Park

66,000

(Base Project Allocation - $55,000)

(Design and Contingencies - $11,000)

(SS) Blue Knob State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(TT) Blue Knob State Park

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(UU) Blue Knob State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(VV) Canoe Creek State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(WW) Colonel Denning State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(XX) Cowan's Gap State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(YY) Fowlers Hollow State Park

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(ZZ) Fowlers Hollow State Park

78,000

(Base Project Allocation - $65,000)

(Design and Contingencies - $13,000)

(AAA) King's Gap Environmental Education Center

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(BBB) King's Gap Environmental Education Center

66,000

(Base Project Allocation - $55,000)

(Design and Contingencies - $11,000)

(CCC) King's Gap Environmental Education Center

66,000

(Base Project Allocation - $55,000)

(Design and Contingencies - $11,000)

(DDD) Penn-Roosevelt State Park

36,000

(Base Project Allocation - $30,000)

(Design and Contingencies - $6,000)

(EEE) Pine Grove Furnace State Park

77,000

(Base Project Allocation - $65,000)

(Design and Contingencies - $12,000)

(FFF) Prince Gallitzin State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(GGG) Shawnee State Park

226,000

(Base Project Allocation - $188,000)

(Design and Contingencies - $38,000)

(HHH) Shawnee State Park

89,000

(Base Project Allocation - $74,000)

(Design and Contingencies - $15,000)

(III) Shawnee State Park

(Base Project Allocation - $188,000)

(Design and Contingencies - $38,000)

(JJJ) Shawnee State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(KKK) Shawnee State Park

48,000

(Base Project Allocation - $40,000)

(Design and Contingencies - $8,000)

(LLL) Trough State Park

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(MMM) Trough State Park

36,000

(Base Project Allocation - $30,000)

(Design and Contingencies - $6,000)

(NNN) Trough State Park

270,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $45,000)

(OOO) Whipple Dam State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(PPP) Bruce Lake State Park

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(QQQ) Bruce Lake State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(RRR) French Creek State Park

66,000

(Base Project Allocation - $55,000)

(Design and Contingencies - $11,000)

(SSS) French Creek State Park

66,000

(Base Project Allocation - $55,000)

(Design and Contingencies - $11,000)

(TTT) French Creek State Park

70,000

(Base Project Allocation - $58,000)

(Design and Contingencies - $12,000)

(UUU) Hickory Run State Park

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(VVV) Hickory Run State Park

26,000

(Base Project Allocation - $21,000)

(Design and Contingencies - $5,000)

(WWW) Hickory Run State Park

110,000

(Base Project Allocation - $91,000)

(Design and Contingencies - $19,000)

(XXX) Hickory Run State Park

114,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $19,000)

(YYY) Hickory Run State Park

114,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $19,000)

(ZZZ) Hickory Run State Park

114,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $19,000)

(AAAA) Hickory Run State Park

104,000

(Base Project Allocation - $86,000)

(Design and Contingencies - $18,000)

(BBBB) Nockamixon State Park

44,000

(Base Project Allocation - $36,000)

(Design and Contingencies - $8,000)

(CCCC) Nolde Forest Environmental Education Center

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(DDDD) Nolde Forest Environmental Education Center

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(EEEE) Nolde Forest Environmental Education Center

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(FFFF) Nolde Forest Environmental Education Center

30,000

(Base Project Allocation - $25,000)

(Design and Contingencies - $5,000)

(GGGG) Nolde Forest Environmental Education Center

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(HHHH) Nolde Forest Environmental Education Center

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(IIII) Nolde Forest Environmental Education Center

24,000

(Base Project Allocation - $20,000)

(Design and Contingencies - $4,000)

(JJJJ) Promised Land State Park

406,000

(Base Project Allocation - $338,000)

(Design and Contingencies - $68,000)

(KKKK) Promised Land State Park

118,000

(Base Project Allocation - $98,000)

(Design and Contingencies - $20,000)

(LLLL) Promised Land State Park

88,000

(Base Project Allocation - $73,000)

(Design and Contingencies - $15,000)

(MMMM) Ralph Stover State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(NNNN) Ricketts Glen State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(OOOO) Ridley Creek State Park

92,000

(Base Project Allocation - $76,000)

(Design and Contingencies - $16,000)

(PPPP) Ridley Creek State Park

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(QQQQ) Tyler State Park

14,000

(Base Project Allocation - $11,000)

(Design and Contingencies - $3,000)

(RRRR) Tyler State Park

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(SSSS) Tyler State Park

42,000

(Base Project Allocation - $35,000)

(Design and Contingencies - $7,000)

(TTTT) Tyler State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(UUUU) Tyler State Park

90,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $15,000)

(VVVV) Tyler State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(WWWW) Tyler State Park

72,000

(Base Project Allocation - $60,000)

(Design and Contingencies - $12,000)

(XXXX) Tyler State Park

60,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $10,000)

(YYYY) Roosevelt State Park

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(ZZZZ) Roosevelt State Park

153,000

(Base Project Allocation - $127,000)

(Design and Contingencies - $26,000)

(A5) Roosevelt State Park

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(B5) Roosevelt State Park

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(C5) Roosevelt State Park

46,000

(Base Project Allocation - $38,000)

(Design and Contingencies - $8,000)

(D5) Roosevelt State Park

24,000

(Base Project Allocation - $20,000)

(Design and Contingencies - $4,000)

(E5) Roosevelt State Park

143,000

(Base Project Allocation - $119,000)

(Design and Contingencies - $24,000)

(F5) Roosevelt State Park

131,000

(Base Project Allocation - $109,000)

(Design and Contingencies - $22,000)

(G5) Roosevelt State Park

34,000

(Base Project Allocation - $28,000)

(Design and Contingencies - $6,000)

(H5) Roosevelt State Park

80,000

(Base Project Allocation - $66,000)

(Design and Contingencies - $14,000)

(I5) Roosevelt State Park

528,000

(Base Project Allocation - $440,000)

(Design and Contingencies - $88,000)

(J5) Roosevelt State Park

51,000

(Base Project Allocation - $42,000)

(Design and Contingencies - $9,000)

(K5) Roosevelt State Park

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(L5) Roosevelt State Park

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(M5) Roosevelt State Park

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(N5) Roosevelt State Park

158,000

(Base Project Allocation - $131,000)

(Design and Contingencies - $27,000)

(O5) Roosevelt State Park

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(P5) Roosevelt State Park

163,000

(Base Project Allocation - $136,000)

(Design and Contingencies - $27,000)

(Q5) Roosevelt State Park

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(R5) Roosevelt State Park

26,000

(Base Project Allocation - $21,000)

(Design and Contingencies - $5,000)

(S5) Roosevelt State Park

131,000

(Base Project Allocation - $109,000)

(Design and Contingencies - $22,000)

(T5) Roosevelt State Park

56,000

(Base Project Allocation - $46,000)

(Design and Contingencies - $10,000)

(U5) Roosevelt State Park

53,000

(Base Project Allocation - $44,000)

(Design and Contingencies - $9,000)

(V5) Roosevelt State Park

124,000

(Base Project Allocation - $103,000)

(Design and Contingencies - $21,000)

(W5) Roosevelt State Park

153,000

(Base Project Allocation - $127,000)

(Design and Contingencies - $26,000)

(X5) Roosevelt State Park

54,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $9,000)

(Y5) Roosevelt State Park

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(Z5) Roosevelt State Park

129,000

(Base Project Allocation - $107,000)

(Design and Contingencies - $22,000)

(A6) Roosevelt State Park

114,000

(Base Project Allocation - $95,000)

(Design and Contingencies - $19,000)

(B6) Roosevelt State Park

110,000

(Base Project Allocation - $91,000)

(Design and Contingencies - $19,000)

(C6) Roosevelt State Park

106,000

(Base Project Allocation - $88,000)

(Design and Contingencies - $18,000)

(D6) Roosevelt State Park

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(E6) Roosevelt State Park

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(F6) Roosevelt State Park

110,000

(Base Project Allocation - $91,000)

(Design and Contingencies - $19,000)

(G6) Roosevelt State Park

30,000

(Base Project Allocation - $25,000)

(Design and Contingencies - $5,000)

(H6) Roosevelt State Park

29,000

(Base Project Allocation - $24,000)

(Design and Contingencies - $5,000)

(I6) Roosevelt State Park

131,000

(Base Project Allocation - $109,000)

(Design and Contingencies - $22,000)

(J6) Roosevelt State Park

131,000

(Base Project Allocation - $109,000)

(Design and Contingencies - $22,000)

(K6) Roosevelt State Park

131,000

(Base Project Allocation - $109,000)

(Design and Contingencies - $22,000)

(L6) Roosevelt State Park

14,000

(Base Project Allocation - $11,000)

(Design and Contingencies - $3,000)

(cviii) Codorus State Park

(A) Repair and improvement of the docking system

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(cix) Cook Forest State Park

(A) Renovation and construction of Saw Mill Center

1,500,000

(Base Project Allocation - $1,500,000)

(cx) French Creek State Park

(A) Additional funds for DGS 111-4, spillway modifications, Hopewell Dam

43,000

(Base Project Allocation - $36,000)

(Design and Contingencies - $7,000)

(cxi) Hickory Run State Park

(A) Replace bridges

264,000

(Base Project Allocation - $220,000)

(Design and Contingencies - $44,000)

(cxii) Kettle Creek State Park

(A) Rehabilitation of park facilities, including five comfort stations

1,420,000

(Base Project Allocation - $1,200,000)

(Design and Contingencies - $220,000)

(cxiii) Keystone State Park

(A) Renovation of facilities

1,080,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $180,000)

(cxiv) Kooser State Park

(A) Reconstruct tent and trailer camping area, road and sites

420,000

(Base Project Allocation - $350,000)

(Design and Contingencies - $70,000)

(B) Construction of a new maintenance center, washhouses for the overnight areas, sewer and other utility connections and extensions, and sewage treatment plant provisions

960,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $160,000)

(cxv) Laurel Hill State Park

(A) Additional funds for DGS 145-6, spillway modifications

660,000

(Base Project Allocation - $550,000)

(Design and Contingencies - $110,000)

(cxvi) Parker Dam State Park

(A) Rehabilitate road and drainage - main park road

264,000

(Base Project Allocation - $220,000)

(Design and Contingencies - $44,000)

(cxvii) Presque Isle State Park

(A) Additional funds for Project No. DGS 163-21; beach protection and beach nourishment

4,833,000

(Base Project Allocation - $4,394,000)

(Design and Contingencies - $439,000)

(B) Renovation of marina

1,154,000

(Base Project Allocation - $962,000)

(Design and Contingencies - $192,000)

(C) Storm damage and beach protection project

2,875,000

(Base Project Allocation - $2,725,000)

(Design and Contingencies - $150,000)

(D) The Department of Environmental Resources, acting for and in the name of the Commonwealth of Pennsylvania, is authorized to agree to hold and save the United States of America free from damages due to construction, operation and maintenance of the shoreline protection project at Presque Isle Peninsula, Erie, Pennsylvania, as authorized by section 501(a) of the Water Resources Development Act of 1986 (Public Law 99-662, 100 Stat. 4133), except for damages due to the fault or negligence of the United States of America or its contractors.

(cxviii) Pymatuning State Park

(A) Additional funds for DGS 103-4, Linesville boat livery facilities, including parking, paving, dockage and other improvements

800,000

(Base Project Allocation - $667,000)

(Design and Contingencies - $133,000)

(B) Repair and rehabilitation of the causeway over Pymatuning Lake

1,648,000

(Base Project Allocation - $1,598,000)

(Design and Contingencies - $50,000)

(cxix) Roosevelt State Park

(A) Improvement program for canal structure in order to return and maintain water in the Delaware Canal

12,785,000

(Base Project Allocation - $12,785,000)

(B) Restoration of the Delaware Canal in Tullytown Borough

3,000,000

(Base Project Allocation - $3,000,000)

(C) Tohickon Creek aqueduct repairs

500,000

(Base Project Allocation - $417,000)

(Design and Contingencies - $83,000)

(D) Paunacoussing Creek aqueduct wall, wall between Point Pleasant and Lumberville and rebuilding of Lock No.17 at Treasure Island

2,000,000

(Base Project Allocation - $1,667,000)

(Design and Contingencies - $333,000)

(E) Yardley Aqueduct at Brock's Creek, MP 14, rehabilitate aqueduct and adjacent walls

250,000

(Base Project Allocation - $209,000)

(Design and Contingencies - $41,000)

(F) Rehabilitate Borden's Lock (Lock No.7)

1,100,000

(Base Project Allocation - $917,000)

(Design and Contingencies - $183,000)

(G) Repairs, stonework, waste gate repairs, wall repair and towpath stabilization

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(H) Rehabilitate Tinicum aqueduct and Erwinna bridge

1,500,000

(Base Project Allocation - $1,250,000)

(Design and Contingencies - $250,000)

(cxx) Ryerson Station State Park

(A) Bridge

276,000

(Base Project Allocation - $230,000)

(Design and Contingencies - $46,000)

(cxxi) Salt Springs State Park

(A) Rehabilitation of park facilities including construction of additional pavilion and restrooms

150,000

(Base Project Allocation - $150,000)

(cxxii) Shawnee State Park

(A) Replace bridges - main park road

528,000

(Base Project Allocation - $440,000)

(Design and Contingencies - $88,000)

(B) Replace bridge decks, walkways, pit latrines; improve dock

1,300,000

(Base Project Allocation - $1,300,000)

(cxxiii) Sinnemahoning State Park

(A) Rehabilitation of gate and outlet tunnel - George B. Stevenson Dam

1,100,000

(Base Project Allocation - $917,000)

(Design and Contingencies - $183,000)

(cxxiv) Susquehanna State Park

(A) Provide riprap and filter blanket, rehabilitate existing boat launching ramp and install new courtesy dock

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

((cxxiv) amended July 11, 1989 P.L.320, No.54)

(cxxv) White Clay Creek Preserve

(A) Land acquisition for the White Clay Creek Preserve

500,000

(Base Project Allocation - $500,000)

(cxxvi) Yellow Creek State Park

(A) Construction of a marina on the north shore of the lake

2,160,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $360,000)

(B) Construction of additional campsites

3,360,000

(Base Project Allocation - $2,800,000)

(Design and Contingencies - $560,000)

(cxxvii) Bicycle trail

(A) Acquisition, construction and improvement of a bicycle trail running from Ohiopyle Borough to the City of Connellsville

500,000

(Base Project Allocation - $500,000)

(cxxviii) Ricketts Glen State Park

(A) Rehabilitation of park facilities, including camp site development

200,000

(Base Project Allocation - $200,000)

(cxxix) Forest District No. 4

(A) Improvement to Laurel Summit Road

500,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $50,000)

(cxxx) Forest District No. 5

(A) Rehabilitate bridges

134,000

(Base Project Allocation - $112,000)

(Design and Contingencies - $22,000)

(cxxxi) Forest District No. 7

(A) Rehabilitate bridges

138,000

(Base Project Allocation - $115,000)

(Design and Contingencies - $23,000)

(cxxxii) Forest District No. 8

(A) Rehabilitation and repair of Greens Valley Road in Spring Township

100,000

(Base Project Allocation - $100,000)

(cxxxiii) Forest District No. 9

(A) FM radio system

386,000

(Base Project Allocation - $322,000)

(Design and Contingencies - $64,000)

(cxxxiv) Forest District No. 10

(A) Rehabilitation and repair of the Kato Orviston Road

58,000

(Base Project Allocation - $58,000)

(B) Rehabilitate bridges

113,000

(Base Project Allocation - $94,000)

(Design and Contingencies - $19,000)

(cxxxv) Forest District No. 20

(A) FM radio system

386,000

(Base Project Allocation - $322,000)

(Design and Contingencies - $64,000)

(cxxxvi) Allegheny County

(A) Additional funds to restore Pine Creek Watershed to pre-May 1986 condition

3,000,000

(Base Project Allocation - $3,000,000)

(B) Construction of eight storm water detention facilities

1,520,000

(Base Project Allocation - $1,520,000)

(C) Relocation of utility lines in connection with the Pine Creek Flood Control Project

100,000

(Base Project Allocation - $100,000)

(D) Completion of the Gregg Lane Storm Sewer Project

60,000

(Base Project Allocation - $60,000)

(E) Completion of the Main Street drainage plan in Findley Township

49,000

(Base Project Allocation - $49,000)

(F) Correction of flooding problem in the Whiskey Run Basin of Chartiers Creek in Scott Township

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(G) Borough of Castle Shannon - Replacement of entire storm water collection system

344,000

(Base Project Allocation - $287,000)

(Design and Contingencies - $57,000)

(H) Borough of Whitehall - Construction of storm water sewer along Barlind Drive from Lot 35 to Provost Road and along Provost Road to Lawnview Drive. Install storm water inlet on Lot 20 on Rolling Hills Road; install two new inlets and lower existing inlets on Echo Glen Drive at 4607 - 4611 and 4615; replace line on Felix Drive; raise headwall at the terminus of Maryal Drive; correct flood condition at 5291 Spring Valley Drive; correct storm water problem at 4731 Brownsville Road; correct flooding problem on Heinen Street; correct flooding problem on Skyline Drive; correct flooding on Doverdell Drive; correct flooding on Oak Ridge Drive; install manhole on South Passage Drive

385,000

(Base Project Allocation - $321,000)

(Design and Contingencies - $64,000)

(I) Borough of Bethel Park - Installation of 100-foot boring beneath the Port Authority transit trolley tracks to correct basement flooding

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(J) Upgrade flood control systems in McCandless Township

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(K) Flood prevention project on Little Bull Creek, Harrison Township

1,000,000

(Base Project Allocation - $1,000,000)

(L) Flood prevention project on Bull Creek, Fawn Township

1,000,000

(Base Project Allocation - $1,000,000)

(M) Coles Road storm sewer project

48,000

(Base Project Allocation - $48,000)

(N) Removal of sand bar in Allegheny River

600,000

(Base Project Allocation - $600,000)

(O) Deer Creek Watershed project

300,000

(Base Project Allocation - $300,000)

(P) Flood protection for Saw Mill Run

1,198,000

(Base Project Allocation - $1,089,000)

(Design and Contingencies - $109,000)

(Q) Engineering and piping for Lick Run Creek

800,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $200,000)

(R) Baldwin Borough, correction of flood problem at Lick Run Creek

800,000

(Base Project Allocation - $800,000)

(S) City of Pittsburgh, 31st Ward - Dredging and repair of flood control structures in Streets Run and Glass Run Creeks, including construction of retaining flood walls and sewer backflow preventers

5,000,000

(Base Project Allocation - $5,000,000)

(T) Flood Prevention Project on Lick Run Creek, Baldwin Borough - engineering and piping

960,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $160,000)

(cxxxvii) Beaver County

(A) Virginia Avenue storm sewer reconstruction in the Borough of Rochester

294,000

(Base Project Allocation - $262,000)

(Design and Contingencies - $32,000)

(B) Railroad Street storm sewer in the Borough of Rochester

101,000

(Base Project Allocation - $89,000)

(Design and Contingencies - $12,000)

(C) Reconstruction of approximately 50 storm water inlets in the Borough of Freedom

260,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $35,000)

(D) Construction of Ranney water well in Aliquippa Borough

1,000,000

(Base Project Allocation - $1,000,000)

(E) Extension of sewer line in Patterson Township

3,000,000

(Base Project Allocation - $3,000,000)

(F) Construction of sewer line to Aliquippa Airport

200,000

(Base Project Allocation - $200,000)

(cxxxviii) Berks County

(A) Rehabilitation of flood damaged areas of Birdsboro Borough

(I) Repairs to Water Street from Main to Beacon

250,000

(Base Project Allocation - $250,000)

(II) Repairs to Jackson Street

10,000

(Base Project Allocation - $10,000)

(III) Repairs to Old River Road

5,000

(Base Project Allocation - $5,000)

(IV) Repairs to the borough sewer system

150,000

(Base Project Allocation - $150,000)

(V) Repairs to the borough water system

150,000

(Base Project Allocation - $150,000)

(VI) Repairs to the Rustic Recreation Area

110,000

(Base Project Allocation - $110,000)

(VII) Repairs to the Water Street Recreation Area

10,000

(Base Project Allocation - $10,000)

(B) Bridge replacement and erosion control project on Topton Creek

2,500,000

(Base Project Allocation - $2,500,000)

(C) Repair of Trout Run Reservoir in Boyertown Borough

450,000

(Base Project Allocation - $450,000)

(D) Improvements to Boyertown Borough Wastewater Treatment Plant

350,000

(Base Project Allocation - $350,000)

(E) Antietam Creek Flood Control Project in Exeter Township

165,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $15,000)

(F) Toad Creek Flood Control Project in Topton Borough

275,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $25,000)

(G) Laurel Run Creek Flood Control Project in Muhlenberg Township

2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(H) Upgrade Berks County Sewage Treatment Plant

3,000,000

(Base Project Allocation - $3,000,000)

(I) Lower Alsace Township - Dredge channel, provide riprap, remove debris downstream from Angora Road

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(J) Columbia Avenue - Install street storm drainage in conjunction with new street construction

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(cxxxix) Bucks County

(A) Lower Southampton Township

(I) Pine Tree Farms drainage project

800,000

(Base Project Allocation - $800,000)

(II) Douglas Drive sewer improvement

120,000

(Base Project Allocation - $120,000)

(B) Falls Township storm water drainage improvement project

1,200,000

(Base Project Allocation - $1,200,000)

(C) Upper Southampton Township storm water drainage improvement project

2,000,000

(Base Project Allocation - $2,000,000)

(D) Ten-foot chain link fence to encircle the Bowman's Hill Wildflower Preserve

250,000

(Base Project Allocation - $250,000)

(cxl) Butler County

(A) Storm water management project for Butler Township

700,000

(Base Project Allocation - $700,000)

(B) City of Butler - Sullivan Run stream bank stabilization

500,000

(Base Project Allocation - $500,000)

(cxli) Cambria County

(A) Additional funds for DGS 182-4, Flood protection - City of Johnstown

160,000

(Base Project Allocation - $133,000)

(Design and Contingencies - $27,000)

(B) City of Johnstown - Channel improvements to St. Clair Run

1,320,000

(Base Project Allocation - $1,200,000)

(Design and Contingencies - $120,000)

(C) Lower Yoder Township - Construction of debris dam on St. Clair Run

605,000

(Base Project Allocation - $550,000)

(Design and Contingencies - $55,000)

(D) Upper Yoder Township - Construction of a flood control project on Cheney Run

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(E) Upper Yoder Township - Construction of a flood control project on Cherry Run

438,000

(Base Project Allocation - $365,000)

(Design and Contingencies - $73,000)

(cxlii) Cameron County

(A) Emporium - Install 5,000 feet of curbing and storm sewers

168,000

(Base Project Allocation - $140,000)

(Design and Contingencies - $28,000)

(cxliii) Carbon County

(A) Acquisition of 18 mile Lehigh Valley Railroad right-of-way from Lehighton to Cementon for Scranton to Philadelphia Heritage Park project

900,000

(Base Project Allocation - $900,000)

(cxliv) Centre County

(A) Construction of a stream diversion project in Milesburg Borough and Boggs Township

400,000

(Base Project Allocation - $350,000)

(Design and Contingencies - $50,000)

(B) Correction of the storm water flooding in the Lytle addition subdivision in State College

485,000

(Base Project Allocation - $404,000)

(Design and Contingencies - $81,000)

(C) Philipsburg Borough - Replacing storm water pipe and cleaning storm drainage ditch

108,000

(Base Project Allocation - $90,000)

(Design and Contingencies - $18,000)

(D) Borough of Osceola Mills

(I) Reconstruction of a storm water culvert known as "the Canal"

432,000

(Base Project Allocation - $360,000)

(Design and Contingencies - $72,000)

(II) Construction of sewage treatment facility in conjunction with Osceola Mills Industrial Park Development

2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(E) Borough of Bellefonte - Expand Borough Sewer Authority facilities

7,800,000

(Base Project Allocation - $6,500,000)

(Design and Contingencies - $1,300,000)

(F) Updating and refurbishing Centre County solid waste transfer station

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(G) Construction and operationalization of Centre County recycling centers

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(H) Sewer line construction from Mid-State Airport to treatment center

960,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $160,000)

(cxlv) Clearfield County

(A) Curwensville Borough - Construction of a flood control project

2,000,000

(Base Project Allocation - $1,833,000)

(Design and Contingencies - $167,000)

(B) For dredging and cleaning Janesville Dam, Smithmill, Clearfield County

300,000

(Base Project Allocation - $300,000)

(cxlvi) Clinton County

(A) Construction of the Beech Creek Rehabilitation Project in Beech Creek Township

400,000

(Base Project Allocation - $350,000)

(Design and Contingencies - $50,000)

(B) Erosion and sediment pollution control and fish habitat improvement project for Kettle Creek

141,000

(Base Project Allocation - $141,000)

(C) Erosion and sediment pollution control and fish habitat improvement project for Fishing Creek

32,000

(Base Project Allocation - $32,000)

(D) Woodward Township - flood control project

2,850,000

(Base Project Allocation - $2,550,000)

(Design and Contingencies - $300,000)

(E) Lock Haven - Federal flood control project

15,565,000

(Base Project Allocation - $14,150,000)

(Design and Contingencies - $1,415,000)

(cxlvii) Columbia County

(A) Town of Bloomsburg - Storm water management project to correct runoff problem from Bloomsburg State University

316,000

(Base Project Allocation - $256,000)

(Design and Contingencies - $60,000)

(B) Borough of Berwick - Construction to divert Thompson Run out of the borough sewer system

1,000,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $200,000)

(cxlviii) Lackawanna County

(A) ((A) repealed July 8, 1994, P.L.444, No.74)

(B) Flood control projects on Lucky Run, Lindley Creek, Keyser Creek, Leach Creek, West Mountain Creek, Leggetts Creek, Meadowbrook, Roaring Brook, Mountain Lake, Stafford-Meadowbrook

5,500,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $500,000)

(C) Replacement and/or rehabilitation of following: Luzerne Street culvert over Keyser Creek; Erie-Lackawanna Railroad culvert #1 over Keyser Creek; Erie-Lackawanna Railroad, West Mountain Road culvert over West Mountain Creek; culvert #2 over Keyser Creek; South Dewey Avenue culvert over Lindley Creek; South Merrifield Avenue culvert over Lindley Creek; South Cameron Avenue culvert over Lindley Creek; Jackson Street culvert over Keyser Creek; Horatio Avenue culvert over West Mountain Creek; North-South Road culvert over Keyser Creek; Erie-Lackawanna culvert #1 over Lucky Run Creek; Erie-Lackawanna culvert #2 over Lucky Run Creek; Erie-Lackawanna culvert #3 over Lucky Run Creek

2,970,000

(Base Project Allocation - $2,700,000)

(Design and Contingencies - $270,000)

(D) City of Carbondale and Carbondale Township - Installation of a storm water drainage system from Wayne Avenue and Copeland Street through Carbondale Township for discharge into the Lackawanna River

1,000,000

(Base Project Allocation - $925,000)

(Design and Contingencies - $75,000)

(E) City of Scranton

(I) ((I) repealed July 8, 1994, P.L.444, No.74)

(II) Storm water management system

11,000,000

(Base Project Allocation - $10,000,000)

(Design and Contingencies - $1,000,000)

(F) Dunmore Borough

(I) Storm water management system

4,400,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $400,000)

(G) ((G) repealed July 11, 1996, Sp.Sess.2, P.L.1791, No.8)

(H) Taylor Borough

(I) Storm water management system

4,400,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $400,000)

(I) Areas of the City of Scranton and Boroughs of Taylor and Dunmore

(I) PennDot Storm Water Management System Project on the State highways of: Jackson Street, Newton Road, Keyser Avenue, Morgan Highway, Luzerne Street, Main Avenue, West Market Street, Oak Street, Saltry Street, Providence Road, Queen Ridge Street, Linden Street, Mulberry Street, Harrison Avenue, Myrtle Street, Wheeler Avenue, Moosic Street, Stafford Avenue, Cedar Avenue, Birney Avenue, Pittston Avenue, Davis Street, Adams Avenue, Continental Street, Wyoming Avenue, Oak Street, Drinker Street and Blakely Street

5,500,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $500,000)

(J) Clarks Summit Borough

(I) Dredging the tributaries of Leggets Creek

426,000

(Base Project Allocation - $355,000)

(Design and Contingencies - $71,000)

(II) Creek repairs to include dredging of creeks under Landsdowne, Maple, Linden, Hosfeld, Clarks Sunset and Center Streets

456,000

(Base Project Allocation - $380,000)

(Design and Contingencies - $76,000)

(III) Sewer line repair project

294,000

(Base Project Allocation - $294,000)

(IV) Clarks Summit and South Abington Township Joint Sewer Project

678,000

(Base Project Allocation - $678,000)

(K) Old Forge Borough

(I) Flood control and dredging of St. Johns Creek

1,050,000

(Base Project Allocation - $875,000)

(Design and Contingencies - $175,000)

(L) Fell Township

(I) Sewers and storm drains on Lackawanna River and Wilson Creek

540,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $90,000)

(M) Scott Township

(I) Hull Creek dredging

1,026,000

(Base Project Allocation - $855,000)

(Design and Contingencies - $171,000)

(II) Construction of storm water drainage systems on Routes 438 and 247

168,000

(Base Project Allocation - $140,000)

(Design and Contingencies - $28,000)

(N) Benton Township

(I) Construction of and dredging of a storm drain

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(O) Moosic Borough - Construction and repair of sewer system

641,000

(Base Project Allocation - $641,000)

(P) South Abington Township sewer construction project

600,000

(Base Project Allocation - $600,000)

(Q) Greenfield Township sewer construction project

510,000

(Base Project Allocation - $510,000)

(cxlix) Lancaster County

(A) West Lampeter Township - Construct storm water runoff control in Willow Street area

270,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $45,000)

(cl) Luzerne County

(A) Additional funds for DGS 182-5, flood protection, Exeter Borough

112,000

(Base Project Allocation - $93,000)

(Design and Contingencies - $19,000)

(B) Construct storm sewer on Trayor Street, Sanovia Street and Scarborough Avenue in Sullivan Park Area

302,000

(Base Project Allocation - $252,000)

(Design and Contingencies - $50,000)

(C) Construct storm sewer system, Exeter Park Area - Harding, Wilson, Whitlock and Roosevelt Avenues

419,000

(Base Project Allocation - $349,000)

(Design and Contingencies - $70,000)

(D) Flood control project on Solomon Creek

500,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $100,000)

(E) Flood control project on Mill Creek

500,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $100,000)

(F) Flood control project on Laurel Run

500,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $100,000)

(G) Flood Control project for Toby Creek and tributaries. To include digging of channel, channel widening, gabion wall construction, riprap slope protection, reinforced concrete retaining structures and water impounding basins in Dallas Borough; Dallas Township and Kingston Township

5,000,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $1,000,000)

(H) Reconstruction and replacement of the storm water system for flood control in Yatesville Borough

360,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $60,000)

(I) Flood control project for Curry Street in Duryea Borough

216,000

(Base Project Allocation - $180,000)

(Design and Contingencies - $36,000)

(J) Reconstruction of the storm water system along Columbus Avenue in the City of Pittston

720,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $120,000)

(K) Construction of a flood control project in the area of the Barnum site and New Street in the City of Pittston and Duryea Borough

900,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $150,000)

(L) Storm water management project along the Pittston Bypass to a discharge point located in the City of Pittston

4,200,000

(Base Project Allocation - $3,500,000)

(Design and Contingencies - $700,000)

(M) Flood control project, Mill Creek, Plains Township

10,000,000

(Base Project Allocation - $9,000,000)

(Design and Contingencies - $1,000,000)

(N) Construction of a flood control project on Forge Creek, Nanticoke, Newport Township

1,120,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $220,000)

(O) Stream bank stabilization project in Pittston Township

2,900,000

(Base Project Allocation - $2,900,000)

(P) Storm sewer extension project on Poplar Street

100,000

(Base Project Allocation - $100,000)

(Q) Abraham's Creek and Warsaw Street Projects

67,000

(Base Project Allocation - $67,000)

(R) Storm water system for Newport Township

936,000

(Base Project Allocation - $936,000)

(S) Susquehanna River flood control project

45,000,000

(Base Project Allocation - $45,000,000)

(T) Separation and reconstruction of storm water drainage system and sewage system along S.R.92 in West Pittston Borough

180,000

(Base Project Allocation - $148,000)

(Design and Contingencies - $32,000)

(U) Matching funds for EPA Sewage Project, Jackson Township

1,011,000

(Base Project Allocation - $1,011,000)

(cli) McKean County

(A) Flood protection, Port Allegheny Borough

6,670,000

(Base Project Allocation - $5,500,000)

(Design and Contingencies - $1,170,000)

(clii) Mercer County

(A) Flood control for Pymatuning Township

200,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $50,000)

(cliii) Mifflin County

(A) Granville Township - establish water and sewer services for Strodes Mills area

1,500,000

(Base Project Allocation - $1,250,000)

(Design and Contingencies - $250,000)

(cliv) Monroe County

(A) Pocono Performing Arts Center

(I) Design and construction of a concert shell infrastructure for the Pennsylvania Center for the Performing Arts in the Delaware Water Gap National Recreational Area, Middle Smithfield Township

17,000,000

(Base Project Allocation - $17,000,000)

((A) amended July 11, 1989, P.L.320, No.54)

(clv) Montgomery County

(A) Township of Upper Moreland - Construction of a retention basin and storm drainage pipe in the Cortello Avenue area

184,000

(Base Project Allocation - $154,000)

(Design and Contingencies - $30,000)

(B) Construction of a storm sewer in Rockledge Borough, South Sylvania Avenue to Church Road

200,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $50,000)

(C) Township of Abington - construction of Cumberland Road storm sewer, Horace Avenue to Susquehanna Road

150,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $50,000)

(D) Township of Abington - construction of Govania Avenue storm sewer, Montgomery Avenue to Glendale Avenue

325,000

(Base Project Allocation - $275,000)

(Design and Contingencies - $50,000)

(E) Various road projects associated with the conversion of Norristown State Hospital Farm to a State park

10,200,000

(Base Project Allocation - $8,160,000)

(Design and Contingencies - $2,040,000)

(F) Channel improvements for Plymouth Creek in Conshohocken Borough

625,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $125,000)

(clvi) Northampton County

(A) Construction of a fish passageway on the Lehigh River at the Easton Dam

2,300,000

(Base Project Allocation - $1,840,000)

(Design and Contingencies - $460,000)

(B) Construction of a fish passageway on the Lehigh River at the Chain Dam

1,000,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $200,000)

(C) Renovation and repair of Illick's Mill Dam on Monocacy Creek in the City of Bethlehem

160,000

(Base Project Allocation - $160,000)

(clvii) Schuylkill County

(A) Construction of a mine acid treatment plant on the upper end of the Little Schuylkill River, north of Tamaqua

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(B) Tamaqua Borough Flood Protection Project, Commonwealth portion of non-Federal cost-share of the Federal flood control project as authorized by the Water Resources Development Act of 1974

2,800,000

(Base Project Allocation - $2,520,000)

(Design and Contingencies - $280,000)

((B) amended July 11, 1989, P.L.320, No.54)

(C) Construction of new water lines for residential water services and fire protection in Coaldale Borough

135,000

(Base Project Allocation - $135,000)

(clviii) Snyder County

(A) Construction of recreational facilities for Walker Lake/Middle Creek Watershed - flood control project

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(clix) Westmoreland County

(A) Flood protection projects DGS 180-35 and 180-36, tributary Jack's Run, road sections 1 and 2: Route 119 to Greensburg High School in City of Greensburg and Hempfield Township, additional appropriation

500,000

(B) ((B) repealed Oct. 10, 1997, P.L.392, No.47)

(C) ((C) repealed Oct. 10, 1997, P.L.392, No.47)

(D) Additional funds for the closing of Greensburg landfill

200,000

(Base Project Allocation - $200,000)

(E) Unity Run culvert extension in Latrobe Borough

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(clx) Wyoming County

(A) Lazybrook Acres flood control project in Tunkhannock Township

3,000,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $500,000)

(clxi) York County

(A) Channel improvements to Little Conewago Creek in Dover and West Manchester Townships

120,000

(Base Project Allocation - $120,000)

(clxii) Departmental Statewide projects

(A) Equipment to maintain flood control projects

5,500,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $500,000)

(B) State Forest Bridge Rehabilitation Program

2,200,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(6) Department of General Services

$83,992,000

(i) Capitol Complex

(A) Upgrade elevators in Health and Welfare Building

1,188,000

(Base Project Allocation - $990,000)

(Design and Contingencies - $198,000)

(B) Upgrade lighting systems in Health and Welfare and Labor and Industry Buildings

1,267,000

(Base Project Allocation - $1,056,000)

(Design and Contingencies - $211,000)

(C) Upgrade elevators, replace windows and roof and repoint North Office Building

3,360,000

(Base Project Allocation - $2,800,000)

(Design and Contingencies - $560,000)

(D) Additional funds for Project No. DGS 948-26; renovation and waterproofing of underground garage

3,600,000

(Additional Base Allocation - $3,000,000)

(Additional Design and Contingencies - $600,000)

(ii) Harrisburg Area

(A) Commonwealth Computer Facility

6,328,000

(Base Project Allocation - $5,219,000)

(Design and Contingencies - $1,109,000)

(B) Additional funds for DGS 948-22; Market Street State Office Building

14,232,000

(Base Project Allocation - $14,232,000)

(C) Environmental Resources Laboratory and Regional Office Building

24,850,000

(Base Project Allocation - $20,500,000)

(Design and Contingencies - $4,350,000)

(iii) David L. Lawrence Convention Center

(A) Funding for preliminary study, planning, property acquisition and expansion of the David L. Lawrence Convention Center

7,000,000

(Base Project Allocation - $7,000,000)

(iv) Erie Civic Center

(A) Construction of addition to the center

3,000,000

(Base Project Allocation - $2,500,000)

(Design and Contingencies - $500,000)

(B) Renovation of existing Erie Civic Center

100,000

(Base Project Allocation - $100,000)

(C) Replacement of HVAC systems and repair facade for Warner Theatre

228,000

(Base Project Allocation - $190,000)

(Design and Contingencies - $38,000)

(D) Renovation and repairs to Louis J. Tullio Convention Center

127,000

(Base Project Allocation - $106,000)

(Design and Contingencies - $21,000)

(E) Replacement of HVAC system for Sears Building

344,000

(Base Project Allocation - $287,000)

(Design and Contingencies - $57,000)

(v) Philadelphia State Office Building

(A) Upgrade chillers, replace windows and lobby flooring, repair exterior tiles and seal and repoint exterior concrete surface

4,488,000

(Base Project Allocation - $3,740,000)

(Design and Contingencies - $748,000)

(vi) Philadelphia Zoo

(A) Proposing acquisition and construction of the Environmental Education Building and amphitheatre at the Philadelphia Zoo to be known as the Frank J. Palumbo Building

5,380,000

(Base Project Allocation - $4,580,000)

(Design and Contingencies - $800,000)

(vii) Summer Facility

(A) Acquisition and development of land in Bedford, Pennsylvania, for multiuse public park with amphitheater suitable for concerts and other cultural events

8,500,000

(Base Project Allocation - $8,500,000)

(7) Department of Health

$6,500,000

(i) Diagnostic and Rehabilitation Center

(A) Additional funds for DGS 522.1 for acquisition of adjacent facility and renovations of existing facility

3,500,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $500,000)

(ii) Addictive Diseases Center

(A) Additional funds for completion of DGS 510-28

3,000,000

(Base Project Allocation - $2,750,000)

(Design and Contingencies - $250,000)

(8) Historical and Museum Commission

$49,186,000

(Amount amended July 11, 1989, P.L.320, No.54)

(i) Cornwall Furnace

(A) Restoration, Phase II

825,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $75,000)

(B) Fire and security system

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(C) Restoration and stabilization

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(ii) Bushy Run Battlefield

(A) Fire and security system

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(iii) Commonwealth Conservation Center

(A) Original equipment

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(iv) Ephrata Cloister

(A) Fire suppression system

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(v) Flagship Niagara

(A) Additional funds for DGS 974-5, restoration of Flagship Niagara

1,500,000

(Base Project Allocation - $1,500,000)

(B) Construction of a maritime museum and permanent berthing facility for the Flagship Niagara

5,000,000

(Base Project Allocation - $5,000,000)

(vi) Old Economy Village

(A) Restoration of Granary

550,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $50,000)

(B) Restoration and preservation of Feast Hall

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(C) Additional funds for restoration and preservation of select miners' houses - Phase II

2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(D) Restoration of outbuildings associated with building

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(E) Restoration of Robertson House

216,000

(Base Project Allocation - $180,000)

(Design and Contingencies - $36,000)

(vii) Daniel Boone Homestead

(A) Construction of an orientation exhibition gallery for the visitors center

110,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $10,000)

(B) Restoration and preservation of Betolet Log Cabin

150,000

(Base Project Allocation - $125,000)

(Design and Contingencies - $25,000)

(C) Restoration of Bertoil Log Cabin

122,000

(Base Project Allocation - $102,000)

(Design and Contingencies - $20,000)

(viii) Eckley Miners Village

(A) Renovation and rehabilitation of buildings

750,000

(Base Project Allocation - $625,000)

(Design and Contingencies - $125,000)

(B) Acquisition of antique furnishings and equipment

144,000

(Base Project Allocation - $120,000)

(Design and Contingencies - $24,000)

(C) Permanent exhibits and period rooms in mine owners house

100,000

(Base Project Allocation - $83,000)

(Design and Contingencies - $17,000)

(D) Additional funds for restoration

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(E) Adoption of coal breaker as visitors center

900,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $150,000)

(ix) Altoona

(A) Conversion of the former Pennsylvania Railroad office building located on Ninth Avenue in the City of Altoona. Conversion to include display area; food service area; storage area; and general office space

4,500,000

(Base Project Allocation - $3,600,000)

(Design and Contingencies - $900,000)

(x) Lackawanna County Anthracite Museum

(A) Additional funds for the Lackawanna County Anthracite Museum at McDade Park

550,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $50,000)

(xi) Landis Valley Museum

(A) Original equipment regional storage facility - Phase II

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(xii) Erie Art Museum

(A) For expansion of the Erie Art Museum to include the Ashby Building as part of the facility, including a physical link between structures

625,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $125,000)

(xiii) Somerset Historical Center

(A) Additional funds for DGS 990-2; construction of an addition to the center and improvements for parking and entrance areas

500,000

(Base Project Allocation - $425,000)

(Design and Contingencies - $75,000)

(xiv) Canal Museum in Easton

(A) For expansion and reconstruction of the Canal Museum in Easton

1,584,000

(Base Project Allocation - $1,440,000)

(Design and Contingencies - $144,000)

(xv) Burnside Farm

(A) Reconstruction and renovation of the historic Burnside Farm in Lehigh County

836,000

(Base Project Allocation - $500,000)

(Land Allocation - $197,000)

(Design and Contingencies - $139,000)

(xvi) Railroad Museum of Pennsylvania

(A) Construction of an addition to Rolling Stock Hall

2,160,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $360,000)

(B) Facility expansion

2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(C) Fire and security system

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(xvii) Anthracite Museum Complex

(A) Reseal and resurface driveways and parking areas

352,000

(Base Project Allocation - $293,000)

(Design and Contingencies - $59,000)

(xviii) Brandywine Battlefield

(A) Restoration and preservation of Lafayette's Headquarters

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(xix) Curtin Village

(A) Restoration of village - Phase I

660,000

(Base Project Allocation - $550,000)

(Design and Contingencies - $110,000)

(xx) Graeme Park

(A) Restoration and preservation of Keith House

420,000

(Base Project Allocation - $350,000)

(Design and Contingencies - $70,000)

(xxi) Hope Lodge/Mather Mill

(A) Restoration and preservation of Manor House and kitchen wing - Phase II

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(B) Restoration of period gardens

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(xxii) Joseph Priestley House

(A) Restoration and preservation

480,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $80,000)

(xxiii) Old Custom House/Cashiers House

(A) Structural repairs and restoration

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(B) Restoration and preservation of Great House

540,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $90,000)

(xxiv) Old Mill Village

(A) Survey and structural repairs

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(xxv) State Museum of Pennsylvania

(A) Planetarium renovations

480,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $80,000)

(xxvi) Washington Crossing Historic Park

(A) Resurface and reseal roads and parking areas

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(B) Restoration and preservation of buildings at Taylorsville - Phase I

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(C) Restoration Taylorsville Houses - Phase II

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(D) Fire and security system

240,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $40,000)

(xxvii) Conrad Weiser Homestead

(A) Fire and security system

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(xxviii) Graeme Park

(A) Remodel Barn as visitor center

480,000

(Base Project Allocation - $400,000)

(Design and Contingencies - $80,000)

(xxix) Hope Lodge/Mather Mill

(A) Conversion of barn to visitor center

1,080,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $180,000)

(xxx) Pennsbury Manor

(A) Expansion and renovation of visitor center

720,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $120,000)

(xxxi) Washington Crossing Historic Park

(A) Upgrade visitor center

252,000

(Base Project Allocation - $210,000)

(Design and Contingencies - $42,000)

(xxxii) Ephrata Cloister

(A) Fire Suppression System, Phase II

496,000

(Base Project Allocation - $413,000)

(Design and Contingencies - $83,000)

(xxxiii) Pennsbury Manor

(A) Construction of a visitor center

3,000,000

(Base Project Allocation - $3,000,000)

(xxxiv) Johnstown Flood Museum

(A) Development of the Cambria Iron Works Building in conjunction with the National Park Service Industrial Heritage Project

1,200,000

(Base Project Allocation - 1,200,000)

(xxxv) Graeme Park and Keith Mansion, Montgomery County

(A) Restoration and maintenance of the park and mansion

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(xxxvi) Fort Pitt Museum, Point State Park

(A) Replace and reconstruct roofing system and restore interior finishes

500,000

(Base Project Allocation - $500,000)

(xxxvii) New Freedom Theatre, Philadelphia

(A) Renovations to the New Freedom Theatre. No funds from this authorization shall be expended until such time that legislation authorizing the acquisition of the New Freedom Theatre in Philadelphia by the Commonwealth has been enacted by the General Assembly

4,000,000

(Base Project Allocation - $3,333,000)

(Design and Contingencies - $667,000)

((xxxvii) added July 11, 1989, P.L.320, No.54)

(9) Department of Military Affairs

$26,558,000

(i) Dixmont State Hospital

(A) Restoration and renovation of the former Dixmont State Hospital for use as a veterans' nursing home

6,000,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $1,000,000)

(ii) South Mountain Restoration Center

(A) Conversion and restoration of vacant facilities at the South Mountain Restoration Center for use as a veterans' nursing home

6,000,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $1,000,000)

(iii) Hollidaysburg Veterans' Home

(A) Construction of a chapel

110,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $10,000)

(B) Additional funds for renovation of Sommer Hall

1,237,000

(Base Project Allocation - $1,031,000)

(Design and Contingencies - $206,000)

(iv) Pennhurst Veterans' Home

(A) Additional funds for DGS 960-50; Renovation and Conversion of Pennhurst Center to a veterans' home

422,000

(Base Project Allocation - $352,000)

(Design and Contingencies - $70,000)

(v) Pennsylvania Soldiers' and Sailors' Home

(A) Conversion of personal care beds (27) to nursing care beds (27)

972,000

(Base Project Allocation - $810,000)

(Design and Contingencies - $162,000)

(vi) Cumberland County, North Middleton Twp., HQ and HQ Bty., 108th Field Artillery

(A) Drill floor addition to Armory, 130 feet x 60 feet x 40 feet

400,000

(Base Project Allocation - $400,000)

(vii) Fort Indiantown Gap

(A) Acquisition of land for weapons training

149,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $14,000)

(viii) Spring City Armory

(A) Convert building at former Pennhurst Center to an armory

198,000

(Base Project Allocation - $165,000)

(Design and Contingencies - $33,000)

(ix) Soldiers' and Sailors' Home - Erie

(A) Vehicle and maintenance facility

380,000

(Base Project Allocation - $317,000)

(Design and Contingencies - $63,000)

(x) Washington County Airport

(A) Air National Guard site improvements

2,500,000

(Base Project Allocation - $2,500,000)

(xi) Northeastern Pennsylvania Veterans' Home

(A) State share of the construction of a veterans' home on the site of the Scranton State General Hospital, including necessary demolition of the existing hospital

8,190,000

(Base Project Allocation - $6,825,000)

(Design and Contingencies - $1,365,000)

(10) Department of Public Welfare

$64,639,000

(i) Clarks Summit State Hospital

(A) Sewage treatment plant holding tank and reflushing digester

540,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $90,000)

(B) Install baseboard or wall radiation - also additional area thermostat

1,350,000

(Base Project Allocation - $1,125,000)

(Design and Contingencies - $225,000)

(C) Air condition geriatric building, 6 Hilltop West

1,780,000

(Base Project Allocation - $1,400,000)

(Design and Contingencies - $380,000)

(D) Construct offices and treatment rooms in Newton Hall

960,000

(Base Project Allocation - $800,000)

(Design and Contingencies - $160,000)

(E) Air conditioning in Newton Building and renovate main kitchen

2,880,000

(Base Project Allocation - $2,400,000)

(Design and Contingencies - $480,000)

(F) Air conditioning in Hill Top East and Abington Hall

1,800,000

(Base Project Allocation - $1,500,000)

(Design and Contingencies - $300,000)

(ii) Farview State Hospital

(A) Renovation of sewage treatment system

1,500,000

(Base Project Allocation - $1,250,000)

(Design and Contingencies - $250,000)

(iii) Harrisburg State Hospital

(A) Upgrade electrical substation and switchgear

1,980,000

(Base Project Allocation - $1,650,000)

(Design and Contingencies - $330,000)

(B) Fire alarm system

648,000

(Base Project Allocation - $540,000)

(Design and Contingencies - $108,000)

(iv) Haverford State Hospital

(A) Secondary water supply system

180,000

(Base Project Allocation - $150,000)

(Design and Contingencies - $30,000)

(v) Norristown State Hospital

(A) Air Condition Patient Building No. 11

969,000

(Base Project Allocation - $774,000)

(Design and Contingencies - $195,000)

(B) Air Condition Patient Building No. 12

1,215,000

(Base Project Allocation - $972,000)

(Design and Contingencies - $243,000)

(vi) Torrance State Hospital

(A) Reservoir cover

211,000

(Base Project Allocation - $176,000)

(Design and Contingencies - $35,000)

(vii) Wernersville State Hospital

(A) Air condition Building No. 34

1,728,000

(Base Project Allocation - $1,440,000)

(Design and Contingencies - $288,000)

(B) Replace heating system in Building No. 30

462,000

(Base Project Allocation - $385,000)

(Design and Contingencies - $77,000)

(C) Air condition Building No. 35

1,582,000

(Base Project Allocation - $1,320,000)

(Design and Contingencies - $262,000)

(D) Air condition Building No. 37

1,020,000

(Base Project Allocation - $850,000)

(Design and Contingencies - $170,000)

((D) amended July 11, 1989, P.L.320, No.54)

(viii) Phillipsburg State General Hospital

(A) Renovations and capital improvements

5,000,000

(Base Project Allocation - $4,200,000)

(Design and Contingencies - $800,000)

(B) Renovations, including relocation and remodeling, and air conditioning in main hospital building

9,025,000

(Base Project Allocation - $7,525,000)

(Design and Contingencies - $1,500,000)

(ix) Scranton State General Hospital

(A) Renovations to existing structure

3,300,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $300,000)

(x) Ebensburg State Center

(A) Upgrade electrical system and install air conditioning in Unit IV

620,000

(Base Project Allocation - $517,000)

(Design and Contingencies - $103,000)

(xi) Embreeville Center

(A) Upgrade heating system and install air conditioning in Towerview Building

858,000

(Base Project Allocation - $715,000)

(Design and Contingencies - $143,000)

(xii) Hamburg Center

(A) Install central chilled air conditioning and heating units in Pine Hall

368,000

(Base Project Allocation - $225,000)

(Design and Contingencies - $143,000)

(xiii) Laurelton Center

(A) Water filtration system

660,000

(Base Project Allocation - $550,000)

(Design and Contingencies - $110,000)

(B) Air condition the hospital building

977,000

(Base Project Allocation - $814,000)

(Design and Contingencies - $163,000)

(C) Construction of a therapeutic swimming pool

835,000

(Base Project Allocation - $685,000)

(Design and Contingencies - $150,000)

(xiv) Polk Center

(A) Air condition the Meadowside Building

1,380,000

(Base Project Allocation - $1,150,000)

(Design and Contingencies - $230,000)

(xv) Selinsgrove Center

(A) Installation of elevators in central building

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(B) Install new baths in central building

852,000

(Base Project Allocation - $710,000)

(Design and Contingencies - $142,000)

(xvi) Warren State Hospital

(A) Exterior renovation/improvement to Israel Building

2,160,000

(Base Project Allocation - $1,800,000)

(Design and Contingencies - $360,000)

(xvii) Western Center

(A) Demolition of Building No. 40

132,000

(Base Project Allocation - $110,000)

(Design and Contingencies - $22,000)

(xviii) Western Pennsylvania Childrens' Intensive Treatment Unit

(A) Construction of three living units

375,000

(Base Project Allocation - $337,500)

(Design and Contingencies - $37,500)

(B) Renovation of eight garages into classrooms

50,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $5,000)

(C) Renovation of two-story administrative structure

22,000

(Base Project Allocation - $20,000)

(Design and Contingencies - $2,000)

(D) Renovation of recreational facility, including supervisor's office and recreational office

50,000

(Base Project Allocation - $45,000)

(Design and Contingencies - $5,000)

(xix) Western Psychiatric Institute and Clinic

(A) Construction of a children and youth center

12,000,000

(Base Project Allocation - $10,000,000)

(Design and Contingencies - $2,000,000)

(B) Infrastructure improvements of Western Center

1,950,000

(Base Project Allocation - $1,950,000)

(xx) Adult Vocational Rehabilitation Center

(A) Design and construction of an adult vocational rehabilitation center in Indiana County

400,000

(Base Project Allocation - $400,000)

(xxi) New Castle Youth Development Center

(A) Education Building

1,320,000

(Base Project Allocation - $1,100,000)

(Design and Contingencies - $220,000)

(B) Construction of new educational facility

1,200,000

(Base Project Allocation - $1,000,000)

(Design and Contingencies - $200,000)

(11) State Police

$8,364,000

(i) State Police Academy

(A) Renovation

5,527,000

(Base Project Allocation - $4,556,000)

(Design and Contingencies - $971,000)

(ii) Bethlehem Headquarters

Additional funds for Project No. DGS 206-3; Renovation and Expansion of Troop "M" Headquarters Building

502,000

(Base Project Allocation - $419,000)

(Design and Contingencies - $83,000)

(iii) Hollidaysburg Barracks

(A) Additional funds for DGS 201-3; renovation and expansion of headquarters building

307,000

(Base Project Allocation - $307,000)

(iv) Lancaster County Station

(A) Renovation and Addition

2,028,000

(Base Project Allocation - $1,690,000)

(Design and Contingencies - $338,000)

(12) State System of Higher Education

$162,052,000

(i) Bloomsburg State University

(A) Automatic fire detection/alarm system

307,000

(Base Project Allocation - $256,000)

(Design and Contingencies - $51,000)

(B) Steam line improvements

1,258,000

(Base Project Allocation - $1,048,000)

(Design and Contingencies - $210,000)

(C) Construction of a new library

11,400,000

(Base Project Allocation - $9,500,000)

(Design and Contingencies - $1,900,000)

(ii) California State University

(A) Automatic fire detection/alarm system

275,000

(Base Project Allocation - $229,000)

(Design and Contingencies - $46,000)

(B) Renovations to Hamer Gymnasium

4,128,000

(Base Project Allocation - $3,440,000)

(Design and Contingencies - $688,000)

(C) Construction of Science and Technology/Math and Earth Science Building

13,718,000

(Base Project Allocation - $11,157,000)

(Land Allocation - $300,000)

(Design and Contingencies - $2,261,000)

(D) Addition of funds to DGS 402-46 to include installation of boilers to permit summer shutdown

550,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $50,000)

(iii) Cheyney State University

(A) Renovation of Biddle Hall

1,625,000

(Base Project Allocation - $1,354,000)

(Design and Contingencies - $271,000)

(B) Additional funds for DGS 403-57; renovation of Armstrong House

220,000

(Base Project Allocation - $200,000)

(Design and Contingencies - $20,000)

(C) Air conditioning of buildings

1,000,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $100,000)

(D) Construction of multipurpose center

11,400,000

(Base Project Allocation - $9,500,000)

(Design and Contingencies - $1,900,000)

(E) Renovation of dining area

650,000

(Base Project Allocation - $585,000)

(Design and Contingencies - $65,000)

(F) Elevator replacements

1,000,000

(Base Project Allocation - $900,000)

(Design and Contingencies - $100,000)

(G) Complete landscaping of campus

500,000

(Base Project Allocation - $450,000)

(Design and Contingencies - $50,000)

(H) Renovation of building for hospitality center

300,000

(Base Project Allocation - $270,000)

(Design and Contingencies - $30,000)

(I) Additional funds for DGS 403-54; Renovations to Tubman Hall, Robinson Hall, Yarnall Hall, King Hall and Truth Hall

3,200,000

(Base Project Allocation - $2,667,000)

(Design and Contingencies - $533,000)

(J) Addition of funds to DGS 403-54 to complete renovations of five dorms as part of the Commonwealth Enhancement Plan

3,960,000

(Base Project Allocation - $3,300,000)

(Design and Contingencies - $660,000)

(iv) Clarion State University

(A) Renovation of Founders Hall

2,189,000

(Base Project Allocation - $1,824,000)

(Design and Contingencies - $365,000)

(B) Upgrade building system in Carlson, Tippen, Marwick-Boyd and Frame Halls

1,560,000

(Base Project Allocation - $1,300,000)

(Design and Contingencies - $260,000)

(C) Renovation of Harvey Hall

840,000

(Base Project Allocation - $700,000)

(Design and Contingencies - $140,000)

(v) East Stroudsburg State University

(A) Renovation of Gessner Science Center

1,758,000

(Base Project Allocation - $1,465,000)

(Design and Contingencies - $293,000)

(vi) Edinboro State University

(A) Automatic fire detection/alarm system

479,000

(Base Project Allocation - $399,000)

(Design and Contingencies - $80,000)

(B) Renovation of Loveland Hall

300,000

(Base Project Allocation - $250,000)

(Design and Contingencies - $50,000)

(C) Upgrade entire electrical system

2,220,000

(Base Project Allocation - $1,850,000)

(Design and Contingencies - $370,000)

(D) Construction of disabled student service facility

6,222,000

(Base Project Allocation - $5,185,000)

(Design and Contingencies - $1,037,000)

(E) Replacement of PCB Transformers

396,000

(Base Project Allocation - $330,000)

(Design and Contingencies - $66,000)

(vii) Indiana State University

(A) Automatic fire detection/alarm system

594,000

(Base Project Allocation - $495,000)

(Design and Contingencies - $99,000)

(B) Phase II renovation of Weyandt Hall

4,800,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $800,000)

(C) Construction of College of Business classroom building

10,371,000

(Base Project Allocation - $8,988,000)

(Design and Contingencies - $1,383,000)

(viii) Kutztown State University

(A) Automatic fire detection/alarm system

350,000

(Base Project Allocation - $292,000)

(Design and Contingencies - $58,000)

(B) Upgrade electrical distribution system

924,000

(Base Project Allocation - $770,000)

(Design and Contingencies - $154,000)

(C) Phase II renovation of Old Main

4,500,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $750,000)

(D) Addition to the library

7,745,000

(Base Project Allocation - $7,745,000)

(E) Renovation of the learning center

2,100,000

(Base Project Allocation - $2,100,000)

(F) Addition to de Francesco Building

1,870,000

(Base Project Allocation - $1,870,000)

(G) Upgrading of athletic facility

2,800,000

(Base Project Allocation - $2,800,000)

(ix) Lock Haven State University

(A) Automatic fire detection/alarm system

179,000

(Base Project Allocation - $149,000)

(Design and Contingencies - $30,000)

(B) Phase III renovation to Jack Stadium and related facilities

723,000

(Base Project Allocation - $602,000)

(Design and Contingencies - $121,000)

(C) Renovation of Ulmer Hall

2,420,000

(Base Project Allocation - $2,016,000)

(Design and Contingencies - $404,000)

(D) Acquisition and construction of new parking facilities

1,550,000

(Base Project Allocation - $1,300,000)

(Design and Contingencies - $250,000)

(x) Mansfield State University

(A) Automatic fire detection/alarm system

158,000

(Base Project Allocation - $132,000)

(Design and Contingencies - $26,000)

(B) Renovate Allen Hall

2,880,000

(Base Project Allocation - $2,400,000)

(Design and Contingencies - $480,000)

(C) Renovation of Straughn Auditorium

2,066,000

(Base Project Allocation - $1,722,000)

(Design and Contingencies - $344,000)

(xi) Millersville State University

(A) Automatic fire detection/alarm system

551,000

(Base Project Allocation - $459,000)

(Design and Contingencies - $92,000)

(B) Intersection improvements and new traffic light

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(C) Rehabilitation of Myers Hall

1,600,000

(Base Project Allocation - $1,280,000)

(Design and Contingencies - $320,000)

(D) Addition to Roddy Science Center, Phase II

11,955,000

(Base Project Allocation - $9,962,000)

(Design and Contingencies - $1,993,000)

(xii) Shippensburg State University

(A) Automatic fire detection/alarm system

298,000

(Base Project Allocation - $248,000)

(Design and Contingencies - $50,000)

(B) Upgrade of electrical distribution system

1,069,000

(Base Project Allocation - $891,000)

(Design and Contingencies - $178,000)

(C) Construction of a computer addition to the Dauphin Humanities Center

4,500,000

(Base Project Allocation - $3,750,000)

(Design and Contingencies - $750,000)

(D) Completion of Old Main renovation

1,200,000

(Base Project Allocation - $1,200,000)

(xiii) Slippery Rock State University

(A) Renovation of the East-West instructional complex

2,395,000

(Base Project Allocation - $1,996,000)

(Design and Contingencies - $399,000)

(xiv) West Chester State University

(A) Automatic fire detection/alarm system

883,000

(Base Project Allocation - $736,000)

(Design and Contingencies - $147,000)

(B) Construction of an addition to the science center

9,996,000

(Base Project Allocation - $8,330,000)

(Design and Contingencies - $1,666,000)

(xv) State System of Higher Education

(A) Asbestos abatement program on all 14 campuses of the State system

10,000,000

(Base Project Allocation - $8,333,000)

(Design and Contingencies - $1,667,000)

(13) Department of Transportation

$161,276,00

(Amount amended July 11, 1989, P.L.320, No.54)

(i) Centre County

(A) Mid-State Airport - General improvements to airport facilities

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(ii) Harrisburg Area

(A) New testing laboratory

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(iii) Adams County

(A) New welcome center

2,580,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $430,000)

(Land Allocation - $150,000)

(iv) ((iv) deleted by amendment July 11, 1989, P.L.320, No.54)

(v) Clinton County

(A) Replacement and relocation of Maintenance District 2-3 Facility to Bald Eagle Township

3,000,000

(Base Project Allocation - $3,000,000)

(B) New welcome center - For the construction of a welcome center serving both east and westbound traffic on Interstate 80 in Clinton County between Exits 24 and 25, including a 2,400 sq. ft. building, parking areas with connecting ramps, utilities, site lighting and landscaping

3,400,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $400,000)

(vi) Columbia County

(A) Maintenance building

2,016,000

(Base Project Allocation - $1,680,000)

(Design and Contingencies - $336,000)

(vii) Erie County

(A) New welcome center

2,297,000

(Base Project Allocation - $1,841,000)

(Land Allocation - $80,000)

(Design and Contingencies - $376,000)

(viii) Elk County

(A) New county maintenance facility, District 2-8

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(ix) Fayette County

(A) Bullskin Township - Relocate road due to flood control project being constructed by U.S. Soil Conservation Service

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(x) Greene County

(A) Rest area and welcome center on Interstate 79, Site "D"

1,570,000

(Base Project Allocation - $1,300,000)

(Land Allocation - $10,000)

(Design and Contingencies - $260,000)

(xi) Lawrence County

(A) New Castle Airport Authority - Improvements to airport facilities

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(xii) Monroe County

(A) Welcome center

720,000

(Base Project Allocation - $600,000)

(Design and Contingencies - $120,000)

(xiii) Montour County

(A) Satellite maintenance building

600,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $100,000)

(B) For construction of transportation maintenance shed in the county

500,000

(Base Project Allocation - $500,000)

(xiv) Northampton County

(A) New welcome center

2,092,000

(Base Project Allocation - $1,674,000)

(Land Allocation - $75,000)

(Design and Contingencies - $343,000)

(xv) Northumberland County

(A) New county maintenance facility, District 3-4

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(xvi) Perry County

(A) Addition and alterations to garage

515,000

(Base Project Allocation - $429,000)

(Design and Contingencies - $86,000)

(B) New county maintenance facility, District 8-9

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(xvii) Pike County

(A) New welcome center

2,640,000

(Base Project Allocation - $2,000,000)

(Land Allocation - $200,000)

(Design and Contingencies - $440,000)

(xviii) Susquehanna County

(A) New welcome center

4,160,000

(Base Project Allocation - $3,360,000)

(Design and Contingencies - $800,000)

(B) New welcome center

4,800,000

(Base Project Allocation - $4,000,000)

(Design and Contingencies - $800,000)

(xix) Union County

(A) Construction of a welcome center at intersection of Interstate 80 and U.S. 15

2,400,000

(Base Project Allocation - $2,000,000)

(Design and Contingencies - $400,000)

(xx) Washington County

(A) New welcome center

2,298,000

(Base Project Allocation - $1,900,000)

(Land Allocation - $15,000)

(Design and Contingencies - $383,000)

(xxi) Port of Philadelphia

(A) Construct or purchase new paper warehouse at adjacent Piers 78-80

11,100,000

(Base Project Allocation - $11,100,000)

(B) Expansion of Tioga Fruit Shed

6,900,000

(Base Project Allocation - $6,900,000)

(C) Rehabilitation and replacement of container cranes

9,275,000

(Base Project Allocation - $8,439,000)

(Design and Contingencies - $836,000)

(D) Packer Avenue Marine Terminal improvements

3,741,000

(Base Project Allocation - $3,015,000)

(Design and Contingencies - $726,000)

(E) Dredging for Port of Philadelphia

550,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $50,000)

(F) Expansion and improvement of the fruit shed on Piers 82-84

6,430,000

(Base Project Allocation - $4,993,000)

(Design and Contingencies - $1,437,000)

(G) Tioga Marine Terminal general improvements

2,118,000

(Base Project Allocation - $1,626,000)

(Design and Contingencies - $492,000)

(H) Improvements to Piers 96 and 98 Annex

2,412,000

(Base Project Allocation - $2,171,000)

(Design and Contingencies - $241,000)

(I) Piers 78-80 general improvements

7,682,000

(Base Project Allocation - $5,734,000)

(Design and Contingencies - $1,948,000)

(J) Construct or purchase new shed for cocoa beans

4,605,000

(Base Project Allocation - $3,744,000)

(Design and Contingencies - $861,000)

(K) Development of facilities necessary to handle passenger cruise ships

633,000

(Base Project Allocation - $500,000)

(Design and Contingencies - $133,000)

(L) Piers 38-40 general improvements

1,972,000

(Base Project Allocation - $1,360,000)

(Design and Contingencies - $612,000)

(M) Philadelphia central riverfront district on Delaware Avenue from Reed Street to Spring Garden Street for construction of street improvements for movement of vehicles and pedestrians, including a river walk

17,000,000

(Base Project Allocation - $17,000,000)

(xxii) Port of Erie

(A) Improvements to the Port of Erie

5,400,000

(Base Project Allocation - $5,400,000)

(xxiii) Allegheny County

(A) Road improvements on L.R.02247, including curbing, sidewalks, handicapped access cuts and guide rails to be performed by Verona Borough

150,000

(Base Project Allocation - $135,000)

(Design and Contingencies - $15,000)

(xxiv) Delaware County Port Corporation

(A) Dredging and other improvements

25,000,000

(Base Project Allocation - $25,000,000)

(xxv) Philadelphia County

(A) Installation of sound barriers on the west side of Interstate 95 between Catherine Street and Porter Street

5,000,000

(Base Project Allocation - $5,000,000)