Section 19. Chester County.
(a) Local Bridges
Local
State
(1) Upper Oxford Township, Watermark Road at Muddy Run Road over Muddy Run, Bridge Replacement, Bridge Key 10651, Project ID 86696
Project Allocation
347,000
(Base Project Allocation - $241,000)
(Land Allocation - $13,000)
(Design & Contingencies - $93,000)
(2) New Garden Township, Auburn Road over East Branch of White Clay Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(3) Newlin Township, County Park Road over West Branch of Brandywine Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(4) Pocopson Township, Denton Hollow Road over Pocopson Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(5) Uwchlan Township, Dowlin Forge Road over Shamona Creek, Bridge Replacement or Rehabilitation
Project Allocation
400,000
(Base Project Allocation - $300,000)
(Land Allocation - $50,000)
(Design & Contingencies - $50,000)
(6) East Goshen Township, East Boot Road over Ridley Creek, Bridge Replacement or Rehabilitation
Project Allocation
500,000
(Base Project Allocation - $375,000)
(Land Allocation - $50,000)
(Design & Contingencies - $125,000)
(7) West Nottingham Township, Freemont Road over Octoraro Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(8) West Nottingham Township, Glenroy Road over Blackburn Run, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(9) East Coventry Township, Harley Road over Bickels Run, Bridge Replacement or Rehabilitation
Project Allocation
400,000
(Base Project Allocation - $350,000)
(Design & Contingencies - $50,000)
(10) Kennett Township, Hillendale Road over East Branch of Red Clay Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(11) West Caln Township, Lion's Head Road over Birch Run Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(12) East Nottingham Township, Little Elk Creek Road over Big Elk Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(13) Caln Township, Lloyd Avenue over Beaver Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(14) Tredyffrin Township, Mill Road over Valley Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(15) Valley Township, Mount Airy Road over Rock Run, Bridge Replacement or Rehabilitation
Project Allocation
470,000
(Base Project Allocation - $400,000)
(Land Allocation - $30,000)
(Design & Contingencies - $40,000)
(16) Westtown Township, New Street over Radley Run, Bridge Replacement or Rehabilitation
Project Allocation
1,400,000
(Base Project Allocation - $850,000)
(Land Allocation - $150,000)
(Design & Contingencies - $400,000)
(17) West Vincent Township, Old Kimberton Road over Tributary of Pickering, Arch, Bridge Replacement or Rehabilitation
Project Allocation
500,000
(Base Project Allocation - $400,000)
(Land Allocation - $20,000)
(Design & Contingencies - $80,000)
(18) West Vincent Township, Old Kimberton Road over Middle Tributary of Pickering, Bridge Replacement or Rehabilitation
Project Allocation
225,000
(Base Project Allocation - $200,000)
(Land Allocation - $5,000)
(Design & Contingencies - $20,000)
(19) Schuylkill Township, Old Route 23 over French Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(20) London Grove Township, Paschall Mill Road over Middle Branch White Clay Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(21) Schuylkill Township, Pawlings Road over Schuylkill River, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(22) South Coventry Township, Pigeon Creek Road over Pigeon Creek, Bridge Replacement or Rehabilitation
Project Allocation
410,000
(Base Project Allocation - $300,000)
(Land Allocation - $10,000)
(Design & Contingencies - $100,000)
(23) East Vincent Township, Pikeland Avenue over Stony Run, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(24) West Pikeland Township, Pikeland Road over Pickering Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(25) Upper Oxford Township, Pusey Mill Road over Big Elk Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(26) East Coventry Township, Sawmill Road over Bickels Run, Bridge Replacement or Rehabilitation
Project Allocation
315,000
(Base Project Allocation - $275,000)
(Design & Contingencies - $40,000)
(27) East Coventry Township, Schoolhouse Road over Tributary of Pigeon Creek, Bridge Replacement or Rehabilitation
Project Allocation
160,000
(Base Project Allocation - $140,000)
(Design & Contingencies - $20,000)
(28) East Coventry Township, Schoolhouse Road over Bickels Run, Bridge Replacement or Rehabilitation
Project Allocation
320,000
(Base Project Allocation - $280,000)
(Design & Contingencies - $40,000)
(29) East Coventry Township, Schoolhouse Road over Tributary of Bickels Run, Bridge Replacement or Rehabilitation
Project Allocation
140,000
(Base Project Allocation - $120,000)
(Design & Contingencies - $20,000)
(30) East Coventry Township, Spiece Road over Bickels Run, Bridge Replacement or Rehabilitation
Project Allocation
265,000
(Base Project Allocation - $230,000)
(Design & Contingencies - $35,000)
(31) Upper Uwchlan Township, Styer Road over Marsh Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(32) New Garden Township, Township Line Road over West Branch of Red Clay Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(33) Warwick Township, Valley Way over South Branch of French Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(34) Kennett Township, West South Street over West Branch of Red Clay Creek, Bridge Replacement or Rehabilitation
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(35) East Coventry Township, Zieber Road over Pigeon Creek, Bridge Replacement or Rehabilitation
Project Allocation
580,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $80,000)
(36) West Brandywine Township, Brandamore Road, T-349 over West Branch of Brandywine Creek, Bridge Rehabilitation or Replacement
Project Allocation
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(37) New Garden Township, PA 0041, Newport Pike over Kaolin Road, Bridge Rehabilitation or Replacement, BMS 15004100200000
Project Allocation
3,385,000
(Base Project Allocation - $2,900,000)
(Land Allocation - $50,000)
(Design & Contingencies - $435,000)
(38) Uwchlan Township, Downlin Forge Road over Shamona Creek, Bridge Rehabilitation, Restoration or Replacement
Project Allocation
100,000
(Base Project Allocation - $100,000)
(39) Uwchlan Township, Downlin Forge Road over Shamona Creek, Bridge Rehabilitation, Restoration or Replacement
Project Allocation
100,000
(Base Project Allocation - $100,000)
(40) Various Municipalities, Various Local Bridges over Various Spans, Bridge Preservation, Bridge Key 0, Project ID 0
Project Allocation
1,100,000
(Base Project Allocation - $1,000,000)
(Design & Contingencies - $100,000)
(b) State Bridges
(1) (Reserved).
(2) Leopard Road 3475-H6 over Branch of Darby Creek, Easttown Township, Bridge Rehabilitation, Bridge Key 10412, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(3) Mansion Road over South Branch of French Creek, Warwick Township, Bridge Rehabilitation, Bridge Key 10631, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(4) Hollow Road 3364C6 over Branch of Pickering Creek, Charlestown Township, Bridge Rehabilitation, Bridge Key 10348, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(5) Linfield Bridge, Parkerford over Schuylkill River, East Coventry Township, Bridge Preservation, Bridge Key 10361, Project ID 89701
Project Allocation
418,000
(Base Project Allocation - $418,000)
(6) Valley Park Road over Branch of Pickering Creek, Schuylkill Township, Bridge Rehabilitation, Bridge Key 10362, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(7) Boot Road over Amtrak, East Caln Township, Bridge Rehabilitation, Bridge Key 10398, Project ID 90612
Project Allocation
1,137,000
(Base Project Allocation - $1,137,000)
(8) Boot Road over Valley Creek, East Caln Township, Bridge Rehabilitation, Bridge Key 10399, Project ID 90612
Project Allocation
1,137,000
(Base Project Allocation - $1,137,000)
(9) Amtrak over Boot Road, East Caln Township, Bridge Rehabilitation, Bridge Key 10400, Project ID 90612
Project Allocation
1,137,000
(Base Project Allocation - $1,137,000)
(10) Pughtown Road over Branch of French Creek, East Vincent Township, Bridge Rehabilitation, Bridge Key 10353, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(11) State Road over Little Elk Creek, Elk Township, Bridge Replacement, Bridge Key 10416, Project ID 92146
Project Allocation
596,000
(Base Project Allocation - $596,000)
(12) Oxford Road over McDonald Run 3908-A5, East Nottingham Township, Bridge Rehabilitation, Bridge Key 10447, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(13) Kelton Pennock Road over West Branch of White Clay Creek, New London Township, Bridge Replacement, Bridge Key 10452, Project ID 92311
Project Allocation
2,000
(Base Project Allocation - $1,000)
(Design & Contingencies - $1,000)
(14) Third Street over East Branch of White Clay Creek, Avondale Borough, Bridge Rehabilitation, Bridge Key 10478, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(15) Ewing Road over Middle Branch of White Clay Creek, London Grove Township, Bridge Replacement, Bridge Key 10497, Project ID 81284
Project Allocation
2,000,000
(Base Project Allocation - $2,000,000)
(16) Brandywine Creek Road over Buck Run and Doe Run, Newlin Township, Bridge Rehabilitation, Bridge Key 10514, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(17) Grove Road over Broad Run Creek, West Whiteland Township, Bridge Rehabilitation, Bridge Key 10544, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(18) Amtrak over Olive Street, Caln Township, Bridge Rehabilitation, Bridge Key 10564, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(19) Bondsville Road over Branch of Beaver Creek 3470-K8, Caln Township, Bridge Rehabilitation, Bridge Key 10607, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(20) Yellow Springs Road over Branch of Pickering Creek, West Pikeland Township, Bridge Rehabilitation, Bridge Key 10339, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(21) Downingtown Pike over East Branch of Brandywine Creek, West Bradford Township, Bridge Replacement, Bridge Key 10199, Project ID 92733
Project Allocation
4,675,000
(Base Project Allocation - $4,675,000)
(22) Swan Road over Officers Run, West Sadsbury Township, Bridge Rehabilitation, Bridge Key 10569, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(23) Street Road over Branch of Chester Creek, Thornbury Township, Bridge Rehabilitation, Bridge Key 10285, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(24) Bondsville Road over Branch of Beaver Creek, Caln Township, Bridge Replacement, Bridge Key 10215, Project ID 92311
Project Allocation
2,000
(Base Project Allocation - $1,000)
(Design & Contingencies - $1,000)
(25) Creek Road over Branch of Brandywine Creek, East Brandywine Township, Bridge Replacement, Bridge Key 10174, Project ID 92311
Project Allocation
753,000
(Base Project Allocation - $645,000)
(Design & Contingencies - $108,000)
(26) Creek Road over East Branch of Red Clay Creek, Kennett Township, Bridge Replacement, Bridge Key 10055, Project ID 92810
Project Allocation
4,565,000
(Base Project Allocation - $4,565,000)
(27) Doe Run Road over Buck Run, East Fallowfield Township, Bridge Replacement, Bridge Key 10045, Project ID 84284
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(28) Doe Run Road over Branch of Sucker Run, East Fallowfield Township, Bridge Replacement, Bridge Key 10044, Project ID 92311
Project Allocation
576,000
(Base Project Allocation - $493,000)
(Design & Contingencies - $83,000)
(29) SR 0041, Newport Pike over Officers Run, Atglen Borough, Bridge Replacement, Bridge Key 10021, Project ID 69918
Project Allocation
4,475,000
(Base Project Allocation - $3,700,000)
(Land Allocation - $250,000)
(Design & Contingencies - $525,000)
(30) Valley Forge Road Near Phoenixville over Pickering Creek, Schuylkill Township, Bridge Rehabilitation, Bridge Key 9947, Project ID 89697
Project Allocation
663,000
(Base Project Allocation - $663,000)
(31) Whitehorse Road over Branch of Pickering Creek, Schuylkill Township, Bridge Replacement, Bridge Key 10303, Project ID 92311
Project Allocation
487,000
(Base Project Allocation - $417,000)
(Design & Contingencies - $70,000)
(32) Conestoga Road over Branch of Pickering Creek, West Vincent Township, Bridge Rehabilitation, Bridge Key 10229, Project ID 88419
Project Allocation
667,000
(Base Project Allocation - $667,000)
(33) Clay Creek Road 2.0 Miles from South Avondale 46E13 over Tributary of East Branch of White Clay Creek, Franklin Township, Bridge Replacement, Bridge Key 39994, Project ID 92311
Project Allocation
2,000
(Base Project Allocation - $1,000)
(Design & Contingencies - $1,000)
(34) PA 282 over Indian Run Creek, Wallace Township, Bridge Replacement or Rehabilitation
Project Allocation
1,124,000
(Base Project Allocation - $914,000)
(Land Allocation - $10,000)
(Design & Contingencies - $200,000)
(35) (Reserved).
(36) (Reserved).
(37) PA 841 over Middle Branch of White Clay Creek, Franklin Township, Bridge Replacement or Rehabilitation
Project Allocation
1,750,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $50,000)
(Design & Contingencies - $500,000)
(38) (Reserved).
(39) (Reserved).
(40) Suplee Road over East Branch of Brandywine Creek, Honeybrook Township, Bridge Replacement or Rehabilitation
Project Allocation
810,000
(Base Project Allocation - $650,000)
(Land Allocation - $10,000)
(Design & Contingencies - $150,000)
(41) Various State-Owned Bridges over Various Spans, Various Municipalities, Bridge Preservation, Bridge Key 0, Project ID 0
Project Allocation
1,100,000
(Base Project Allocation - $1,000,000)
(Design & Contingencies - $100,000)