Section 38. Juniata County.
(a) Local Bridges
Local
State
(1) Tuscarora Township, T-322, Dobbs Road over Willow Run, Bridge Replacement, Bridge Key 20352, Project ID 95964
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(2) Lack Township, T-307 over George Creek, Bridge Replacement, Bridge Key 20337, Project ID 95955
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(3) Walker Township, T-351, Deerville Road 1.0 Mile North of Mexico over Cedar Spring Run, Bridge Replacement, Bridge Key 20354, Project ID 95967
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(4) Spruce Hill Township, T-343 over Tributary of Tuscarora Creek, Bridge Replacement, Bridge Key 20344, Project ID 95684
Project Allocation
1,452,000
(Base Project Allocation - $553,000)
(Land Allocation - $208,000)
(Design & Contingencies - $691,000)
(5) Spruce Hill Township, T-343 over Tributary of Tuscarora Creek, Bridge Replacement, Bridge Key 20344, Project ID 95689
Project Allocation
1,951,000
(Base Project Allocation - $975,000)
(Land Allocation - $225,000)
(Design & Contingencies - $751,000)
(6) Milford Township, T-379 over East Licking Creek, Bridge Replacement, Bridge Key 46001, Project ID 95970
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(7) Milford Township, T-360 over Licking Creek, Bridge Replacement, Bridge Key 20341, Project ID 95682
Project Allocation
1,452,000
(Base Project Allocation - $553,000)
(Land Allocation - $208,000)
(Design & Contingencies - $691,000)
(8) Milford Township, T-359 over East Licking Creek, Bridge Replacement, Bridge Key 0, Project ID 95690
Project Allocation
920,000
(Base Project Allocation - $400,000)
(Land Allocation - $120,000)
(Design & Contingencies - $400,000)
(9) Lack Township, T-371, Black Log Road 4.5 Miles Southwest of SR 4005 over Black Log Creek, Bridge Replacement, Bridge Key 20338, Project ID 95959
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(10) Fermanagh Township, T-527, Arch Rock Road over Big Run, Bridge Replacement, Bridge Key 20333, Project ID 95963
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(11) Fermanagh Township, T-410, Mill Road, Village of Jericho Mills over Lost Creek, Bridge Replacement, Bridge Key 20331, Project ID 95681
Project Allocation
3,251,000
(Base Project Allocation - $2,167,000)
(Land Allocation - $250,000)
(Design & Contingencies - $834,000)
(12) Fayette Township, T-602, Leonard Road over Little Lost Creek, Bridge Replacement, Bridge Key 20329, Project ID 95678
Project Allocation
1,351,000
(Base Project Allocation - $473,000)
(Land Allocation - $203,000)
(Design & Contingencies - $675,000)
(13) Fayette Township, T-602 Leonard Road over Little Lost Creek, Bridge Replacement, Bridge Key 20321, Project ID 95679
Project Allocation
1,502,000
(Base Project Allocation - $594,000)
(Land Allocation - $210,000)
(Design & Contingencies - $698,000)
(14) Fayette Township, T-558, Whitehall Road over West Branch of Cocolamus Creek, Bridge Replacement, Bridge Key 20327, Project ID 95683
Project Allocation
1,602,000
(Base Project Allocation - $676,000)
(Land Allocation - $214,000)
(Design & Contingencies - $712,000)
(15) Fayette Township, T-556, Foundry Road over Little Cocolamus Creek, Bridge Replacement, Bridge Key 20326, Project ID 95957
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(16) Fayette Township, T-556, Foundry Road over Little Cocolamus Creek, Bridge Replacement, Bridge Key 20325, Project ID 95968
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(17) Fermanagh Township, T-533 1.5 Miles Northwest of Arch Rock over Macedonia Run, Bridge Replacement, Bridge Key 44383, Project ID 95972
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(18) Fayette Township, T-535, Sunset Drive over Laurel Run, Bridge Replacement, Bridge Key 20324, Project ID 95961
Project Allocation
1,082,000
(Base Project Allocation - $636,000)
(Land Allocation - $64,000)
(Design & Contingencies - $382,000)
(19) Walker Township, T-455, Red Rock Road 600 Feet North of SR 2005 over Doe Run, Bridge Replacement, Bridge Key 20355, Project ID 95284
Project Allocation
1,051,000
(Base Project Allocation - $788,000)
(Land Allocation - $66,000)
(Design & Contingencies - $197,000)
(20) Delaware Township, T-436, East Salem Road over Delaware Creek, Bridge Replacement, Bridge Key 20312, Project ID 95680
Project Allocation
1,452,000
(Base Project Allocation - $553,000)
(Land Allocation - $208,000)
(Design & Contingencies - $691,000)
(21) Greenwood Township, T-475, Meiser Road over Cocolamus Creek, Bridge Replacement, Bridge Key 20335, Project ID 95675
Project Allocation
1,652,000
(Base Project Allocation - $718,000)
(Land Allocation - $216,000)
(Design & Contingencies - $718,000)
(22) Various Municipalities, Various Local Bridges over Various Spans, Bridge Preservation, Bridge Key 0, Project ID 0
Project Allocation
1,100,000
(Base Project Allocation - $1,000,000)
(Design & Contingencies - $100,000)
(b) State Bridges
(1) US 22 1.0 Mile West of Thompsontown over SR 2009, Delaware Township, Bridge Rehabilitation and Preservation, Bridge Key 19944, Project ID 91065
Project Allocation
20,000
(Design & Contingencies - $20,000)
(2) US 22 Thompsontown over PA 333, Delaware Township, Bridge Rehabilitation, Bridge Key 19945, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(3) SR 0035, PA 35 over Lost Creek, Fayette Township, Bridge Replacement, Bridge Key 19990, Project ID 88652
Project Allocation
500,000
(Design & Contingencies - $500,000)
(4) US 22 1.0 Mile East of Thompsontown over TR 554, Delaware Township, Bridge Rehabilitation, Bridge Key 19950, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(5) SR 3021 1.0 Mile Southeast of McCoysville over Tributary of Tuscarora Creek, Tuscarora Township, Bridge Replacement, Bridge Key 20280, Project ID 93955
Project Allocation
740,000
(Base Project Allocation - $400,000)
(Land Allocation - $54,000)
(Design & Contingencies - $286,000)
(6) SR 3023 2.0 Miles Southeast of Cross Keys over Lick Run, Lack Township, Bridge Replacement, Bridge Key 20286, Project ID 88588
Project Allocation
524,000
(Base Project Allocation - $325,000)
(Land Allocation - $17,000)
(Design & Contingencies - $182,000)
(7) SR 0035 Nook over Tributary of Doyle Run, Beale Township, Bridge Replacement, Bridge Key 19969, Project ID 93955
Project Allocation
649,000
(Base Project Allocation - $351,000)
(Land Allocation - $47,000)
(Design & Contingencies - $251,000)
(8) PA 35 1.0 Mile Northeast of Cross Keys over Willow Run, Lack Township, Bridge Rehabilitation, Bridge Key 19960, Project ID 69400
Project Allocation
19,000
(Base Project Allocation - $19,000)
(9) US 22 1.0 Mile Southeast of Thompsontown over TR 554, Delaware Township, Bridge Rehabilitation, Bridge Key 19953, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(10) SR 3014 2.0 Miles South of Nook over Doyle Run, Beale Township, Bridge Rehabilitation, Bridge Key 20261, Project ID 94970
Project Allocation
160,000
(Base Project Allocation - $160,000)
(11) US 22 Thompsontown over TR 466, Delaware Township, Bridge Rehabilitation, Bridge Key 19949, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(12) SR 3011 2.0 Miles Southwest of Mifflin over Licking Creek, Milford Township, Bridge Replacement, Bridge Key 20252, Project ID 91520
Project Allocation
3,527,000
(Base Project Allocation - $2,612,000)
(Land Allocation - $196,000)
(Design & Contingencies - $719,000)
(13) US 22 Thompsontown over PA 333, Delaware Township, Bridge Rehabilitation, Bridge Key 19946, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(14) SR 3013 Academia over Tributary of Tuscarora Creek, Beale Township, Bridge Replacement, Bridge Key 20254, Project ID 93955
Project Allocation
831,000
(Base Project Allocation - $449,000)
(Land Allocation - $61,000)
(Design & Contingencies - $321,000)
(15) (Reserved).
(16) US 22 1.0 Mile West of Thompsontown over SR 2009, Delaware Township, Bridge Rehabilitation, Bridge Key 19943, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(17) US 22 2.0 Miles West of Thompsontown over SR 2007 and Locust Run, Walker Township, Bridge Rehabilitation, Bridge Key 19940, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(18) US 22 4.0 Miles West of Thompsontown over SR 2005, Walker Township, Bridge Rehabilitation, Bridge Key 19936, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(19) US 22 Thompsontown over Township Road 466, Delaware Township, Bridge Rehabilitation, Bridge Key 19948, Project ID 91065
Project Allocation
1,000
(Design & Contingencies - $1,000)
(20) PA 235 1.0 Mile Southeast of Seven Stars over Cranes Run, Greenwood Township, Bridge Replacement, Bridge Key 20045, Project ID 93942
Project Allocation
800,000
(Base Project Allocation - $800,000)
(21) PA 35 McAlisterville over Tributary of Lost Creek, Fayette Township, Bridge Replacement, Bridge Key 19992, Project ID 88195
Project Allocation
1,557,000
(Base Project Allocation - $978,000)
(Land Allocation - $109,000)
(Design & Contingencies - $470,000)
(22) PA 35 2.0 Miles West of Cocolamus over Tributary of Cocolamus Creek, Fayette Township, Bridge Replacement, Bridge Key 19994, Project ID 88175
Project Allocation
411,000
(Base Project Allocation - $263,000)
(Land Allocation - $33,000)
(Design & Contingencies - $115,000)
(23) PA 74 2.0 Miles Northeast of Spruce Hill over Hunters Creek, Turbett Township, Bridge Rehabilitation, Bridge Key 20001, Project ID 94970
Project Allocation
160,000
(Base Project Allocation - $160,000)
(24) PA 75 over Tuscarora Creek, Lack Township, Bridge Replacement, Bridge Key 20005, Project ID 91524
Project Allocation
220,000
(Base Project Allocation - $220,000)
(25) PA 75 1.0 Mile Northeast of East Waterford over Tributary of Tuscarora Creek, Tuscarora Township, Bridge Rehabilitation, Bridge Key 20023, Project ID 69400
Project Allocation
12,000
(Base Project Allocation - $12,000)
(26) PA 75 1.0 Mile Northeast of Waterford over Tributary of Tuscarora Creek, Tuscarora Township, Bridge Rehabilitation, Bridge Key 20024, Project ID 69400
Project Allocation
27,000
(Base Project Allocation - $27,000)
(27) SR 0075 1.0 Mile Southwest of Spruce Hill over Esh's Run, Spruce Hill Township, Bridge Replacement, Bridge Key 20030, Project ID 93955
Project Allocation
1,110,000
(Base Project Allocation - $600,000)
(Land Allocation - $81,000)
(Design & Contingencies - $429,000)
(28) PA 75 1.0 Mile Southwest of Spruce Hill over Esh's Run, Spruce Hill Township, Bridge Replacement, Bridge Key 20030, Project ID 91515
Project Allocation
812,000
(Base Project Allocation - $476,000)
(Land Allocation - $63,000)
(Design & Contingencies - $273,000)
(29) SR 3014 2.0 Miles South of Nook over Doyle Run, Beale Township, Bridge Replacement, Bridge Key 20261, Project ID 91516
Project Allocation
468,000
(Base Project Allocation - $134,000)
(Design & Contingencies - $334,000)
(30) PA 75 2.0 Miles Northeast of Port Royal over US 22, Walker Township, Bridge Rehabilitation, Bridge Key 20040, Project ID 50579
Project Allocation
1,551,000
(Base Project Allocation - $1,279,000)
(Land Allocation - $136,000)
(Design & Contingencies - $136,000)
(31) SR 3008 over Tributary of Doyle Run, Beale Township, Bridge Replacement, Bridge Key 20234, Project ID 93955
Project Allocation
831,000
(Base Project Allocation - $449,000)
(Land Allocation - $61,000)
(Design & Contingencies - $321,000)
(32) PA 235 McAlisterville over Little Lost Creek, Fayette Township, Bridge Replacement, Bridge Key 20057, Project ID 91519
Project Allocation
456,000
(Base Project Allocation - $114,000)
(Design & Contingencies - $342,000)
(33) SR 2006 Van Wert over Doe Run, Walker Township, Bridge Replacement, Bridge Key 20137, Project ID 81508
Project Allocation
925,000
(Base Project Allocation - $445,000)
(Land Allocation - $90,000)
(Design & Contingencies - $390,000)
(34) SR 2019 at Seven Stars over Cabala Run, Greenwood Township, Bridge Restoration, Bridge Key 20187, Project ID 92421
Project Allocation
54,000
(Base Project Allocation - $50,000)
(Design & Contingencies - $4,000)
(35) SR 2017 near PA 35 over Tributary of Cocolamus Creek, Monroe Township, Bridge Replacement, Bridge Key 20180, Project ID 91962
Project Allocation
400,000
(Base Project Allocation - $300,000)
(Design & Contingencies - $100,000)
(36) SR 2012 3.0 Miles East of Cocolamus over Tributary of Stony Run, Monroe Township, Bridge Replacement, Bridge Key 20157, Project ID 88175
Project Allocation
513,000
(Base Project Allocation - $328,000)
(Land Allocation - $41,000)
(Design & Contingencies - $144,000)
(37) SR 2007 Oakland Mills over Lost Creek, Fayette Township, Bridge Replacement, Bridge Key 20147, Project ID 91518
Project Allocation
920,000
(Base Project Allocation - $446,000)
(Land Allocation - $89,000)
(Design & Contingencies - $385,000)
(38) PA 75 2.0 Miles Northeast of Port Royal over US 22, Walker Township, Bridge Rehabilitation, Bridge Key 20040, Project ID 97529
Project Allocation
118,000
(Base Project Allocation - $118,000)
(39) SR 2006 over Delaware Creek, Delaware Township, Bridge Restoration, Bridge Key 20138 Project ID 90248
Project Allocation
325,000
(Base Project Allocation - $325,000)
(40) PA 333 1.0 Mile South of Port Royal over Blue Spring Run, Turbett Township, Bridge Replacement, Bridge Key 20070, Project ID 81485
Project Allocation
861,000
(Base Project Allocation - $463,000)
(Land Allocation - $102,000)
(Design & Contingencies - $296,000)
(41) SR 2003 0.5 Mile North of Mexico over Doe Run, Walker Township, Bridge Replacement, Bridge Key 20125, Project ID 101634
Project Allocation
2,502,000
(Base Project Allocation - $1,667,000)
(Land Allocation - $193,000)
(Design & Contingencies - $642,000)
(42) SR 1006 North of Horningtown Road over Horning Run, Fermanagh Township, Bridge Restoration, Bridge Key 20120, Project ID 90249
Project Allocation
402,000
(Base Project Allocation - $402,000)
(43) SR 1003 South of Mountain Road over Tributary of Tennis Run, Fayette Township, Bridge Replacement, Bridge Key 20116, Project ID 88209
Project Allocation
525,000
(Base Project Allocation - $250,000)
(Land Allocation - $100,000)
(Design & Contingencies - $175,000)
(44) SR 1002 South of US 22 over Lost Creek, Fermanagh Township, Bridge Restoration, Bridge Key 20106, Project ID 90249
Project Allocation
402,000
(Base Project Allocation - $402,000)
(45) PA 850 1.0 Mile North of Honey Grove over Little Laurel Run, Tuscarora Township, Bridge Rehabilitation, Bridge Key 20100, Project ID 94970
Project Allocation
160,000
(Base Project Allocation - $160,000)
(46) PA 850 1.0 Mile North of Honey Grove over Tuscarora Creek, Tuscarora Township, Bridge Rehabilitation, Bridge Key 20097, Project ID 69400
Project Allocation
366,000
(Base Project Allocation - $366,000)
(47) Various State-Owned Bridges over Various Spans, Various Municipalities, Bridge Preservation, Bridge Key 0, Project ID 0
Project Allocation
1,100,000
(Base Project Allocation - $1,000,000)
(Design & Contingencies - $100,000)