Berks County

Act 128 of 2008, § 306, under HIGHWAY CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2008-2009 - ENACTMENT.

Act 128 of 2008, § 306

Section 306. Berks County.

Projects are as follows:

(1) SR 1010, Intersection Signalization, SR 1010 and Dries Road Intersection, Ontelaunee Township

200,000

(Base Project Allocation - $50,000)

(Design and Contingencies - $150,000)

(2) SR 1021, Safety Improvement, Tree Cutting, Excavating and Shoulder Work, SR 1021 and SR 1024, Long Lane Intersection, Maxatawny Township

325,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $250,000)

(3) SR 12, Excavating, Embankment, Shoulders, Guide Rail and Utility Poles, SR 12, Safety Improvements, Alsace Township

600,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $500,000)

(4) SR 222, Highway Reconstruction, SR 222, North Corridor Phase I, Maidencreek, Ontelaunee and Richmond Townships

36,600,000

(Base Project Allocation - $30,600,000)

(Land Allocation - $2,800,000)

(Design and Contingencies - $3,200,000)

(5) SR 222, Install Closed Circuit Television Cameras, Route 222, Nonurban Area, Various Municipalities

1,124,000

(Base Project Allocation - $254,000)

(Land Allocation - $20,000)

(Design and Contingencies - $850,000)

(6) SR 222 and SR 422, Installation of Dynamic Message Signs, SR 222 and SR 422, Nonurban Area, Various Municipalities

410,000

(Base Project Allocation - $250,000)

(Land Allocation - $15,000)

(Design and Contingencies - $145,000)

(7) SR 222 and SR 422, Installation of Variable Message Signs and Closed Circuit Television Cameras, SR 222 and SR 422 Urban Area, Various Municipalities

390,000

(Base Project Allocation - $225,000)

(Land Allocation - $15,000)

(Design and Contingencies - $150,000)

(8) SR 3008, Intersection Improvement and Curve Safety Improvements, SR 3008, Segment 50 to Segment 60, Lower Heidelberg and North Heidelberg Townships

300,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $225,000)

(9) SR 3023, Curve Safety Improvements, SR 3023, Vicinity of Evans Hill Road and Sweitzer Road, Lower Heidelberg Township

300,000

(Base Project Allocation - $75,000)

(Design and Contingencies - $225,000)

(10) SR 422, Congestion Reduction, Safety Improvements, Penn Avenue, SR 422 Corridor, Robesonia, Sinking Spring and Wernersville Boroughs, Heidelberg, Lower Heidelberg and South Heidelberg Townships

360,000

(Base Project Allocation - $285,000)

(Land Allocation - $15,000)

(Design and Contingencies - $60,000)

(11) SR 562, Intersection Improvement, Congestion Mitigation, SR 562, Intersection of Shelbourne Road, Boyertown Pike and Oley Turnpike Road, Exeter and Oley Townships

400,000

(Base Project Allocation - $100,000)

(Land Allocation - $40,000)

(Design and Contingencies - $260,000)

(12) SR 78, Replacement of Precast Parapets, RATS Precast Parapets, Greenwich Township

475,000

(Base Project Allocation - $20,000)

(Design and Contingencies - $455,000)

(13) SR 78, Safety Gates, SR 78 Corridor, Various Municipalities

525,000

(Base Project Allocation - $525,000)

(14) SR 78, Installation of Closed Circuit Television Cameras, Highway Advisory Radio, Changeable Message Signs, I-78 Corridor and SR 61 into I-78 Intersection, Various Municipalities

490,000

(Base Project Allocation - $360,000)

(Land Allocation - $15,000)

(Design and Contingencies - $115,000)

(15) SR 78, Install Tenth Mile Location Markers, Safety Improvement, I-78 Corridor, Various Municipalities

102,000

(Base Project Allocation - $7,000)

(Design and Contingencies - $95,000)

(16) I-176, Interstate Restoration and Reconstruction

11,100,000

(Base Project Allocation - $11,100,000)

(17) I-78, Interstate Restoration and Reconstruction

38,500,000

(Base Project Allocation - $38,500,000)

(18) SR 183, Intersection Improvement

268,000

(Base Project Allocation - $111,000)

(Land Allocation - $52,000)

(Design and Contingencies - $105,000)

(19) SR 82, Highway Restoration

1,500,000

(Base Project Allocation - $1,500,000)

(20) South 9th Street Extension, New Construction and Intersection, 1.5 Miles, SR 0422 to Laurel Street, City of Reading, Cumru Township and Exeter Township

61,250,000

(Base Project Allocation - $46,250,000)

(Land Allocation - $11,000,000)

(Design and Contingencies - $4,000,000)