Bucks County

Act 128 of 2008, § 309, under HIGHWAY CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2008-2009 - ENACTMENT.

Act 128 of 2008, § 309

Section 309. Bucks County.

Projects are as follows:

(1) SR 202, Relocation, Realignment, US 202, Pickertown Road to PA 611, Doylestown Township

87,058,000

(Base Project Allocation - $49,600,000)

(Land Allocation - $19,943,000)

(Design and Contingencies - $17,515,000)

(2) SR 202, Wetland Replacement Environmental Mitigation, US 202, Section 700 Wetland Mitigation, New Britain Township

16,070,000

(Base Project Allocation - $5,600,000)

(Land Allocation - $1,850,000)

(Design and Contingencies - $8,620,000)

(3) Bridgetown Interconnect Project, Including Certain Interconnection, New Signals and Widening, Lower Southampton Township

3,210,000

(Base Project Allocation - $3,210,000)

(4) I-95, Interstate Restoration and Reconstruction

18,000,000

(Base Project Allocation - $18,000,000)

(5) SR 2018, Intersection Improvement, Widen and Provide Left Lane

600,000

(Base Project Allocation - $600,000)

(6) SR 202, Intersection Improvement, to Include Left Turn Lane

230,000

(Land Allocation - $100,000)

(Design and Contingencies - $130,000)

(7) SR 2029, Intersection Improvement, Add Turn Lanes

2,000,000

(Base Project Allocation - $2,000,000)

(8) SR 2033, Widen, Additional Lanes

485,000

(Base Project Allocation - $485,000)

(9) SR 2038, Widen, Additional Lanes

4,000,000

(Base Project Allocation - $4,000,000)

(10) SR 2038, Widen From Two to Four Lanes With Turning Lanes, Associated Improvements, Signal Upgrade

2,309,000

(Base Project Allocation - $1,369,000)

(Land Allocation - $120,000)

(Design and Contingencies - $820,000)

(11) SR 4033, Reconstruct, Including Curbs, Sidewalks and Drainage

1,400,000

(Base Project Allocation - $1,400,000)