Section 356. Somerset County.
Projects are as follows:
(1) SR 219, New Four-Lane Roadway Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships
36,000,000
(Base Project Allocation - $27,000,000)
(Land Allocation - $7,000,000)
(Design and Contingencies - $2,000,000)
(2) SR 219, Paving, New Four-Lane Roadway Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships
14,000,000
(Base Project Allocation - $14,000,000)
(3) SR 219, Construction, New Four-Lane Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships
20,000,000
(Base Project Allocation - $20,000,000)
(4) SR 219, New Four-Lane Roadway Alignment, US 219, I-68, Maryland to Meyersdale Bypass, Salisbury Borough, Elk Lick and Summit Townships
51,000,000
(Base Project Allocation - $40,000,000)
(Land Allocation - $6,000,000)
(Design and Contingencies - $5,000,000)
(5) SR 3029, Reconstruction, Ream Road, T-362, Intersection to Seven Springs Borough Line, Seven Springs Borough, Middlecreek and Milford Townships
7,450,000
(Base Project Allocation - $6,600,000)
(Land Allocation - $550,000)
(Design and Contingencies - $300,000)
(6) PA 160, Safety Improvement, Construction of a Runaway Truck Ramp
772,000
(Base Project Allocation - $270,000)
(Land Allocation - $387,000)
(Design and Contingencies - $115,000)
(7) PA 281, Intersection Improvement
755,000
(Base Project Allocation - $370,000)
(Land Allocation - $200,000)
(Design and Contingencies - $185,000)
(8) SR 3041, Intersection Improvement, Construction of Left Turn Lanes and Increasing the Roadway Curve Radius
301,000
(Base Project Allocation - $216,000)
(Land Allocation - $85,000)
(9) SR 3010, Highway Restoration
574,000
(Base Project Allocation - $574,000)
(10) SR 3037, Overlay and Intersection Improvement
2,300,000
(Base Project Allocation - $2,300,000)