Somerset County

Act 128 of 2008, § 356, under HIGHWAY CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2008-2009 - ENACTMENT.

Act 128 of 2008, § 356

Section 356. Somerset County.

Projects are as follows:

(1) SR 219, New Four-Lane Roadway Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships

36,000,000

(Base Project Allocation - $27,000,000)

(Land Allocation - $7,000,000)

(Design and Contingencies - $2,000,000)

(2) SR 219, Paving, New Four-Lane Roadway Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships

14,000,000

(Base Project Allocation - $14,000,000)

(3) SR 219, Construction, New Four-Lane Alignment, US 219, Garrett, End of Existing Four-Lane in Somerset Township to Meyersdale Bypass in Summit Township, Brothersvalley, Somerset and Summit Townships

20,000,000

(Base Project Allocation - $20,000,000)

(4) SR 219, New Four-Lane Roadway Alignment, US 219, I-68, Maryland to Meyersdale Bypass, Salisbury Borough, Elk Lick and Summit Townships

51,000,000

(Base Project Allocation - $40,000,000)

(Land Allocation - $6,000,000)

(Design and Contingencies - $5,000,000)

(5) SR 3029, Reconstruction, Ream Road, T-362, Intersection to Seven Springs Borough Line, Seven Springs Borough, Middlecreek and Milford Townships

7,450,000

(Base Project Allocation - $6,600,000)

(Land Allocation - $550,000)

(Design and Contingencies - $300,000)

(6) PA 160, Safety Improvement, Construction of a Runaway Truck Ramp

772,000

(Base Project Allocation - $270,000)

(Land Allocation - $387,000)

(Design and Contingencies - $115,000)

(7) PA 281, Intersection Improvement

755,000

(Base Project Allocation - $370,000)

(Land Allocation - $200,000)

(Design and Contingencies - $185,000)

(8) SR 3041, Intersection Improvement, Construction of Left Turn Lanes and Increasing the Roadway Curve Radius

301,000

(Base Project Allocation - $216,000)

(Land Allocation - $85,000)

(9) SR 3010, Highway Restoration

574,000

(Base Project Allocation - $574,000)

(10) SR 3037, Overlay and Intersection Improvement

2,300,000

(Base Project Allocation - $2,300,000)