Projects are as follows:

(1) SR 1045, Environmental Mitigation, SR 1045, Stream Mitigation, Unity Township

300,000

(Base Project Allocation - $300,000)

(2) SR 130, Intersection Improvement, SR 130 and College Avenue, Hempfield Township and City of Jeannette

125,000

(Base Project Allocation - $125,000)

(3) SR 30, Highway Restoration, SR 30 from Theater Street to PA 217, Derry and Unity Townships

3,500,000

(Base Project Allocation - $3,500,000)

(4) SR 30, Highway Restoration, US 30 Betterment, Hempfield Township

6,200,000

(Base Project Allocation - $6,200,000)

(5) SR 30, Widen to Provide Center and Left Turning Lane and Add Signals, SR 30 Corridor from Irwin Bridge to Lower Circleville, Irwin Borough and North Huntingdon Township

800,000

(Base Project Allocation - $600,000)

(Land Allocation - $120,000)

(Design and Contingencies - $80,000)

(6) SR 30, Highway Restoration, SR 30 from Robbins Station Road to Central Avenue, Irwin Borough, North Huntingdon Township

2,800,000

(Base Project Allocation - $2,800,000)

(7) SR 30, Widen, Add Lane, SR 30, Allegheny County Line to Leger Road, SR 4019, North Huntingdon Township

920,000

(Base Project Allocation - $700,000)

(Land Allocation - $160,000)

(Design and Contingencies - $60,000)

(8) SR 30, Widen to Provide Center and Left Turning Lane and Add Signals where Warranted, Add Lane, SR 30 from SR 4019 to Malts Lane, North Huntingdon Township

300,000

(Base Project Allocation - $100,000)

(Land Allocation - $120,000)

(Design and Contingencies - $80,000)

(9) SR 780, Intersection Improvement, New Traffic Signal, PA 780 and PA 380 Intersection, Washington Township

315,000

(Base Project Allocation - $240,000)

(Design and Contingencies - $75,000)

(10) I-70, Interstate Restoration and Reconstruction

16,600,000

(Base Project Allocation - $16,600,000)

(11) PA 66, Intersection Improvement, Signal Improvements and Add Lane

2,463,000

(Base Project Allocation - $1,839,000)

(Land Allocation - $260,000)

(Design and Contingencies - $364,000)

(12) SR 51, Intersection Improvement, Add Left Turning Lanes

3,823,000

(Base Project Allocation - $2,813,000)

(Land Allocation - $306,000)