Section 312. Cameron County.
Projects are as follows:
(1) (Reserved).
(2) SR 0120, Highway Portion Bridge Replacement, SR 0120 over Grove Run, Gibson Township, Project ID 69483
Project Allocation
600,000
(Base Project Allocation - $600,000)
(3) SR 0155, Highway Portion Bridge Preservations, SR 155, Portage and Shippen Township, Project ID 94961
Project Allocation
884,000
(Base Project Allocation - $812,000)
(Land Allocation - $11,000)
(Design & Contingencies - $61,000)
(4) SR 0872, Resurface, SR 0872, Grove Township, Project ID 72752
Project Allocation
891,000
(Base Project Allocation - $800,000)
(Land Allocation - $31,000)
(Design & Contingencies - $60,000)
(5) SR 0120, Highway Restoration, SR 0120, SR 0872 and SR 0049, Various Municipalities in Cameron and Potter Counties, Project ID 90256
Project Allocation
1,677,000
(Base Project Allocation - $1,677,000)
(6) SR 0155, Resurface, SR 0155 Emporium to Potter County Line, Segments 0010/0000 to 0150/2513, Portage and Shippen Townships, Project ID 91970
Project Allocation
601,000
(Base Project Allocation - $401,000)
(Design & Contingencies - $200,000)
(7) SR 0120, Highway Restoration, SR 0120, Segments 0100/0000 to 0220/0955, Shippen Township, Emporium Borough, Project ID 88292
Project Allocation
600,000
(Base Project Allocation - $600,000)
(8) SR 0872, Highway Betterment Project, SR 0872, Segments 0070/1559 to 0210/0000, Grove Township, Project ID 88293
Project Allocation
850,000
(Base Project Allocation - $850,000)
(9) SR 0880, Highway Restoration, SR 0046 Segments 0150/0106 to 0200/1485, Shippen Township, Project ID 88295
Project Allocation
300,000
(Base Project Allocation - $300,000)
(10) SR 0872, Highway Reconstruction, SR 0872 near George B. Stevenson Reservoir, Grove Township, Project ID 91964
Project Allocation
600,000
(Base Project Allocation - $400,000)
(Design & Contingencies - $200,000)
(11) SR 0046, Highway Rehabilitation Associated with Bridge Replacement, SR 0046 over North Creek Northwest of Lockwood, Shippen Township, Project ID 94693
Project Allocation
718,000
(Base Project Allocation - $450,000)
(Land Allocation - $43,000)
(Design & Contingencies - $225,000)
(12) SR 0120, Guide Rail Improvements, Cameron County SR 0120, Potter County, SR 0144, SR 0872, Various Municipalities in Cameron and Potter Counties, Project ID 89249
Project Allocation
500,000
(Base Project Allocation - $500,000)
(13) SR 0120, Intersection Improvements, SR 0120/0555 Intersection, Driftwood Borough, Project ID 96066
Project Allocation
563,000
(Base Project Allocation - $401,000)
(Land Allocation - $41,000)
(Design & Contingencies - $121,000)
(14) SR 4004, Highway Portion Bridge Replacement, SR 4004 over Driftwood Branch, Segment 0200/1791, Village of Lockwood, Shippen Township, Project ID 91177
Project Allocation
200,000
(Base Project Allocation - $200,000)
(15) SR 0120, Highway Resurfacing, SR 0120, Segments 0620/0000 to 0750/3751, Driftwood Borough, Gibson and Grove Townships, Project ID 93334
Project Allocation
1,160,000
(Base Project Allocation - $1,020,000)
(Land Allocation - $50,000)
(Design & Contingencies - $90,000)
(16) SR 0555, Highway Restoration, Various Segments - Cameron County SR 0555, SR 2006, Elk County SR 2003, SR 2004, SR 2012, SR 2219, SR 4009, Various Municipalities in Cameron and Elk Counties, Project ID 91086
Project Allocation
4,782,000
(Base Project Allocation - $4,782,000)
(17) SR 0120, Rehabilitation, Resurface, SR 0555 and SR 0120, Driftwood to Sterling Run, Driftwood Borough, Gibson Township, Project ID 96369
Project Allocation
1,405,000
(Base Project Allocation - $1,002,000)
(Land Allocation - $60,000)
(Design & Contingencies - $343,000)
(18) SR 0155, Highway Restoration, Various Segments - Cameron County SR 0155, SR 2006, SR 1001 Elk County, SR 0255, SR 0948, SR 2003, SR 2004, SR 3002, SR 0219, SR 1001 and SR 1003, Various Municipalities in Cameron and Elk Counties, Project ID 91081
Project Allocation
5,528,000
(Base Project Allocation - $5,528,000)
(19) SR 0155, Highway Resurfacing, SR 155 from Emporium to Potter County Line, Portage and Shippen Townships, Project ID 96368
Project Allocation
12,680,000
(Base Project Allocation - $11,756,000)
(Land Allocation - $168,000)
(Design & Contingencies - $756,000)
(20) SR 0120, Resurface, SR 0120 - Elk County Line to Emporium, Segments 0010/0000 to 0270/0000, Emporium Borough, Shippen Township, Project ID 93363
Project Allocation
1,891,000
(Base Project Allocation - $1,760,000)
(Land Allocation - $50,000)
(Design & Contingencies - $81,000)
(21) SR 0120, Resurface, SR 0120 from SR 0155 to Britton Hill Road, Segments 0270/000 to 0300/0000, Portage Township, Shippen Township, Project ID 100480
Project Allocation
515,000
(Base Project Allocation - $515,000)
(22) SR 2001, Betterment (Restoration), SR 2000 Quad Routes, Gibson and Grove Townships, Project ID 101952
Project Allocation
5,111,000
(Base Project Allocation - $4,961,000)
(Design & Contingencies - $150,000)
(23) SR 1001, Betterment (Restoration), SR 1000 Quad Routes, Emporium Borough, Project ID 101951
Project Allocation
396,000
(Base Project Allocation - $245,000)
(Design & Contingencies - $151,000)
(24) SR 0046, Betterment (Restoration), PA 0046, Emporium Borough, Shippen Township, Project ID 101639
Project Allocation
3,477,000
(Base Project Allocation - $3,326,000)
(Design & Contingencies - $151,000)
(25) SR 0120, Resurface, PA 120 from Britton Hill Road to Square Timber Run, Segments 0300/0000 to 0420/0000, Lumber and Portage Townships, Project ID 100497
Project Allocation
2,232,000
(Base Project Allocation - $2,232,000)
(26) SR 0120, Resurface, PA 0120 from Stillhouse Run Road to Tributary of Sinnemahoning Creek, Segments 0420/0000 to 0510/0000, Gibson and Lumber Townships, Project ID 100500
Project Allocation
1,749,000
(Base Project Allocation - $1,749,000)
(27) SR 3001, Betterment (Restoration), SR 3000 Quad Routes, Emporium Borough, Lumber and Shippen Townships, Project ID 101953
Project Allocation
5,531,000
(Base Project Allocation - $5,380,000)
(Design & Contingencies - $151,000)
(28) SR 4001, Betterment (Restoration), SR 4000 Quad Routes, Shippen Township, Project ID 101954
Project Allocation
6,101,000
(Base Project Allocation - $5,951,000)
(Design & Contingencies - $150,000)
(29) PA 120, Resurface, PA 120 from Tributary of Sinnemahoning Creek to Driftwood Borough, Segments 0510/0000 to 0590/0000, Gibson Township, Driftwood Borough, Project ID 100503
Project Allocation
1,164,000
(Base Project Allocation - $1,164,000)
(30) SR 0120, Resurface, PA 120 in Driftwood Borough, Segments 0590/0000 to 0620/0000, Driftwood Borough, Project ID 100506
Project Allocation
859,000
(Base Project Allocation - $859,000)
(31) Various, Highway Portion Bridge Preservation, Various State Routes, Various Municipalities in Elk and Cameron Counties, Project ID 69371
Project Allocation
714,000
(Base Project Allocation - $714,000)