Section 314. Centre County.
Projects are as follows:
(1) (Reserved).
(2) SR 0045, SR 0192, SR 3041, Highway Reconstruction, Various Segments of SR 0045, SR 0192 and SR 3041, Benner, College, Haines, Miles and Penn Townships, Project ID 91100
Project Allocation
2,747,000
(Base Project Allocation - $2,747,000)
(3) SR 0322, Highway Reconstruction, SR 0322 from Thompson Curve to the 4 Lane Segments, Rush Township, Project ID 92736
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(4) SR 0099, Roadway Resurfacing, Mount Nittany Expressway I-99 and SR 0322, College, Harris and Patton Townships, Project ID 92740
Project Allocation
3,800,000
(Base Project Allocation - $3,800,000)
(5) SR 0099, Concrete Pavement Rehabilitation, Overlay, SR 0099 Concrete Pavement Rehabilitation, Overlay, Taylor and Worth Townships, Project ID 91586
Project Allocation
2,361,000
(Base Project Allocation - $2,361,000)
(6) I-99, Reconstruction, I-99 between Bald Eagle Valley Road and East of the Intersection with US 322, Worth Township, Project ID 91585
Project Allocation
550,000
(Base Project Allocation - $550,000)
(7) I-99, Reconstruction, I-99 between Sellers Lane and SR 8022, Patton Township, Project ID 91584
Project Allocation
660,000
(Base Project Allocation - $660,000)
(8) SR 2005, Highway Portion Bridge Replacement, SR 2005 over Sinking Creek, Segments 0020 Offset 0839 Near Spring Mills, Gregg Township, Project ID 91500
Project Allocation
1,050,000
(Base Project Allocation - $791,000)
(Land Allocation - $49,000)
(Design & Contingencies - $210,000)
(9) SR 0192, Highway Reconstruction, SR 0192 from Spring Bank to Wolfs Store, Miles Township, Project ID 91963
Project Allocation
600,000
(Base Project Allocation - $400,000)
(Design & Contingencies - $200,000)
(10) SR 0144, Safety Improvements, SR 0144 Nectarine Road, Segments 0620/1854 to 0620/2425, Snow Shoe Township, Snow Shoe Borough, Project ID 91959
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(11) SR 0322, Safety Improvements, SR 0322 near Sharer Road, Harris Township, Project ID 91958
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(12) SR 0144, Safety Improvements, SR 0144 Segments 0010/2395 to 0020/0957, Potter Township, Project ID 91955
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(13) SR 0045, Safety Improvements, SR 0045 at Kline Road Intersection, Gregg Township, Project ID 91954
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(14) SR 0477, Safety Improvements, SR 0477, Segment 0010, Miles Township, Project ID 91953
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(15) SR 0322, Safety Improvements, SR 0322 near Satellite Building, Rush Township, Project ID 91956
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(16) SR 3003, Safety and Intersection Improvements, SR 3005 Airport Intersection, Benner Township, Project ID 93263
Project Allocation
900,000
(Land Allocation - $400,000)
(Design & Contingencies - $500,000)
(17) SR 0192, Reconstruction, SR 0192, Segments 0400 through 0610 and Other Various Locations, Various Municipalities, Project ID 91072
Project Allocation
12,175,000
(Base Project Allocation - $12,175,000)
(18) SR 0192, SR 2012, Highway Reconstruction, SR 0192 and SR 2012, College, Gregg, Haines, Huston, Miles, Penn and Potter Townships, Millheim Borough, Project ID 91075
Project Allocation
9,740,000
(Base Project Allocation - $9,740,000)
(19) SR 0144, Resurface, PA 144, Bishop Street to Molasses Hill, Segments 0280/0000 to 0340/0000, Bellefonte Borough, Spring Township, Project ID 91093
Project Allocation
300,000
(Base Project Allocation - $300,000)
(20) SR 3005, SR 3029, SR 3049, Highway Reconstruction, Various Segments of SR 3005, SR 3029, SR 3049, Benner, College, Patton, Rush and Worth Townships, Port Matilda Borough, Project ID 91095
Project Allocation
520,000
(Base Project Allocation - $520,000)
(21) SR 0150, Highway Restoration, Various Segments on SR 0045, SR 0144, SR 0150, SR 0322, SR 1016 and SR 3010, Various Municipalities, Project ID 91097
Project Allocation
3,750,000
(Base Project Allocation - $3,750,000)
(22) SR 0322, Safety Improvements, SR 0322 Intersection with SR 0144, Potters Mills, Potter Township, Project ID 91952
Project Allocation
300,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $100,000)
(23) SR 0045, Add Lane/Widen, SR 0045 and SR 2006, Segment/Offset 0292/0000 to 0310/0000, Segment/Offset 0010/0000, Harris Township, Project ID 93267
Project Allocation
914,000
(Base Project Allocation - $914,000)
(24) SR 3040, Reconstruction, Drainage and Shoulders, SR 3040, Segments 0280 to 0370/2238, Huston and Union Townships, Unionville Borough, Project ID 91102
Project Allocation
5,000,000
(Base Project Allocation - $5,000,000)
(25) SR 0026, Intersection Improvement, SR 0026 and SR 0150 Intersections, Segment/Offset 0640/0421 to 0640/2150, Segment/Offset 0310/2500 to 0320/1000, Howard Township, Project ID 93262
Project Allocation
759,000
(Base Project Allocation - $701,000)
(Land Allocation - $29,000)
(Design & Contingencies - $29,000)
(26) SR 0350, Left Turn Lane, SR 0350, Glass City Road, Dale Road, Sleepy Hollow Road, Rush Township, Project ID 93260
Project Allocation
530,000
(Base Project Allocation - $307,000)
(Land Allocation - $97,000)
(Design & Contingencies - $126,000)
(27) SR 0322, Highway Resurfacing, SR 0322, Philipsburg to Port Mountain, Segment/Offset 0052/0000 to 0150/0000, Rush Township, Project ID 93256
Project Allocation
4,102,000
(Base Project Allocation - $3,901,000)
(Design & Contingencies - $201,000)
(28) SR 0322, Highway Resurfacing, SR 0322, Port Matilda Mountain, Segments 0150/0000 to 0272/0000, Rush and Worth Townships, Project ID 93255
Project Allocation
989,000
(Base Project Allocation - $593,000)
(Land Allocation - $45,000)
(Design & Contingencies - $351,000)
(29) SR 0026, Highway Reconstruction, SR 0026, Segments 0510 through 0640 and Other Various Locations, Howard and Marion Townships, Howard Borough, Project ID 91099
Project Allocation
863,000
(Base Project Allocation - $863,000)
(30) SR 0045, Congestion Improvement, SR 0045, Segments/Offset 0140/0000 to 0240/0000, Ferguson and Harris Townships, Project ID 93367
Project Allocation
60,000
(Design & Contingencies - $60,000)
(31) SR 0026, Highway Restoration, Various Segments on SR 0026, SR 0045, SR 0150, SR 0192, SR 0120, SR 0477, SR 4001, Various Municipalities in Centre and Clinton Counties, Project ID 91098
Project Allocation
3,806,000
(Base Project Allocation - $3,806,000)
(32) SR 0026, Safety and Intersection Improvements, Intersection of SR 0026 and SR 0064, Spring Township, Project ID 95827
Project Allocation
1,500,000
(Base Project Allocation - $1,500,000)
(33) SR 2003, Highway Restoration, SR 0192 Stover Gap Road to Union County Line, Miles Township, Project ID 88341
Project Allocation
500,000
(Base Project Allocation - $500,000)
(34) SR 0948, Highway Restoration, SR 0322 Satellite to Top of Port Matilda Mountain, Rush Township, Project ID 88342
Project Allocation
300,000
(Base Project Allocation - $300,000)
(35) SR 3040, Highway Betterment Project, SR 3040, Alternate 220 Bottom of Sky Top Mountain to County Line, Segments 0190/2084 to 0370/2238, Huston and Union Townships, Unionville Borough, Worth Township, Project ID 88343
Project Allocation
1,800,000
(Base Project Allocation - $1,800,000)
(36) SR 3014, Highway Portion Bridge Replacement, SR 3014 over SR 0322, Patton Township, Project ID 88353
Project Allocation
201,000
(Base Project Allocation - $201,000)
(37) SR 3014, Safety Improvements, SR 3014, North Atherton Street, Southbound, Segments 0030 to 0180, State College Borough, Patton, Ferguson, College and Harris Townships, Project ID 95832
Project Allocation
2,000,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $200,000)
(Design & Contingencies - $300,000)
(38) SR 3014, Reconstruction and Drainage Work, SR 3014, North and South Atherton Street, Segments 0030/0000 to 0180/1500 and 0031/0000 to 0181/1550, College, Ferguson, Harris and Patton Townships, State College Borough, Project ID 89019
Project Allocation
7,347,000
(Base Project Allocation - $6,155,000)
(Land Allocation - $791,000)
(Design & Contingencies - $401,000)
(39) SR 0026, Safety Improvements, SR 0026, Buckhout to Struble Road, State College Borough, College Township, Project ID 95828
Project Allocation
1,950,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $150,000)
(Design & Contingencies - $300,000)
(40) SR 0006, Highway Restoration, SR 0045, Segments 0060/0000 to 0690/0000, Millheim Borough, Penn Township, Project ID 88268
Project Allocation
300,000
(Base Project Allocation - $300,000)
(41) I-80, Highway Reconstruction, I-80, Segments 1520 through 1590, Boggs Township, Project ID 88577
Project Allocation
300,000
(Base Project Allocation - $300,000)
(42) I-99, Highway Reconstruction, I-99, Segments 0694 through 0740, College and Patton Townships, Project ID 88578
Project Allocation
2,500,000
(Base Project Allocation - $2,500,000)
(43) I-99, Concrete Pavement Rehabilitation and Guide Rail Improvements, I-99, Segments 0740 through 0820, Benner, College and Spring Townships, Project ID 88581
Project Allocation
2,500,000
(Base Project Allocation - $2,500,000)
(44) I-99, Concrete Pavement Rehabilitation and Guide Rail Improvements, I-99, Segments 0680 through 0650, Huston, Patton and Worth Townships, Project ID 88582
Project Allocation
1,400,000
(Base Project Allocation - $1,400,000)
(45) I-99, Reconstruction, I-99, Segments 0694 through 0680, Patton Township, Project ID 88583
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(46) SR 0026, Installation of Truck Escape Ramp, SR 0026, Pine Grove Mountain II, Segments 0040/1150 to 0040/2650, Ferguson Township, Project ID 88629
Project Allocation
516,000
(Base Project Allocation - $200,000)
(Land Allocation - $41,000)
(Design & Contingencies - $275,000)
(47) SR 0045, Highway Portion Bridge Preservation Activities, PA 45 over Elk Creek and PA 144 over Irish Hollow, Millheim Borough, Spring Township, Project ID 94957
Project Allocation
600,000
(Base Project Allocation - $600,000)
(48) SR 3014, Safety Improvements, SR 3014, North Atherton Street, Northbound, Segments 0023 to 0105, State College Borough, Patton and Ferguson Townships, Project ID 95831
Project Allocation
2,000,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $200,000)
(Design & Contingencies - $300,000)
(49) SR 4005, Highway Portion Bridge Replacement, SR 4005 over SR 0080, I-80, Segment 0010 Offset 0240, Snow Shoe Township, Project ID 88217
Project Allocation
358,000
(Base Project Allocation - $281,000)
(Land Allocation - $43,000)
(Design & Contingencies - $34,000)
(50) SR 0322, New Alignment and Relocation of 4 Lane Roadway, SR 0322, Segments 0570 to 0770, Harris and Potter Townships, Project ID 96820
Project Allocation
307,000,000
(Base Project Allocation - $250,000,000)
(Land Allocation - $32,000,000)
(Design & Contingencies - $25,000,000)
(51) SR 0144, Highway Portion Bridge Rehabilitation, SR 0144 over Bald Eagle Creek, BMS 14-0144-0370-0654, Boggs Township, Milesburg Borough, Project ID 69434
Project Allocation
205,000
(Base Project Allocation - $177,000)
(Land Allocation - $28,000)
(52) SR 0026, Roadway Restoration/Resurfacing, SR 0026, Jacksonville Road, Segments 0470/0169 to 0510/0609, Marion Township, Project ID 85965
Project Allocation
2,051,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $1,000,000)
(Design & Contingencies - $51,000)
(53) Build Park and Ride Lot, Philipsburg Area, Philipsburg Borough, Project ID 87155
Project Allocation
1,800,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $500,000)
(Design & Contingencies - $300,000)
(54) SR 0144, Highway Portion Bridge Replacement, SR 0144 over South Fork Beech Creek, BMS 14-0144-0560-1203, Boggs and Snow Shoe Townships, Project ID 88170
Project Allocation
728,000
(Base Project Allocation - $728,000)
(55) SR 3011, Highway Portion Bridge Replacement, SR 3011 over Slab Cabin Run, BMS 14-3011-0040-0000, College Township, State College Borough, Project ID 88189
Project Allocation
387,000
(Base Project Allocation - $295,000)
(Land Allocation - $92,000)
(56) SR 0045, Highway Portion Bridge Replacement, SR 0045 over Elk Creek, Millheim Borough, Project ID 88193
Project Allocation
238,000
(Base Project Allocation - $106,000)
(Land Allocation - $85,000)
(Design & Contingencies - $47,000)
(57) SR 0219, Highway Restoration, SR 0192 Elk Creek to Stover Gap Road, Miles Township, Project ID 88340
Project Allocation
(Base Project Allocation - $650,000)
650,000
(58) SR 3040, Highway Portion Bridge Replacement, SR 3040 over Laurel Run, BMS 14-3040-0280-1591, Huston Township, Project ID 88206
Project Allocation
984,000
(Base Project Allocation - $675,000)
(Land Allocation - $58,000)
(Design & Contingencies - $251,000)
(59) SR 0120, Highway Restoration, SR 0192, SR 0445, Elk Creek, Miles Township, Project ID 88339
Project Allocation
600,000
(Base Project Allocation - $600,000)
(60) SR 0322, Highway Reconstruction, SR 0322, Segments 0770/0000 to 0820, Potters Mills to Sand Mountain Road, Potter Township, Project ID 96370
Project Allocation
1,000,000
(Design & Contingencies - $1,000,000)
(61) SR 3014, Highway Portion Bridge Replacement, SR 3014 over Slab Cabin Run, Segments 0140 Offset 1699, State College Borough, Project ID 88235
Project Allocation
3,980,000
(Base Project Allocation - $3,287,000)
(Land Allocation - $130,000)
(Design & Contingencies - $563,000)
(62) SR 3014, Safety Improvements, SR 0026, Jacksonville Road to SR 0150, Segments 0510/0000 to 0640/2150, Howard Borough, Howard and Marion Townships, Project ID 88259
Project Allocation
400,000
(Base Project Allocation - $100,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(63) SR 0153, Safety Improvements, SR 0150, Segments 0030/0000 to 0150/0200, College, Benner and Spring Townships, Bellefonte Borough, Rush Township, Project ID 88261
Project Allocation
400,000
(Base Project Allocation - $100,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(64) SR 0219, Safety Improvements, SR 3014, Atherton Street, Patton and Ferguson Townships, State College Borough, College and Harris Townships, Project ID 88262
Project Allocation
400,000
(Base Project Allocation - $100,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(65) SR 0066, Highway Restoration, SR 3014, South Atherton, Segment 0104/0000 to 0190/0000, State College Borough, College and Harris Townships, Project ID 88267
Project Allocation
700,000
(Base Project Allocation - $700,000)
(66) SR 0044, Safety Improvements, SR 0144 to Bumbarger Lane, Spring Township, Bellefonte Borough, Boggs and Burnside Townships, Project ID 88260
Project Allocation
400,000
(Base Project Allocation - $100,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(67) SR 0045, Highway Portion Bridge Replacement, SR 0045 over Pine Creek, BMS 14-0045-0790-2031, Haines Township, Project ID 88201
Project Allocation
1,931,000
(Base Project Allocation - $1,357,000)
(Land Allocation - $108,000)
(Design & Contingencies - $466,000)
(68) SR 0099, Embankment Removal and Guide Rail Updates, I-99, Benner, College, Huston, Patton, Spring, Taylor and Worth Townships, Project ID 89251
Project Allocation
100,000
(Base Project Allocation - $100,000)
(69) SR 0080, Signing, Mile Marker Sign, Segments 0080/1380 through 0080/1700, Various, Project ID 89243
Project Allocation
250,000
(Base Project Allocation - $250,000)
(70) SR 0026, SR 0064, SR 0322, Guide Rail Improvements, Various Segments of SR 0026, SR 0064, SR 0322, Various Municipalities, Project ID 89246
Project Allocation
500,000
(Base Project Allocation - $500,000)
(71) SR 0144, Roadway Resurfacing, Milesburg Interchange, Segments 0144/0150, Boggs Township, Milesburg Borough, Project ID 89247
Project Allocation
820,000
(Base Project Allocation - $820,000)
(72) SR 4002, Betterment, Restoration, SR 4000 Quad Routes, Boggs and Rush Townships, Snow Shoe Borough, Snow Shoe and Union Townships, Project ID 101995
Project Allocation
8,905,000
(Base Project Allocation - $8,755,000)
(Design & Contingencies - $150,000)
(73) SR 3040, Resurface, SR 3040, Silverdale Road to PA 504, Segments 0270/0000 to 0370/2238, Huston and Union Townships, Unionville Borough, Project ID 100563
Project Allocation
2,100,000
(Base Project Allocation - $2,100,000)
(74) SR 0504, Resurface, PA 504, Black Bear Run to SR 3032, Segments 0080/0000 to 0170/2195, Rush Township, Project ID 100538
Project Allocation
900,000
(Base Project Allocation - $900,000)
(75) SR 3010, Resurface, SR 3010, Oak Hall Interchange, Segments 0060/0000 to 0070/1945, College and Harris Townships, Project ID 101035
Project Allocation
772,000
(Base Project Allocation - $772,000)
(76) SR 0879, Resurface, SR 0879, Karthaus to the Crossroads, Segments 0010/0000 to 0170/1859, Burnside and Snow Shoe Townships, Project ID 101031
Project Allocation
3,200,000
(Base Project Allocation - $3,200,000)
(77) SR 3041, Resurface, SR 3041, Shiloh Road, Segments 0010/0000 to 0020/4370, Benner and College Townships, Project ID 101042
Project Allocation
626,000
(Base Project Allocation - $626,000)
(78) SR 3042, Resurface, SR 3042, Laurel Run Road to Port Matilda, Segments 0274/0000 to 0302/0000, Port Matilda Borough, Worth Township, Project ID 101045
Project Allocation
500,000
(Base Project Allocation - $500,000)
(79) SR 0150, Resurface, SR 0150, PA 26 to County Line, Segments 0320/1279 to 0430/1820, Howard and Liberty Townships, Project ID 100546
Project Allocation
1,060,000
(Base Project Allocation - $1,060,000)
(80) SR 0045, Resurface, SR 0045, Old Fort to Spring Mills, Segments 0430/000 to 0530/0000, Gregg Township, Potter Township, Project ID 100551
Project Allocation
1,002,000
(Base Project Allocation - $1,002,000)
(81) SR 3020, Resurface, SR 3020, University Drive, Whitehall Road to Atherton Street, Segments 0010/0000 to 0020/1513, College Township, State College Borough, Project ID 100545
Project Allocation
200,000
(Base Project Allocation - $200,000)
(82) SR 0550, Resurface, SR 0550, Blair County Line to Eagle Spring Road, Segments 0010/0000 to 0160/2505, Half Moon and Patton Townships, Project ID 101056
Project Allocation
7,300,000
(Base Project Allocation - $7,300,000)
(83) SR 0192, Resurface, Livonia to County Line, Miles Township, Project ID 100528
Project Allocation
1,223,000
(Base Project Allocation - $1,223,000)
(84) SR 0045, Resurface, SR 0045, Cedar Run Road to Old Fort, Segments 0320/000 to 0410/1950, Harris and Potter Townships, Project ID 10126
Project Allocation
3,345,000
(Base Project Allocation - $3,345,000)
(85) SR 1010, Resurface, SR 1010, PA 64 to Jacksonville Road, Segments 0014/0000 to 0150/2284, Marion and Walker Townships, Project ID 100562
Project Allocation
1,500,000
(Base Project Allocation - $1,500,000)
(86) SR 2012, Resurface, SR 2012, Greenbriar Road to Coburn Road, Segments 0230/0000 to 0270/3149, Penn Township, Project ID 100534
Project Allocation
434,000
(Base Project Allocation - $434,000)
(87) SR 3001, Betterment, Restoration, SR 3000 Quad Routes, Various, Project ID 101993
Project Allocation
36,236,000
(Base Project Allocation - $36,085,000)
(Design & Contingencies - $151,000)
(88) SR 0026, Resurface, SR 0026, Ferguson Township to College Avenue Southbound, Segments 0143/0000 to 0181/0000, Ferguson Township, State College Borough, Project ID 101008
Project Allocation
600,000
(Base Project Allocation - $600,000)
(89) SR 0026, Resurface, SR 0026, Ferguson Township to College Avenue Northbound, Segments 0142/0000 to 0180/0000, Ferguson Township, State College Borough, Project ID 101003
Project Allocation
600,000
(Base Project Allocation - $600,000)
(90) SR 3017, Resurface, SR 3017, PA 550 to SR 3042, Segments 0010/0000 to 0050/0802, Half Moon Township, Port Matilda Borough, Worth Township, Project ID 100554
Project Allocation
550,000
(Base Project Allocation - $550,000)
(91) SR 3005, Resurface, SR 3005, SR 3007 to Fox Hill Road, Segments 0010/0000 to 0070/2676, Benner Township, College and Patton Townships, Project ID 100557
Project Allocation
720,000
(Base Project Allocation - $720,000)
(92) SR 0350, Resurface, SR 0350, Linnwood Development to Presqueisle Street, Segments 0200/0000 to 0260/0357, Philipsburg Borough, Rush Township, Project ID 100559
Project Allocation
800,000
(Base Project Allocation - $800,000)
(93) SR 0504, Resurface, SR 0504, Black Moshannon to Wallace Run, Segments 0180/0000 to 0340/1389, Rush and Union Townships, Project ID 100560
Project Allocation
2,000,000
(Base Project Allocation - $2,000,000)
(94) SR 0144, Resurface, SR 0144, Centre Hall, Segments 0090/0000 to 0130/0000, Centre Hall Borough, Potter Township, Project ID 101028
Project Allocation
1,132,000
(Base Project Allocation - $1,132,000)
(95) SR 0045, Betterment, Restoration, PA 45, Ferguson, Harris and Potter Townships, Project ID 101509
Project Allocation
4,461,000
(Base Project Allocation - $4,310,000)
(Design & Contingencies - $151,000)
(96) SR 0322, Resurface, SR 0322, Clearfield County Line to Cold Stream, Segments 0012/0000 to 0052/0000, Philipsburg Borough, Rush Township, Project ID 100594
Project Allocation
500,000
(Base Project Allocation - $500,000)
(97) SR 0192, Betterment, Restoration, PA 192, Centre Hall Borough, Gregg and Potter Townships, Project ID 101514
Project Allocation
3,875,000
(Base Project Allocation - $3,725,000)
(Design & Contingencies - $150,000)
(98) SR 0322, Betterment, Restoration, US 322, Harris, Potter, Rush and Worth Townships, Project ID 101539
Project Allocation
4,371,000
(Base Project Allocation - $4,221,000)
(Design & Contingencies - $150,000)
(99) SR 3010, Rehabilitation, Resurface, SR 3010, Oak Hall Intersection, College and Harris Townships, Project ID 99528
Project Allocation
2,039,000
(Base Project Allocation - $2,039,000)
(100) SR 0150, Betterment, Restoration, PA 150, Boggs, College and Howard Townships, Project ID 101513
Project Allocation
4,285,000
(Base Project Allocation - $4,135,000)
(Design & Contingencies - $150,000)
(101) I-80, Reconstruction, I-80 from the Clearfield County Line to the Clinton County Line, Various Municipalities, Project ID 0
Project Allocation
131,000,000
(Base Project Allocation - $131,000,000)
(102) SR 0053, Betterment, Restoration, PA 53, Snow Shoe Township, Project ID 101506
Project Allocation
1,617,000
(Base Project Allocation - $1,466,000)
(Design & Contingencies - $151,000)
(103) SR 0322, Resurface, SR 0322, Bypass to Boalsburg Westbound, Segments 0541/0000 to 0585/1074, College and Harris Townships, Project ID 100586
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(104) SR 0026, Betterment, Restoration, PA 26, Ferguson Township, Howard Borough, Howard and Spring Townships, Project ID 101511
Project Allocation
2,531,000
(Base Project Allocation - $2,381,000)
(Design & Contingencies - $150,000)
(105) SR 0064, Betterment, Restoration, PA 64, Spring and Walker Townships, Project ID 101512
Project Allocation
6,526,000
(Base Project Allocation - $6,376,000)
(Design & Contingencies - $150,000)
(106) SR 0350, Resurface, SR 0350, Blair County to Sandy Ridge, Segments 0010/0000 to 0130/0000, Rush and Taylor Townships, Project ID 100590
Project Allocation
3,000,000
(Base Project Allocation - $3,000,000)
(107) SR 0144, Betterment, Restoration, PA 144, Boggs, Burnside and Potter Townships, Snow Shoe Borough, Snow Shoe and Spring Townships, Project ID 101501
Project Allocation
17,221,000
(Base Project Allocation - $17,071,000)
(Design & Contingencies - $150,000)
(108) SR 0080, Betterment, Restoration, I-80, Boggs, Marion and Rush Townships, Snow Shoe Borough, Snow Shoe and Spring Townships, Project ID 101609
Project Allocation
19,412,000
(Base Project Allocation - $19,261,000)
(Design & Contingencies - $151,000)
(109) I-99, Reconstruction, I-99 from the Blair County Line to its Northern Terminus at I-80, Various Municipalities, Project ID 0
Project Allocation
119,400,000
(Base Project Allocation - $119,400,000)
(110) SR 0026, Resurface, SR 0026, High Street to SR 9012 Southbound, Segments 0181/0000 to 0247/0670, College Township, State College Borough, Project ID 100571
Project Allocation
1,250,000
(Base Project Allocation - $1,250,000)
(111) SR 2001, Betterment, Restoration, SR 2000 Quad Routes, Various, Project ID 101989
Project Allocation
19,402,000
(Base Project Allocation - $19,251,000)
(Design & Contingencies - $151,000)
(112) SR 1001, Betterment, Restoration, SR 1000 Quad Routes, Various, Project ID 101987
Project Allocation
15,120,000
(Base Project Allocation - $14,970,000)
(Design & Contingencies - $150,000)
(113) SR 3027, Resurface, SR 3049 to Stone Street, Rush Township, Project ID 100564
Project Allocation
250,000
(Base Project Allocation - $250,000)
(114) SR 0026, Resurface, SR 0026, County Line to SR 3018, Segments 0010/0000 to 0090/1853, Ferguson Township, Project ID 100565
Project Allocation
1,632,000
(Base Project Allocation - $1,632,000)
(115) SR 0322, Resurface, SR 0322, Bypass to Boalsburg Interchange Eastbound, Segments 0540/0000 to 0590/0000, College and Harris Townships, Project ID 100583
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(116) SR 0045, Resurface, SR 0045, Millheim to County Line, Segments 0670/2711 to 0880/1958, Haines Township, Millheim Borough, Penn Township, Project ID 100549
Project Allocation
3,240,000
(Base Project Allocation - $3,240,000)
(117) SR 0550, Resurface, SR 0550, SR 3042 to Park Avenue, Segments 0190/0000 to 0390/0000, Benner, Patton and Spring Townships, Project ID 100580
Project Allocation
3,876,000
(Base Project Allocation - $3,876,000)
(118) SR 0026, Highway Portion Bridge Replacement, SR 0026 over Lick Run, Segment 0590/1750, Marion Township, Project ID 99872
Project Allocation
448,000
(Base Project Allocation - $199,000)
(Land Allocation - $50,000)
(Design & Contingencies - $199,000)
(119) SR 3040, Betterment, Restoration, SR 3040, Huston Township, Port Matilda Borough, Taylor and Worth Townships, Project ID 101633
Project Allocation
6,397,000
(Base Project Allocation - $6,246,000)
(Design & Contingencies - $151,000)
(120) SR 0144 and SR 4005, Intersection Improvements
Project Allocation
250,000
(Base Project Allocation - $250,000)
(121) I-80, Clearfield to Clinton, Resurface and Restoration
Project Allocation
131,300,000
(Base Project Allocation - $131,000,000)
(Land Allocation - $50,000)
(Design & Contingencies - $250,000)
(122) Various, Highway Portion Bridge Preservation Activities, Various State Routes, Various Municipalities, Project ID 94960
Project Allocation
744,000
(Base Project Allocation - $744,000)
(123) Various, Tree Trimming Safety Improvements, Various Highways and Segments throughout Centre County, Various Municipalities, Project ID 88350
Project Allocation
500,000
(Base Project Allocation - $500,000)