Section 341. Lycoming County.
Projects are as follows:
(1) (Reserved).
(2) SR 0414, Highway Portion Bridge Truss Rehabilitation, SR 0414 over Pine Creek, Brown Township, Project ID 6206
Project Allocation
242,000
(Base Project Allocation - $196,000)
(Design & Contingencies - $46,000)
(3) SR 0015, Reconstruct Roadway, Intersection of US 15 and 4 Mile Road, Lewis Township, Project ID 93024
Project Allocation
1,466,000
(Base Project Allocation - $1,041,000)
(Land Allocation - $225,000)
(Design & Contingencies - $200,000)
(4) SR 0180, Resurface, I-180 from Loyalsock Creek to Turkey Run, Fairfield Township, Montoursville Borough, Muncy Township, Project ID 82310
Project Allocation
246,000
(Base Project Allocation - $240,000)
(Design & Contingencies - $6,000)
(5) SR 0220, Install New Overhead Sign Structure, SR 0220 Main Street and SR 0044 Interchange, Segment/Offset 0061/1900, Piatt Township, Project ID 87006
Project Allocation
271,000
(Base Project Allocation - $262,000)
(Design & Contingencies - $9,000)
(6) SR 0014, Resurface, PA 14 from Pleasant Stream Road to Red Run, McIntyre Township, Project ID 97774
Project Allocation
304,000
(Base Project Allocation - $304,000)
(7) SR 8006, Replace Existing Overhead Sign Structure, SR 0180 Hepburn Street Off-Ramp, Segment/Offset 0010/0530, City of Williamsport, Project ID 87002
Project Allocation
309,000
(Base Project Allocation - $299,000)
(Design & Contingencies - $10,000)
(8) SR 2014, Reconstruct Roadway, SR 2014 from Hillside Avenue to US 15, Segments 0060/0000 to 0070/2210, City of Williamsport, Project ID 87986
Project Allocation
1,061,000
(Land Allocation - $251,000)
(Design & Contingencies - $810,000)
(9) SR 0044, Resurface, PA 44 from Ramsey Run to SR 4001 (Little Pine Creek Road), Cummings Township, Project ID 97776
Project Allocation
349,000
(Base Project Allocation - $349,000)
(10) SR 0118, Highway Portion Bridge Rehabilitation, PA 118 over Little Muncy Creek, Jordan Township, Project ID 97658
Project Allocation
421,000
(Base Project Allocation - $321,000)
(Design & Contingencies - $100,000)
(11) SR 2014, Reconstruct Roadway, SR 2014 from Campbell Street to Basin Street, Segments 0120/0000 to 0160/0811, City of Williamsport, Project ID 87987
Project Allocation
802,000
(Land Allocation - $101,000)
(Design & Contingencies - $701,000)
(12) SR 0287, SR 0187, Intersection and Bridge Improvements, SR 0287 Intersection SR 0187, Cogan House Township, Project ID 96791
Project Allocation
267,000
(Base Project Allocation - $250,000)
(Land Allocation - $17,000)
(13) SR 0180, Resurface, I-180 Eastbound from Cemetery Road to SR 2014, Fairfield, Muncy Creek and Muncy Townships, Project ID 97671
Project Allocation
3,226,000
(Base Project Allocation - $3,201,000)
(Design & Contingencies - $25,000)
(14) SR 0405, Resurface, PA 405 from Brick Church Road to Susquehanna River, Clinton Township, Project ID 97785
Project Allocation
267,000
(Base Project Allocation - $267,000)
(15) SR 0405, Highway Portion Bridge Rehabilitation, PA 405 over Tributary of Susquehanna River, Clinton Township, Project ID 97661
Project Allocation
771,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $271,000)
(16) SR 2055, Resurface, SR 2055 from SR 2042 (East Lime Bluff Road) to SR 2053 (Beacon Light Road), Muncy Creek and Muncy Townships, Project ID 97801
Project Allocation
136,000
(Base Project Allocation - $136,000)
(17) SR 0118, Highway Portion Bridge Rehabilitation, PA 118 over Sugar Run, Wolf Township, Project ID 97654
Project Allocation
771,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $271,000)
(18) SR 0054, Resurface, PA 54 from Brouse Road to Main Street, Clinton Township, Montgomery Borough, Project ID 97777
Project Allocation
101,000
(Base Project Allocation - $101,000)
(19) SR 2053, Highway Portion Bridge Rehabilitation, SR 2053 over Wolf Run, Muncy Township, Project ID 97662
Project Allocation
1,121,000
(Base Project Allocation - $901,000)
(Design & Contingencies - $220,000)
(20) SR 2018, Resurface, SR 2018 from SR 2029 (Northway Road) to SR 2039 (Warrensville Road), Loyalsock Township, Project ID 97797
Project Allocation
196,000
(Base Project Allocation - $196,000)
(21) SR 2014, Reconstruction, SR 2014 (Fourth Street) from US 15 to Campbell Street, Segments 0070/2210 to 0120/0000, City of Williamsport, Project ID 97508
Project Allocation
5,021,000
(Base Project Allocation - $4,601,000)
(Land Allocation - $220,000)
(Design & Contingencies - $200,000)
(22) SR 0287, Highway Portion Bridge Replacement, PA 287 over Larry's Creek, Cummings Township, Project ID 97625
Project Allocation
1,721,000
(Base Project Allocation - $1,300,000)
(Design & Contingencies - $421,000)
(23) SR 2027, Resurface, SR 2027 from SR 2018 (Four Mile Drive) to SR 2024 (Northway Road Extension), Loyalsock Township, City of Williamsport, Project ID 97799
Project Allocation
254,000
(Base Project Allocation - $254,000)
(24) SR 0180, Crack Seal and Plug Joints, Hepburn Street to Faxon, Segments 0310/0000 to 0370/0000, 0311/0000 to 0371/0096, Loyalsock Township, City of Williamsport, Project ID 95772
Project Allocation
296,000
(Base Project Allocation - $276,000)
(Design & Contingencies - $20,000)
(25) SR 0180, Resurface, I-180 Westbound from SR 2049 (Lycoming Mall Drive) to SR 2014, Fairfield, Muncy Creek and Muncy Townships, Project ID 97672
Project Allocation
2,926,000
(Base Project Allocation - $2,900,000)
(Design & Contingencies - $26,000)
(26) SR 0864, Resurface, PA 864 from PA 87 to Mill Creek, Upper Fairfield Township, Project ID 97789
Project Allocation
285,000
(Base Project Allocation - $285,000)
(27) SR 0180, Phase B Devices, I-180/US 15/US 220 Interchange Area, City of Williamsport, Project ID 95185
Project Allocation
760,000
(Base Project Allocation - $351,000)
(Land Allocation - $17,000)
(Design & Contingencies - $392,000)
(28) SR 2014, Safety Improvement, Intersection of SR 2014, SR 2036 and Legion Road, Muncy Township, Project ID 97607
Project Allocation
1,060,000
(Base Project Allocation - $1,060,000)
(29) SR 0220, Resurface, US 220 from SR 2036 to Achmuty Road, Segments 0320/0000 to 0380/0000, Muncy Township, Project ID 92849
Project Allocation
1,010,000
(Base Project Allocation - $1,000,000)
(Design & Contingencies - $10,000)
(30) SR 0015, Mill and Resurface, SR 0015 from the Union County Line to Route 54, SR 0015 Segments 0010/0000 to 0080/3340 and Segments 0041/0000 to 0041/0460, Brady and Clinton Townships, Project ID 87953
Project Allocation
2,393,000
(Base Project Allocation - $2,369,000)
(Design & Contingencies - $24,000)
(31) SR 0284, Highway Portion Bridge Replacement, PA 284 over Blacks Creek, Pine Township, Project ID 97623
Project Allocation
1,746,000
(Base Project Allocation - $1,400,000)
(Design & Contingencies - $346,000)
(32) SR 0015, Mill and Resurface, SR 0015 from Route 284 to the Lycoming County Line, Segments 1770/0874 to 1860/2330, Segments 1771/0000 to 1861/2315, Jackson Township, Project ID 87969
Project Allocation
5,998,000
(Base Project Allocation - $5,982,000)
(Design & Contingencies - $16,000)
(33) SR 0044, Resurface, PA 44 from Rattling Camp Run to PA 654, Segments 0220/0000 to 0260/0950, Limestone Township, Project ID 97698
Project Allocation
587,000
(Base Project Allocation - $566,000)
(Design & Contingencies - $21,000)
(34) SR 0220, Highway Portion Bridge Rehabilitation, US 220 over Lick Run, Shrewsbury Township, Project ID 97660
Project Allocation
771,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $271,000)
(35) SR 2003, Highway Portion Bridge Replacement, SR 2003 over Spring Creek, Washington Township, Project ID 97632
Project Allocation
1,448,000
(Base Project Allocation - $1,001,000)
(Land Allocation - $146,000)
(Design & Contingencies - $301,000)
(36) SR 2018, Mill and Resurface Roadway, SR 2018 from Almond Street to Northway Road, Segments 0040/0035 to 0060/0678, Loyalsock Township, City of Williamsport, Project ID 87970
Project Allocation
803,000
(Base Project Allocation - $779,000)
(Design & Contingencies - $24,000)
(37) SR 0044, Highway Portion Bridge Rehabilitation, PA 44 over Ramsey Run, Cummings Township, Project ID 97609
Project Allocation
1,136,000
(Base Project Allocation - $791,000)
(Design & Contingencies - $345,000)
(38) SR 0284, Highway Portion Bridge Rehabilitation, PA 284 over Bonnell Run, Pine Township, Project ID 97617
Project Allocation
901,000
(Base Project Allocation - $801,000)
(Design & Contingencies - $100,000)
(39) SR 1017, Highway Portion Bridge Rehabilitation, SR 1017 (Lycoming Creek Road) over Lycoming Creek, Hepburn and Lewis Townships, Project ID 87917
Project Allocation
860,000
(Base Project Allocation - $845,000)
(Land Allocation - $15,000)
(40) SR 0087, Highway Portion Bridge Rehabilitation, PA 87 over Little Bear Creek, Plunketts Creek Township, Project ID 97615
Project Allocation
1,021,000
(Base Project Allocation - $921,000)
(Design & Contingencies - $100,000)
(41) SR 0220, Roadway Safety Improvement (Median Barrier), US 220 From Martins Road to Christians Road, Piatt Township, Project ID 82869
Project Allocation
211,000
(Base Project Allocation - $200,000)
(Design & Contingencies - $11,000)
(42) SR 0220, Roadway Intersection Improvement, Intersection of US 220 and SR 0405, SR 0220 Segments 0420/0775 to 0430/1375, SR 0405 Segments 0250/0000 to 0250/1862, Hughesville Borough, Wolf Township, Project ID 93016
Project Allocation
4,453,000
(Base Project Allocation - $2,751,000)
(Land Allocation - $1,201,000)
(Design & Contingencies - $501,000)
(43) SR 4002, Highway Portion Bridge Replacement, SR 4002 over Trout Run, Pine Township, Project ID 97664
Project Allocation
320,000
(Base Project Allocation - $175,000)
(Land Allocation - $75,000)
(Design & Contingencies - $70,000)
(44) SR 0220, Mill and Resurface Roadway, US 220 SR 0220 from Youngs Road to Stewart Street, Segments 0160/0000 to 0210/1638, Segments 0181/1852 to 0211/1625, Woodward Township, Project ID 87878
Project Allocation
1,248,000
(Base Project Allocation - $1,230,000)
(Design & Contingencies - $18,000)
(45) SR 0864, Highway Portion Bridge Rehabilitation, PA 864 over Mill Creek, Upper Fairfield Township, Project ID 97620
Project Allocation
1,067,000
(Base Project Allocation - $966,000)
(Design & Contingencies - $101,000)
(46) SR 4001, Highway Restoration, SR 4001 (Little Pine Creek Road) over Little Pine Creek, Pine Township, Project ID 88743
Project Allocation
1,194,000
(Base Project Allocation - $1,194,000)
(47) SR 0405, Resurface, PA 405 from Muncy Creek to Hughesville, Hughesville Borough, Muncy Creek and Wolf Townships, Project ID 97702
Project Allocation
836,000
(Base Project Allocation - $816,000)
(Design & Contingencies - $20,000)
(48) SR 2056, Resurface, SR 2056 from SR 2029 (Northway Road) to SR 2016 (Washington Boulevard), Loyalsock Township, Project ID 97803
Project Allocation
74,000
(Base Project Allocation - $58,000)
(Design & Contingencies - $16,000)
(49) SR 0414, Slide Correction, SR 0414 Cedar Run Narrows, Brown Township, Project ID 98089
Project Allocation
2,600,000
(Base Project Allocation - $2,500,000)
(Land Allocation - $50,000)
(Design & Contingencies - $50,000)
(50) SR 3003, Resurface, SR 3003 from Nelson Street to PA 44, Jersey Shore Borough, Project ID 97704
Project Allocation
197,000
(Base Project Allocation - $176,000)
(Design & Contingencies - $21,000)
(51) SR 3004, Resurface, SR 3004 from Mountain Road to Mosquito Creek, Armstrong and Bastress Townships, Project ID 97806
Project Allocation
500,000
(Base Project Allocation - $500,000)
(52) SR 0220, Resurface, US 220 from Main Street to Water Street, Segments 0460/2006 to 0490/0164, Picture Rocks Borough, Wolf Township, Project ID 97700
Project Allocation
591,000
(Base Project Allocation - $570,000)
(Design & Contingencies - $21,000)
(53) SR 0118, Highway Portion Bridge Rehabilitation, PA 118 over Greggs Creek, Wolf Township, Project ID 97639
Project Allocation
771,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $271,000)
(54) SR 0118, Reconstruction, SR 0118 from Spruce Street to Muncy Creek Segments 0010/0225 to 0010/2500, Hughesville Borough, Wolf Township, Project ID 87861
Project Allocation
1,335,000
(Base Project Allocation - $1,308,000)
(Design & Contingencies - $27,000)
(55) SR 0220, Intersection Improvements, SR 0220 from Williamsport to Jersey Shore Borough, Piatt and Woodward Townships, Project ID 93732
Project Allocation
350,000
(Base Project Allocation - $350,000)
(56) SR 0180, Highway Portion Bridge Replacement, SR 0180 over Lycoming Valley Railroad, City of Williamsport, Project ID 96579
Project Allocation
6,368,000
(Base Project Allocation - $5,644,000)
(Land Allocation - $1,000)
(Design & Contingencies - $723,000)
(57) SR 0015, Highway Portion Bridge Replacement, US 15 over Black Hole Creek, Clinton Township, Project ID 91436
Project Allocation
2,737,000
(Base Project Allocation - $2,138,000)
(Design & Contingencies - $599,000)
(58) SR 2018, Highway Portion Bridge Rehabilitation, SR 2018 over Millers Run, Loyalsock Township, Project ID 99337
Project Allocation
1,121,000
(Base Project Allocation - $971,000)
(Design & Contingencies - $150,000)
(59) SR 3013, Slide Repair, SR 3013 from Spring Valley Road to Mahaffey Hollow, Woodward Township, Project ID 99373
Project Allocation
1,101,000
(Base Project Allocation - $751,000)
(Design & Contingencies - $350,000)
(60) SR 0044, Highway Portion Bridge Replacement, PA 44 over Upper Pine Bottom Run, Cummings Township, Project ID 99393
Project Allocation
1,491,000
(Base Project Allocation - $1,291,000)
(Design & Contingencies - $200,000)
(61) SR 0015, Install High Tension Cable Median Barrier, I-180, US 15 and US 220, Various Municipalities, Project ID 99375
Project Allocation
4,651,000
(Base Project Allocation - $4,451,000)
(Design & Contingencies - $200,000)
(62) SR 0405, Resurface Roadway, SR 0405 from SR 2014 to SR 2057, Muncy Borough, Muncy Creek Township, Project ID 98931
Project Allocation
186,000
(Base Project Allocation - $111,000)
(Design & Contingencies - $75,000)
(63) SR 0180, Highway Portion Bridge Painting, I-180, Various Municipalities, Project ID 99226
Project Allocation
2,871,000
(Base Project Allocation - $2,850,000)
(Design & Contingencies - $21,000)
(64) SR 0220, Highway Portion Bridge Rehabilitation, US 220 Northbound over Ramp A-1 to Fourth Street, Woodward Township, Project ID 99228
Project Allocation
621,000
(Base Project Allocation - $601,000)
(Design & Contingencies - $20,000)
(65) SR 0054, Resurface Roadway, SR 0054 from SR 0015 to Brouse Road, Clinton Township, Project ID 98913
Project Allocation
53,000
(Base Project Allocation - $30,000)
(Design & Contingencies - $23,000)
(66) SR 2061, Slide Correction, SR 2061 at Intersection of Crawley Road, Penn Township, Project ID 99372
Project Allocation
2,600,000
(Base Project Allocation - $2,350,000)
(Land Allocation - $50,000)
(Design & Contingencies - $200,000)
(67) SR 0654, Resurface Roadway, SR 0654 from Cold Water Town Road to Village Drive, Bastress and Susquehanna Townships, Project ID 98932
Project Allocation
161,000
(Base Project Allocation - $101,000)
(Design & Contingencies - $60,000)
(68) SR 0014, Highway Portion Bridge Replacement, PA 14 over Abbotts Run, McIntyre Township, Project ID 99383
Project Allocation
1,421,000
(Base Project Allocation - $1,221,000)
(Design & Contingencies - $200,000)
(69) SR 0014, Highway Portion Bridge Rehabilitation, PA 14 over Trout Run, Lewis Township, Project ID 99227
Project Allocation
323,000
(Base Project Allocation - $303,000)
(Design & Contingencies - $20,000)
(70) SR 0220, Resurface, US 220 from School Street to Arch Street, City of Williamsport, Woodward Township, Project ID 98990
Project Allocation
3,776,000
(Base Project Allocation - $3,725,000)
(Design & Contingencies - $51,000)
(71) SR 0284, Resurface Roadway, SR 0284 from SR 0287 to Flooks Run, Pine Township, Project ID 98927
Project Allocation
955,000
(Base Project Allocation - $884,000)
(Design & Contingencies - $71,000)
(72) SR 0087, Resurface Roadway, SR 0087 from Little Bear Creek Road to Lower Manor Road, Plunketts Creek Township, Project ID 98919
Project Allocation
80,000
(Base Project Allocation - $50,000)
(Design & Contingencies - $30,000)
(73) SR 0220, Resurface Roadway, SR 0220 from Muncy Creek to Main Street, Wolf Township, Project ID 98924
Project Allocation
87,000
(Base Project Allocation - $57,000)
(Design & Contingencies - $30,000)
(74) SR 0044, Highway Portion Bridge Replacement, PA 44 over Furnace Run, Watson Township, Project ID 99348
Project Allocation
1,421,000
(Base Project Allocation - $1,221,000)
(Design & Contingencies - $200,000)
(75) SR 2014 and SR 2045, Congestion and Safety Improvements, SR 2014 (Lycoming Mall Drive) and SR 2014 (Fairfield Road), Fairfield Township, Project ID 98166
Project Allocation
3,000,000
(Base Project Allocation - $3,000,000)
(76) SR 0284, Resurface Roadway, SR 0284 from Flooks Run to SR 1009, Jackson Township, Project ID 98925
Project Allocation
462,000
(Base Project Allocation - $432,000)
(Design & Contingencies - $30,000)
(77) SR 0044, Highway Portion Bridge Replacement, PA 44 over Tombs Run, Watson Township, Project ID 99397
Project Allocation
1,491,000
(Base Project Allocation - $1,291,000)
(Design & Contingencies - $200,000)
(78) SR 0287, Highway Portion Bridge Replacement, PA 287 over Tributary of Larry's Creek, Piatt Township, Project ID 99352
Project Allocation
1,421,000
(Base Project Allocation - $1,221,000)
(Design & Contingencies - $200,000)
(79) SR 0220, Highway Portion Bridge Rehabilitation, US 220 Southbound over Ramp A-1 to Fourth Street, Woodward Township, Project ID 99230
Project Allocation
621,000
(Base Project Allocation - $601,000)
(Design & Contingencies - $20,000)
(80) SR 0180, Highway Portion Bridge Rehabilitation, I-180 over Muncy Creek, Muncy Creek Township, Project ID 98986
Project Allocation
1,451,000
(Base Project Allocation - $1,300,000)
(Design & Contingencies - $151,000)
(81) SR 2014, Highway Portion Bridge Replacement, SR 2014 over Wolf Run, Muncy Creek Township, Project ID 99359
Project Allocation
1,821,000
(Base Project Allocation - $1,620,000)
(Design & Contingencies - $201,000)
(82) SR 0220, Resurface, US 220 from Plank Road to 0.5 Mile East of Northway Road, Piatt and Woodward Townships, Project ID 98989
Project Allocation
4,051,000
(Base Project Allocation - $4,000,000)
(Design & Contingencies - $51,000)
(83) SR 0220, Highway Portion Bridge Rehabilitation, US 220 Northbound over TR 331 (Antlers Lane), Woodward Township, Project ID 99229
Project Allocation
320,000
(Base Project Allocation - $300,000)
(Design & Contingencies - $20,000)
(84) SR 0220, Highway Portion Bridge Rehabilitation, US 220 over Larry's Creek, Piatt Township, Project ID 99235
Project Allocation
1,222,000
(Base Project Allocation - $1,121,000)
(Design & Contingencies - $101,000)
(85) SR 1017, Resurface, SR 1027 from PA 973 to Trout Run Mountain Road, Segments 0120/0800 to 0250/1901, Hepburn and Lewis Townships, Project ID 99292
Project Allocation
836,000
(Base Project Allocation - $816,000)
(Design & Contingencies - $20,000)
(86) SR 0015, Reconstruction, US 15 from Main Street to Southern Avenue, South Williamsport Borough, Project ID 98983
Project Allocation
3,214,000
(Base Project Allocation - $2,801,000)
(Land Allocation - $213,000)
(Design & Contingencies - $200,000)
(87) SR 0015, Highway Portion Bridge Rehabilitation, US 15 Northbound over Trout Run and a Private Drive, Lewis Township, Project ID 98984
Project Allocation
1,451,000
(Base Project Allocation - $1,300,000)
(Design & Contingencies - $151,000)
(88) SR 0220, Highway Portion Bridge Rehabilitation, US 220 over Wolf Run, Wolf Township, Project ID 99231
Project Allocation
771,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $271,000)
(89) SR 0180, Highway Portion Bridge Rehabilitation, I-180 over Muncy Creek, Muncy Creek Township, Project ID 98985
Project Allocation
1,452,000
(Base Project Allocation - $1,302,000)
(Design & Contingencies - $150,000)
(90) SR 0180, Highway Portion Bridge Rehabilitation, I-180 over SR 2045 (Fairfield Road), Fairfield Township, Project ID 98988
Project Allocation
502,000
(Base Project Allocation - $401,000)
(Design & Contingencies - $101,000)
(91) SR 0442, Resurface Roadway, SR 0442 from SR 2061 to SR 2019, Moreland and Muncy Creek Townships, Project ID 98930
Project Allocation
186,000
(Base Project Allocation - $110,000)
(Design & Contingencies - $76,000)
(92) SR 0405, Highway Portion Bridge Replacement, PA 405 over Tributary of Susquehanna River, Clinton Township, Montgomery Borough, Project ID 99354
Project Allocation
1,501,000
(Base Project Allocation - $1,301,000)
(Design & Contingencies - $200,000)
(93) SR 1009, Highway Portion Bridge Replacement, SR 1009 over Tributary of Blockhouse Creek, Jackson Township, Project ID 99025
Project Allocation
231,000
(Base Project Allocation - $190,000)
(Design & Contingencies - $41,000)
(94) SR 2014, Highway Portion Bridge Replacement, SR 2014 over Bennett's Run, Fairfield Township, Project ID 99038
Project Allocation
1,421,000
(Base Project Allocation - $1,221,000)
(Design & Contingencies - $200,000)
(95) SR 4004, Highway Portion Bridge Replacement, SR 4004 (Granger Lane) over Hughes Run, Pine Township, Project ID 99037
Project Allocation
231,000
(Base Project Allocation - $190,000)
(Design & Contingencies - $41,000)
(96) SR 0405, Reconstruction, PA 405 from PA 54 to Brick Church Road, Clinton Township, Montgomery Borough, Project ID 99008
Project Allocation
4,121,000
(Base Project Allocation - $3,871,000)
(Design & Contingencies - $250,000)
(97) SR 2023, Resurface Roadway, SR 2023 from SR 0015 to Little League Boulevard, City of Williamsport, Project ID 98943
Project Allocation
168,000
(Base Project Allocation - $153,000)
(Design & Contingencies - $15,000)
(98) SR 0287, Highway Portion Bridge Replacement, PA 287 over Lick Run, Pine Township, Project ID 99400
Project Allocation
1,511,000
(Base Project Allocation - $1,091,000)
(Design & Contingencies - $420,000)
(99) SR 2023, Resurface Roadway, SR 2023 from Little League Boulevard to SR 2018, City of Williamsport, Project ID 98944
Project Allocation
80,000
(Base Project Allocation - $50,000)
(Design & Contingencies - $30,000)
(100) SR 2029, Resurface Roadway, SR 2029 from Miller Hill Road to SR 0973, Eldred and Loyalsock Townships, Project ID 98947
Project Allocation
83,000
(Base Project Allocation - $52,000)
(Design & Contingencies - $31,000)
(101) SR 3007, Highway Portion Bridge Replacement, SR 3007 (Level Corners Road) over Pine Run, Piatt and Woodward Townships, Project ID 99036
Project Allocation
297,000
(Base Project Allocation - $181,000)
(Land Allocation - $65,000)
(Design & Contingencies - $51,000)
(102) SR 2029, Resurface Roadway, SR 2029 from SR 2014 to SR 2024, Loyalsock Township, Project ID 98948
Project Allocation
166,000
(Base Project Allocation - $106,000)
(Design & Contingencies - $60,000)
(103) SR 2049, Resurface Roadway, SR 2049 from Pond Road to Mall Road, Muncy Township, Project ID 98949
Project Allocation
278,000
(Base Project Allocation - $247,000)
(Design & Contingencies - $31,000)
(104) SR 2061, Resurface Roadway, SR 2061 from SR 0118 to Crawley Road, Moreland, Penn and Wolf Townships, Project ID 98952
Project Allocation
183,000
(Base Project Allocation - $160,000)
(Design & Contingencies - $23,000)
(105) SR 2061, Resurface Roadway, SR 2061 from SR 2073 to the Sullivan County Line, Penn Township, Project ID 98954
Project Allocation
183,000
(Base Project Allocation - $160,000)
(Design & Contingencies - $23,000)
(106) SR 0180, Highway Portion Bridge Rehabilitation, I-180 over SR 0405, Muncy Creek Township, Project ID 99045
Project Allocation
3,501,000
(Base Project Allocation - $3,350,000)
(Design & Contingencies - $151,000)
(107) SR 1006, Highway Portion Bridge Replacement, SR 1006 over Slacks Run, Cascade Township, Project ID 99013
Project Allocation
250,000
(Base Project Allocation - $150,000)
(Land Allocation - $20,000)
(Design & Contingencies - $80,000)
(108) SR 0044, Resurface, SR 0044 from PA 880 to SR 3003, Segments 0344/0968 to 0420/1918, Jersey Shore Borough, Limestone and Nippenose Townships, Project ID 99280
Project Allocation
1,322,000
(Base Project Allocation - $1,301,000)
(Design & Contingencies - $21,000)
(109) SR 3015, Highway Portion Bridge Rehabilitation, SR 3015 over Cogan Run, Anthony Township, Project ID 99232
Project Allocation
67,000
(Base Project Allocation - $65,000)
(Design & Contingencies - $2,000)
(110) SR 0014, Highway Portion Bridge Rehabilitation, PA 14 over Red Run, McIntyre Township, Project ID 99233
Project Allocation
891,000
(Base Project Allocation - $870,000)
(Design & Contingencies - $21,000)
(111) SR 3014, Resurface Roadway, SR 3014 from SR 3015 to Princeton Avenue, Old Lycoming Township, Project ID 98957
Project Allocation
650,000
(Base Project Allocation - $605,000)
(Design & Contingencies - $45,000)
(112) SR 1010, Highway Portion Bridge Replacement, SR 1010 over Little Elk Run, Jackson Township, Project ID 99027
Project Allocation
262,000
(Base Project Allocation - $191,000)
(Land Allocation - $30,000)
(Design & Contingencies - $41,000)
(113) I-180, Reconstruction, I-180 from the Northumberland County Line to its Western Terminus in City of Williamsport, Various Municipalities, Project ID 0
Project Allocation
78,000,000
(Base Project Allocation - $78,000,000)
(114) SR 1017, Resurface, SR 1017 (Lycoming Creek Road) from High Street to Pleasant Hill Road, Loyalsock, Lycoming and Old Lycoming Townships, Project ID 99029
Project Allocation
3,191,000
(Base Project Allocation - $3,091,000)
(Design & Contingencies - $100,000)
(115) SR 0014, Highway Portion Bridge Preservation, PA 14, SR 1017 (Lycoming Creek Road) and SR 3021 (Memorial Avenue) over Lycoming Creek, Loyalsock, McIntyre and Old Lycoming Townships, City of Williamsport, Project ID 99030
Project Allocation
931,000
(Base Project Allocation - $901,000)
(Design & Contingencies - $30,000)
(116) SR 2004, Highway Portion Bridge Replacement, SR 2004 over Tributary of Spring Creek, Washington Township, Project ID 99031
Project Allocation
231,000
(Base Project Allocation - $150,000)
(Design & Contingencies - $81,000)
(117) SR 2004, Highway Portion Bridge Replacement, SR 2004 (Alvira Road) over Tributary of Spring Creek, Washington Township, Project ID 99032
Project Allocation
296,000
(Base Project Allocation - $151,000)
(Land Allocation - $65,000)
(Design & Contingencies - $80,000)
(118) SR 2014, Resurface, SR 2014 (Third Street) from River Avenue to Loyalsock Creek, Loyalsock Township, Project ID 99033
Project Allocation
2,136,000
(Base Project Allocation - $2,001,000)
(Design & Contingencies - $135,000)
(119) SR 4010, Resurface Roadway, SR 4010 from SR 0184 to Larry's Creek, Cogan House Township, Project ID 98961
Project Allocation
438,000
(Base Project Allocation - $407,000)
(Design & Contingencies - $31,000)
(120) SR 2073, Highway Portion Bridge Replacement, SR 2073 over Greggs Run, Wolf Township, Project ID 99035
Project Allocation
191,000
(Base Project Allocation - $150,000)
(Design & Contingencies - $41,000)
(121) SR 0180, Highway Portion Bridge Rehabilitation, I-180 over Maynard Street, City of Williamsport, Project ID 99234
Project Allocation
1,151,000
(Base Project Allocation - $1,051,000)
(Design & Contingencies - $100,000)
(122) SR 0220, Highway Portion Bridge Rehabilitation, US 220 over Pine Run, Piatt and Woodward Townships, Project ID 99236
Project Allocation
1,321,000
(Base Project Allocation - $1,220,000)
(Design & Contingencies - $101,000)
(123) SR 0414, Highway Portion Bridge Replacement, PA 414 over Truman Run, McHenry Township, Project ID 99402
Project Allocation
1,511,000
(Base Project Allocation - $1,091,000)
(Design & Contingencies - $420,000)
(124) SR 0973, Resurface Roadway, SR 0973 from SR 0044 to SR 0287, Mifflin and Watson Townships, Project ID 98934
Project Allocation
856,000
(Base Project Allocation - $796,000)
(Design & Contingencies - $60,000)
(125) SR 0014, Rehabilitation, Resurface, SR 0014 from Red Run to Tioga County, McIntyre Township, Project ID 98508
Project Allocation
1,176,000
(Base Project Allocation - $1,150,000)
(Design & Contingencies - $26,000)
(126) SR 0973, Resurface Roadway, SR 0973 on SR 1017 to SR 2029, Eldred and Hepburn Townships, Project ID 98935
Project Allocation
168,000
(Base Project Allocation - $108,000)
(Design & Contingencies - $60,000)
(127) SR 2083, Highway Portion Bridge Replacement, SR 2083 over Lick Run, Shrewsbury Township, Project ID 99408
Project Allocation
1,422,000
(Base Project Allocation - $1,421,000)
(Design & Contingencies - $1,000)
(128) SR 0973, Highway Portion Bridge Rehabilitation, PA 973 over Mill Creek, Hepburn Township, Project ID 99237
Project Allocation
821,000
(Base Project Allocation - $670,000)
(Design & Contingencies - $151,000)
(129) SR 0973, Resurface, PA 973 from Long Run to SR 1017 (Lycoming Creek Road), Hepburn Township, Project ID 99411
Project Allocation
592,000
(Base Project Allocation - $576,000)
(Design & Contingencies - $16,000)
(130) SR 2014, Resurface Roadway, SR 2014 from Shadduck Road to SR 0405, Muncy Borough, Muncy Creek Township, Project ID 98938
Project Allocation
78,000
(Base Project Allocation - $47,000)
(Design & Contingencies - $31,000)
(131) SR 0220, Resurface, US 220 from Water Street to Muncy Creek, Penn Township, Picture Rocks Borough, Shrewsbury Township, Project ID 99003
Project Allocation
4,172,000
(Base Project Allocation - $4,101,000)
(Design & Contingencies - $71,000)
(132) SR 0087, Resurface, SR 0087, Plunketts Creek and Upper Fairfield Townships, Project ID 99451
Project Allocation
99,000
(Base Project Allocation - $58,000)
(Design & Contingencies - $41,000)
(133) SR 1017, Highway Portion Rehabilitation, SR 1017 over Trout Run, Lewis Township, Project ID 99051
Project Allocation
701,000
(Base Project Allocation - $600,000)
(Design & Contingencies - $101,000)
(134) SR 0287, Resurface, PA 287 from 1 Mile South of Oregon Hill Road to Tioga County Line, Pine Township, Project ID 99005
Project Allocation
2,014,000
(Base Project Allocation - $1,951,000)
(Design & Contingencies - $63,000)
(135) SR 2014, Resurface Roadway, SR 2014 from SR 2045 to Odell Road, Fairfield Township, Montoursville Borough, Project ID 98940
Project Allocation
201,000
(Base Project Allocation - $125,000)
(Design & Contingencies - $76,000)
(136) SR 2016, Resurface Roadway, SR 2016 from SR 1017 to Hepburn Street, Loyalsock and Old Lycoming Townships, City of Williamsport, Project ID 98942
Project Allocation
213,000
(Base Project Allocation - $138,000)
(Design & Contingencies - $75,000)
(137) SR 2014, Reconstruction, SR 2014 from PA 405 (Water Street) to Rose Hill Road, Muncy Borough, Muncy Creek Township, Project ID 99410
Project Allocation
3,501,000
(Base Project Allocation - $3,000,000)
(Design & Contingencies - $501,000)
(138) SR 0414, SR 0414 Cedar Run Narrows
Project Allocation
2,600,000
(Base Project Allocation - $2,500,000)
(Land Allocation - $50,000)
(Design & Contingencies - $50,000)
(139) Various, Highway Portion Bridge Preservation, Various State Routes, Various Municipalities, Project ID 99034
Project Allocation
2,002,000
(Base Project Allocation - $1,901,000)
(Design & Contingencies - $101,000)
(140) Various, Highway Portion Bridge Rehabilitation, Various Routes, Various Municipalities, Project ID 87918
Project Allocation
905,000
(Base Project Allocation - $800,000)
(Land Allocation - $75,000)
(Design & Contingencies - $30,000)