Tioga County

Act 129 of 2014, § 359, under HIGHWAY CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2014-2015.

Act 129 of 2014, § 359

Section 359. Tioga County.

Projects are as follows:

(1) (Reserved).

(2) SR 0006, Highway Portion Bridge Replacement, US 6 over Marsh Creek, Shippen Township, Project ID 97669

Project Allocation

846,000

(Base Project Allocation - $600,000)

(Design & Contingencies - $246,000)

(3) SR 1022, Highway Portion Bridge Replacement, SR 1022 over Allen Creek, Jackson Township, Project ID 97571

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(4) SR 3098, Highway Portion Bridge Replacement, SR 3098 over Tributary of the East Branch of Stony Fork Creek, Delmar Township, Project ID 97573

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(5) SR 0287, Resurface, PA 287 from Cole Road to SR 4024, Segments 0610/0970 to 0670/1491, Middlebury and Tioga Townships, Project ID 97719

Project Allocation

1,247,000

(Base Project Allocation - $1,226,000)

(Design & Contingencies - $21,000)

(6) SR 0006, Resurface, US 6 from US 15 to SR 1001, Segments 0760/1330 to 0780/1097, Mansfield Borough, Project ID 97718

Project Allocation

272,000

(Base Project Allocation - $251,000)

(Design & Contingencies - $21,000)

(7) SR 0015, Mill and Resurface, SR 0015, Segments 0444/0000 to 0514/0142, 0445/0000 to 0515/0188, Mansfield Borough, Richmond Township, Project ID 87971

Project Allocation

458,000

(Base Project Allocation - $423,000)

(Design & Contingencies - $35,000)

(8) SR 4001, Highway Portion Bridge Replacement, SR 4001 over Tributary of Wattles Run, Clymer Township, Project ID 97574

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(9) SR 0287, Highway Portion Bridge Deck Rehabilitation, SR 0287 over Tioga River, BMS 58-0287-0730-0745, Tioga Borough, Tioga Township, Project ID 7039

Project Allocation

152,000

(Land Allocation - $15,000)

(Design & Contingencies - $137,000)

(10) SR 0006, Highway Portion Bridge Rehabilitation, US 6 over Long Run, Gaines Township, Project ID 97673

Project Allocation

572,000

(Base Project Allocation - $471,000)

(Design & Contingencies - $101,000)

(11) SR 1001, Highway Portion Bridge Rehabilitation, SR 1001 over Lambs Creek, Richmond Township, Project ID 97677

Project Allocation

1,196,000

(Base Project Allocation - $1,181,000)

(Design & Contingencies - $15,000)

(12) SR 0049, Mill and Resurface, SR 0049, Segments 0080/2742 to 0130/1621, Westfield Borough, Westfield Township, Project ID 87950

Project Allocation

1,154,000

(Base Project Allocation - $1,154,000)

(13) SR 0006, Highway Portion Bridge Replacement, US 6 over Phoenix Run, Gaines Township, Project ID 97674

Project Allocation

1,920,000

(Base Project Allocation - $1,500,000)

(Design & Contingencies - $420,000)

(14) SR 0015, Resurface Roadway, US 15 from the Tioga County Line to Connolly Lane US 15, Segments 0012/0000 to 0052/3726, US 15 Segments 0013/0000 to 0053/3767, Liberty Township, Project ID 87869

Project Allocation

704,000

(Base Project Allocation - $686,000)

(Design & Contingencies - $18,000)

(15) SR 0414, Roadway Soil Slide Repair, SR 0414, Segments/Offset 0080/0000 to 0080/2549, Morris Township, Project ID 87879

Project Allocation

500,000

(Base Project Allocation - $369,000)

(Land Allocation - $41,000)

(Design & Contingencies - $90,000)

(16) SR 4017, Highway Portion Bridge Replacement, SR 4017 over Losey Creek, Chatham Township, Project ID 97575

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(17) SR 0328, Resurface, PA 328 from PA 287 to Button Hill Road, Jackson and Lawrence Townships, Project ID 97773

Project Allocation

614,000

(Base Project Allocation - $614,000)

(18) SR 0015, Mill and Resurface Roadway, US 15 from Tioga River to SR 2005, Segments 0142/0077 to 0272/1075, 0143/0075 to 0273/1148, Bloss Township, Blossburg Borough, Liberty Township, Project ID 93553

Project Allocation

2,489,000

(Base Project Allocation - $2,449,000)

(Design & Contingencies - $40,000)

(19) SR 0287, Slide Correction, SR 287 East of SR 0414, Morris Township, Project ID 95646

Project Allocation

215,000

(Base Project Allocation - $175,000)

(Land Allocation - $20,000)

(Design & Contingencies - $20,000)

(20) SR 4002, Highway Portion Bridge Replacement, SR 4002 over Morris Brook, Wellsboro Borough, Project ID 97682

Project Allocation

1,851,000

(Base Project Allocation - $1,651,000)

(Design & Contingencies - $200,000)

(21) SR 2017, Highway Portion Bridge Rehabilitation, SR 2017 over Tioga River, Blossburg Borough, Project ID 97680

Project Allocation

871,000

(Base Project Allocation - $671,000)

(Design & Contingencies - $200,000)

(22) SR 0006, Roadway Safety Improvement, US 6 from Wellsboro Borough Limits to Cherry Flats Road, Segments/Offset 0540/0975 to 0560/3260, Charleston Township, Wellsboro Borough, Project ID 88875

Project Allocation

1,074,000

(Base Project Allocation - $1,074,000)

(23) SR 4007, Highway Portion Bridge Rehabilitation, SR 4007 over North Brook, Brookfield Township, Project ID 97684

Project Allocation

726,000

(Base Project Allocation - $500,000)

(Design & Contingencies - $226,000)

(24) SR 0006, Mill and Resurface Roadway, SR 0006 from SR 0287 to Wellsboro Borough Limits, Segments/Offset 0500/0000 to 0540/1000 and 0560/0500 to 0560/2848, Wellsboro Borough, Project ID 82984

Project Allocation

137,000

(Base Project Allocation - $117,000)

(Design & Contingencies - $20,000)

(25) SR 0414, Resurface, PA 0414 from SR 2005 (Water Street) to Blockhouse Creek, Liberty Borough, Project ID 97772

Project Allocation

62,000

(Base Project Allocation - $46,000)

(Design & Contingencies - $16,000)

(26) SR 4002, Resurface, SR 4002 from Fellows Avenue to US 6, Charleston Township, Wellsboro Borough, Project ID 97750

Project Allocation

721,000

(Base Project Allocation - $721,000)

(27) SR 4009, Highway Portion Bridge Replacement, SR 4009 over Troups Creek, 140/458, Brookfield Township, Project ID 95548

Project Allocation

531,000

(Land Allocation - $95,000)

(Design & Contingencies - $436,000)

(28) SR 0015, Roadway Soil Slide Repair, US 15 Between Segments 0621/2345 through 0631/0523, Tioga Township, Project ID 93087

Project Allocation

475,000

(Base Project Allocation - $325,000)

(Design & Contingencies - $150,000)

(29) SR 0014, Resurface, PA 14 from the Lycoming County Line to McCracken Road, Union Township, Project ID 97778

Project Allocation

848,000

(Base Project Allocation - $848,000)

(30) SR 1005, Highway Portion Bridge Rehabilitation, SR 1005 over Mill Creek, Roseville Borough, Project ID 97678

Project Allocation

926,000

(Base Project Allocation - $701,000)

(Design & Contingencies - $225,000)

(31) SR 0006, Highway Portion Bridge Replacement, US 6 over Tributary of North Elk Run, Richmond Township, Project ID 99107

Project Allocation

1,400,000

(Base Project Allocation - $1,400,000)

(32) SR 4012, Resurface, SR 4012 from Jemison Creek to SR 0249, Segments 0090/1009 to 0190/2141, Chatham and Clymer Townships, Project ID 99399

Project Allocation

771,000

(Base Project Allocation - $750,000)

(Design & Contingencies - $21,000)

(33) SR 0015, Resurface, US 15 Northbound and Southbound from Welcome Center to the New York State Line, Tioga and Lawrence Townships, Project ID 101335

Project Allocation

4,410,000

(Base Project Allocation - $4,410,000)

(34) SR 0287, Resurface Roadway, SR 0287 from Tioga River to SR 0049, Lawrenceville Borough, Project ID 99127

Project Allocation

150,000

(Base Project Allocation - $124,000)

(Design & Contingencies - $26,000)

(35) SR 1013, Highway Portion Bridge Replacement, SR 1013 over Hammond Creek, Jackson Township, Project ID 99365

Project Allocation

317,000

(Base Project Allocation - $230,000)

(Land Allocation - $46,000)

(Design & Contingencies - $41,000)

(36) SR 3016, Highway Portion Bridge Replacement, SR 3016 over a Tributary of Zimmerman Creek, Morris Township, Project ID 99412

Project Allocation

230,000

(Base Project Allocation - $230,000)

(37) SR 0014, Highway Portion Bridge Replacement, PA 14 over Tributary of Lycoming Creek, BMS 58-0014-0140-0000, Union Township, Project ID 99113

Project Allocation

1,600,000

(Base Project Allocation - $1,600,000)

(38) SR 0014, Highway Portion Bridge Replacement, PA 14 over Dry Run, BMS 58-0014-0090-0870, Union Township, Project ID 99112

Project Allocation

1,500,000

(Base Project Allocation - $1,500,000)

(39) SR 4007, Resurface, SR 4007 from SR 0049 to Bertch Road, Segments 0010/0000 to 0100/3105, Brookfield and Westfield Townships, Project ID 99395

Project Allocation

1,020,000

(Base Project Allocation - $1,000,000)

(Design & Contingencies - $20,000)

(40) SR 3023, Highway Portion Bridge Replacement, SR 3023 over Heise Run, Delmar Township, Project ID 99413

Project Allocation

230,000

(Base Project Allocation - $230,000)

(41) SR 0287, Highway Portion Bridge Replacement, PA 287 over Tributary of the Tioga River, BMS 58-0287-0810-0000, Lawrence Township, Project ID 99132

Project Allocation

1,400,000

(Base Project Allocation - $1,400,000)

(42) SR 0287, Highway Portion Bridge Rehabilitation, PA 287 over Mutton Lane Creek, BMS 58-0287-0810-0633, Lawrence Township, Project ID 99133

Project Allocation

1,100,000

(Base Project Allocation - $1,100,000)

(43) SR 2016, Highway Portion Bridge Replacement, SR 2016 over Bellman Run, Hamilton Township, Project ID 98539

Project Allocation

1,380,000

(Base Project Allocation - $1,300,000)

(Land Allocation - $25,000)

(Design & Contingencies - $55,000)

(44) SR 3023, Highway Portion Bridge Replacement, SR 3023 over Heise Run, Delmar Township, Project ID 99414

Project Allocation

230,000

(Base Project Allocation - $230,000)

(45) SR 0014, Highway Portion Bridge Replacement, PA 14 over Tributary of Lycoming Creek, BMS 58-0014-0050-0984, Union Township, Project ID 99109

Project Allocation

1,600,000

(Base Project Allocation - $1,600,000)

(46) SR 0287, Resurface Roadway, SR 0287 from Sand Run to Wilson Creek, Delmar Township, Project ID 99128

Project Allocation

173,000

(Base Project Allocation - $112,000)

(Design & Contingencies - $61,000)

(47) SR 1022, Highway Portion Bridge Replacement, SR 1022 over Allen Creek, Jackson Township, Project ID 99367

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(48) SR 4001, Highway Portion Bridge Replacement, SR 4001 over Potter Brook, Clymer Township, Project ID 99415

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(49) SR 3009, Highway Portion Bridge Rehabilitation, SR 3009 over Charleston Creek, Charleston Township, Project ID 99377

Project Allocation

381,000

(Base Project Allocation - $331,000)

(Land Allocation - $25,000)

(Design & Contingencies - $25,000)

(50) SR 0006, Resurface, US 6 from Old Mills Road to Main Street, Charleston Township, Wellsboro Borough, Project ID 101052

Project Allocation

3,675,000

(Base Project Allocation - $3,675,000)

(51) SR 0006, Resurface, SR 0006 from Long Run to Colton Road, Segments 0074/0941 to 0200/1558, Gaines and Shippen Townships, Project ID 99386

Project Allocation

2,620,000

(Base Project Allocation - $2,600,000)

(Design & Contingencies - $20,000)

(52) SR 0287, Highway Portion Bridge Rehabilitation, PA 287 over Crooked Creek, BMS 58-0287-0530-0828, Middlebury Township, Project ID 99118

Project Allocation

700,000

(Base Project Allocation - $700,000)

(53) SR 0249, Highway Portion Bridge Rehabilitation, PA 249 over Crooked Creek, BMS 58-0249-0172-1570, Chatham Township, Project ID 99116

Project Allocation

800,000

(Base Project Allocation - $800,000)

(54) SR 3007, Highway Portion Bridge Replacement, SR 3007 over the West Branch of Stoney Fork Creek, Delmar Township, Project ID 99370

Project Allocation

230,000

(Base Project Allocation - $230,000)

(55) SR 1013, Highway Portion Bridge Replacement, SR 1013 over Hammond Creek, Jackson Township, Project ID 99366

Project Allocation

336,000

(Base Project Allocation - $231,000)

(Land Allocation - $45,000)

(Design & Contingencies - $60,000)

(56) SR 2011, Highway Portion Bridge Replacement, SR 2011 over Blockhouse Creek, Liberty Township, Project ID 99368

Project Allocation

230,000

(Base Project Allocation - $230,000)

(57) SR 0006, Intersection Improvement, US 6, PA 660 and SR 4002, Charleston Township, Project ID 101292

Project Allocation

1,850,000

(Base Project Allocation - $1,850,000)

(58) SR 0006, Resurface, SR 0006 from Dantz Run to PA 287, Segments 0300/0000 to 0420/1100, Delmar Township, Project ID 99387

Project Allocation

3,695,000

(Base Project Allocation - $3,675,000)

(Design & Contingencies - $20,000)

(59) SR 0049, Resurface, SR 0049 from East Street to Renkin Street, Segments 0280/0000 to 0390/2681, Deerfield and Osceola Townships, Project ID 99388

Project Allocation

3,720,000

(Base Project Allocation - $3,700,000)

(Design & Contingencies - $20,000)

(60) SR 0349, Slide Correction, SR 0349 Slide, Clymer Township, Project ID 101278

Project Allocation

750,000

(Base Project Allocation - $750,000)

(61) SR 0287, Resurface, SR 0287 from Lake Nessmuk to Pearl Street, Segments 0320/1835 to 0360/0327, Delmar Township, Wellsboro Borough, Project ID 99389

Project Allocation

1,261,000

(Base Project Allocation - $1,240,000)

(Design & Contingencies - $21,000)

(62) SR 0049, Highway Portion Bridge Rehabilitation, PA 49 over Skinner Hollow, BMS 58-0049-0180-2680, Westfield Township, Project ID 99115

Project Allocation

800,000

(Base Project Allocation - $800,000)

(63) SR 2007, Resurface, SR 2007 from Lycoming County Line to Creamery Street, Segments 0010/0000 to 0020/2120, Liberty Borough, Liberty Township, Project ID 99394

Project Allocation

1,722,000

(Base Project Allocation - $1,701,000)

(Design & Contingencies - $21,000)

(64) SR 2005, Reconstruction and Resurfacing, SR 2005 from Main Street to Corey Street, Mansfield Borough, Project ID 101285

Project Allocation

3,800,000

(Base Project Allocation - $3,800,000)

(65) SR 2022, Highway Portion Bridge Replacement, SR 2022 over Howland Creek, Covington Township, Project ID 99369

Project Allocation

230,000

(Base Project Allocation - $230,000)

(66) SR 2025, Resurface, SR 2025 from SR 2005 to SR 2022, Covington and Putnam Townships, Project ID 99199

Project Allocation

342,000

(Base Project Allocation - $312,000)

(Design & Contingencies - $30,000)

(67) SR 4027, Highway Portion Bridge Replacement, SR 4027 over Branch of Cummings Creek, Farmington Township, Project ID 99416

Project Allocation

230,000

(Base Project Allocation - $230,000)

(68) SR 0287, Reconstruction, PA 287 from US 15 to Mitchell Creek Road, Tioga Township, Project ID 99170

Project Allocation

880,000

(Base Project Allocation - $880,000)

(69) SR 0660, Highway Portion Bridge Replacement, PA 660 over Tributary of North Elk Run, BMS 58-0660-0250-1661, Richmond Township, Project ID 99138

Project Allocation

1,200,000

(Base Project Allocation - $1,200,000)

(70) SR 2020, Highway Portion Bridge Rehabilitation, SR 2020 over North Elk Run, Covington Township, Project ID 98470

Project Allocation

900,000

(Base Project Allocation - $900,000)

(71) SR 2017, Highway Portion Bridge Rehabilitation, SR 2017 over Taylor Run, Hamilton Township, Project ID 98465

Project Allocation

900,000

(Base Project Allocation - $900,000)

(72) SR 0349, Reconstruction, PA 349 from Ladd Road to PA 49, Westfield Borough, Westfield Township, Project ID 99171

Project Allocation

2,921,000

(Base Project Allocation - $2,695,000)

(Land Allocation - $26,000)

(Design & Contingencies - $200,000)

(73) SR 0414, Reconstruction, PA 414 from US 15 to SR 2005 (Water Street), Liberty Borough, Project ID 99173

Project Allocation

1,925,000

(Base Project Allocation - $1,800,000)

(Design & Contingencies - $125,000)

(74) SR 1015, Resurface, SR 1015 from PA 49 to the New York State Line, Lawrenceville Borough, Project ID 99187

Project Allocation

91,000

(Base Project Allocation - $76,000)

(Design & Contingencies - $15,000)

(75) SR 2005, Resurface, SR 2005 from Tioga River to Covington, Covington and Putnam Townships, Project ID 99189

Project Allocation

32,000

(Base Project Allocation - $6,000)

(Design & Contingencies - $26,000)

(76) SR 2005, Resurface, SR 2005 from Cowan Road to PA 660, Covington Township, Project ID 99190

Project Allocation

135,000

(Base Project Allocation - $110,000)

(Design & Contingencies - $25,000)

(77) SR 2005, Resurface, SR 2005 from Covington to Cowan Road, Putnam Township, Project ID 99191

Project Allocation

81,000

(Base Project Allocation - $50,000)

(Design & Contingencies - $31,000)

(78) SR 2022, Resurface, SR 2022 from SR 2020 to SR 2005, Covington and Putnam Townships, Project ID 99192

Project Allocation

685,000

(Base Project Allocation - $630,000)

(Design & Contingencies - $55,000)

(79) SR 0049, Resurface, PA 49 from Taft Avenue to 0.5 Mile West of Barney Hill Road, Elkland Borough, Nelson Township, Project ID 99168

Project Allocation

3,475,000

(Base Project Allocation - $3,475,000)

(80) SR 2022, Resurface, SR 2022 from Corey Creek to the Bradford County Line, Sullivan Township, Project ID 99197

Project Allocation

615,000

(Base Project Allocation - $569,000)

(Design & Contingencies - $46,000)

(81) SR 0049, Reconstruction, PA 49 from Water Tower Road to PA 287, Lawrence Township, Lawrenceville Borough, Project ID 99169

Project Allocation

1,750,000

(Base Project Allocation - $1,750,000)

(82) SR 3007, Resurface, SR 3007 from Tiadaghton Hill Road to Stony Fork Creek, Delmar Township, Project ID 99201

Project Allocation

519,000

(Base Project Allocation - $473,000)

(Design & Contingencies - $46,000)

(83) SR 3011, Resurface, SR 3011 from Calkins Road to Valley View Estate Road, Charleston Township, Project ID 99202

Project Allocation

323,000

(Base Project Allocation - $292,000)

(Design & Contingencies - $31,000)

(84) SR 4002, Resurface, SR 4002 from US 6 to Fellows Avenue, Wellsboro Borough, Project ID 99204

Project Allocation

123,000

(Base Project Allocation - $78,000)

(Design & Contingencies - $45,000)

(85) SR 4009, Resurface, SR 4009 from PA 49 to the New York State Line, Brookfield and Westfield Townships, Project ID 99206

Project Allocation

926,000

(Base Project Allocation - $877,000)

(Design & Contingencies - $49,000)

(86) SR 4023, Resurface, SR 4023 from PA 49 to the New York State Line, Elkland Borough, Project ID 99209

Project Allocation

399,000

(Base Project Allocation - $359,000)

(Design & Contingencies - $40,000)

(87) SR 4039, Resurface, SR 4039 from SR 4037 to Reese Hill Road, Charleston Township, Project ID 99214

Project Allocation

588,000

(Base Project Allocation - $542,000)

(Design & Contingencies - $46,000)

(88) SR 4039, Resurface, SR 4039 from Reese Hill Road to SR 0287, Charleston and Middlebury Townships, Project ID 99217

Project Allocation

671,000

(Base Project Allocation - $620,000)

(Design & Contingencies - $51,000)

(89) SR 0049, Resurface, PA 49 from Woodbine Avenue to Troups Creek, Deerfield Township, Knoxville Borough, Westfield Township, Project ID 99224

Project Allocation

168,000

(Base Project Allocation - $93,000)

(Design & Contingencies - $75,000)

(90) SR 0549, Highway Portion Bridge Replacement, PA 549 over Tributary of Mill Creek, Rutland Township, Project ID 99315

Project Allocation

1,400,000

(Base Project Allocation - $1,400,000)

(91) SR 0249, Highway Portion Bridge Replacement, PA 249 over Tributary of Crooked Creek, Chatham Township, Project ID 99314

Project Allocation

1,400,000

(Base Project Allocation - $1,400,000)

(92) SR 0414, Highway Portion Bridge Rehabilitation, PA 414 over Blockhouse Creek, Liberty Borough, Project ID 99312

Project Allocation

1,000,000

(Base Project Allocation - $1,000,000)

(93) SR 4017, Slide Repair, SR 4017 from Briar Hill Road to Osceola, Osceola Township, Project ID 98117

Project Allocation

1,400,000

(Base Project Allocation - $1,200,000)

(Land Allocation - $50,000)

(Design & Contingencies - $150,000)

(94) SR 2022, Resurface, SR 2022 from Welch Mountain Road to Corey Creek, Sullivan Township, Project ID 99196

Project Allocation

559,000

(Base Project Allocation - $518,000)

(Design & Contingencies - $41,000)

(95) SR 2005, Highway Portion Bridge Replacement, SR 2005 over Frost Creek, BMS 58-2005-0300-0000, Covington Township, Project ID 99140

Project Allocation

1,400,000

(Base Project Allocation - $1,400,000)

(96) SR 0006, Resurface, US 6 from Sassafras Street to 0.5 Mile East of Old Mainsburg Road, Mansfield Borough, Richmond Township, Project ID 99424

Project Allocation

2,900,000

(Base Project Allocation - $2,900,000)

(97) SR 0006, Reconstruction, US 6 from 0.5 Mile East of Old Mainsburg Road to Strange Road, Richmond and Sullivan Townships, Project ID 99426

Project Allocation

8,250,000

(Base Project Allocation - $8,250,000)

(98) SR 0414, Highway Portion Bridge Rehabilitation, PA 414 over Blacks Creek, BMS 58-0414-0350-0000, Liberty Township, Project ID 99136

Project Allocation

400,000

(Base Project Allocation - $400,000)

(99) SR 0015, Resurface, US 15 from SR 2005 to Tioga River, Blossburg Borough, Covington and Richmond Townships, Project ID 99427

Project Allocation

4,375,000

(Base Project Allocation - $4,375,000)

(100) SR 0287, Reconstruction, PA 287 from US 15 to Tioga River, Lawrence Township, Lawrenceville Borough, Tioga Township, Project ID 99428

Project Allocation

9,350,000

(Base Project Allocation - $9,350,000)

(101) SR 0287, Resurface, PA 287 from Crooked Creek to Bentley Creek, Tioga Borough, Tioga Township, Project ID 99429

Project Allocation

3,375,000

(Base Project Allocation - $3,375,000)

(102) SR 0549, Resurface, PA 549 from US 6 to SR 1005, Richmond Township, Roseville Borough, Rutland and Sullivan Townships, Project ID 99441

Project Allocation

3,040,000

(Base Project Allocation - $3,040,000)

(103) SR 2022, Highway Portion Bridge Rehabilitation, SR 2022 over a Tributary of Corey Creek, Sullivan Township, Project ID 98478

Project Allocation

700,000

(Base Project Allocation - $700,000)

(104) SR 1013, Highway Portion Bridge Rehabilitation, SR 1013 over Hammond Creek, BMS 58-1013-0100-2257, Jackson Township, Project ID 99139

Project Allocation

800,000

(Base Project Allocation - $800,000)

(105) SR 1001, Resurface, SR 1001 from SR 0006 to SR 4002, Charleston Township, Project ID 99167

Project Allocation

72,000

(Base Project Allocation - $56,000)

(Design & Contingencies - $16,000)

(106) SR 0328, Resurface, SR 0328 from Button Hill Road to SR 1013, Jackson Township, Project ID 99151

Project Allocation

102,000

(Base Project Allocation - $62,000)

(Design & Contingencies - $40,000)

(107) SR 0660, Resurface, SR 0660 from Spencer Road to SR 2005, Covington and Richmond Townships, Project ID 99161

Project Allocation

112,000

(Base Project Allocation - $66,000)

(Design & Contingencies - $46,000)

(108) SR 0660, Resurface, SR 0660 from Benauer Road to SR 0287, Wellsboro Borough, Project ID 99165

Project Allocation

33,000

(Base Project Allocation - $7,000)

(Design & Contingencies - $26,000)

(109) SR 0015, Guide Sign Upgrade, US 15, Various Municipalities, Project ID 99164

Project Allocation

75,000

(Base Project Allocation - $75,000)

(110) SR 0015, Guide Rail Upgrade, US 15 from PA 414 to PA 287, Tioga, Richmond, Covington, Bloss and Liberty Townships, Blossburg and Mansfield Boroughs, Project ID 99162

Project Allocation

2,350,000

(Base Project Allocation - $2,350,000)

(111) SR 0328, Resurface, SR 0328 from SR 1013 to the Bradford County Line, Jackson Township, Project ID 99152

Project Allocation

108,000

(Base Project Allocation - $63,000)

(Design & Contingencies - $45,000)

(112) SR 0006, Resurface, US 6 from the Potter County Line to Long Run, Gaines Township, Project ID 99160

Project Allocation

1,521,000

(Base Project Allocation - $1,501,000)

(Design & Contingencies - $20,000)

(113) SR 2027, Highway Portion Bridge Rehabilitation, SR 2027 over Canoe Camp Creek, Richmond Township, Project ID 98514

Project Allocation

900,000

(Base Project Allocation - $900,000)

(114) SR 0660, Resurface, SR 0660 from SR 4002 to Spencer Road, Charleston and Richmond Townships, Project ID 99154

Project Allocation

114,000

(Base Project Allocation - $68,000)

(Design & Contingencies - $46,000)

(115) SR 0349, Resurface, SR 0349 from Elk Lick Run to Mill Creek, Clymer Township, Project ID 99153

Project Allocation

121,000

(Base Project Allocation - $75,000)

(Design & Contingencies - $46,000)

(116) SR 4039, Highway Portion Bridge Rehabilitation, SR 4039 over Hills Creek, Charleston Township, Project ID 98515

Project Allocation

1,212,000

(Base Project Allocation - $1,201,000)

(Design & Contingencies - $11,000)

(117) SR 0660, Resurface, SR 0660 from Benauer Road to SR 0287, Delmar Township, Wellsboro Borough, Project ID 99163

Project Allocation

235,000

(Base Project Allocation - $145,000)

(Design & Contingencies - $90,000)

(118) Various, Highway Portion Bridge Painting, Various State Routes, Various Municipalities, Project ID 97675

Project Allocation

1,712,000

(Base Project Allocation - $1,701,000)

(Design & Contingencies - $11,000)