Section 3. Itemization of public improvement projects.
Additional capital projects in the category of public improvement projects to be constructed or acquired by the Department of General Services, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated financial costs, as follows:
Total
Project
Project
Allocation
(1) Department of Agriculture
(i) Farm Show Complex
(A) Removal of piping and ducting which contain asbestos materials and/or encapsulation of asbestos-containing materials in large arena
$785,000
(Base Project Allocation - $654,000)
(Design and Contingencies - $131,000)
(B) Reconstruction of roof system, including supporting joists, framing, decking, asbestos abatement and exterior materials involving 455,000 square feet over all main exhibition areas. Project must be fully evaluated regarding feasibility and costs of alternatives to reconstructing the existing design before implementation
9,000,000
(Base Project Allocation - $7,500,000)
(Design and Contingencies - $1,500,000)
(C) Conversion of one existing boiler to a gas/oil-fired unit to allow flexible operations at lower pressures
420,000
(Base Project Allocation - $350,000)
(Design and Contingencies - $70,000)
(D) Exterior cleaning, sealing and reconstruction of masonry walls and decorative friezes of main building
1,800,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $300,000)
(E) Land acquisition and construction of parking lot
3,000,000
(Base Project Allocation - $3,000,000)
(ii) Laboratory
(A) Construction of a bio-level 3 agriculture laboratory
13,000,000
(Base Project Allocation - $10,500,000)
(Design and Contingencies - $2,500,000)
(iii) Fayette County Agricultural Education Center
(A) Land acquisition, development and construction for the Fayette County Agricultural Education Center
1,000,000
(2) Department of Community and Economic Development
(i) Nemacolin Industrial Park, Greene County
(A) Phase I site development, environmental assessment and cleanup and improvements to port facilities
10,000,000
(ii) Former Curtis Wright facility, Clearfield County
(A) Relocation of the manufacturing plant at the former Curtis Wright facility
2,000,000
(iii) Washington County
(A) Repair and mitigation of flood-damaged facilities in Charleroi Borough, Twilight Borough, California Borough and Fallowfield Township due to flash flooding in June 2002
3,000,000
(iv) Fayette County
(A) Repair and mitigation of flood-damaged facilities in Brownsville Borough due to flash flooding in 2002
1,000,000
(v) Office of PennPORTS
(A) Construction of streetscape improvements, including lighting amenities, along the Benjamin Franklin Parkway in the City of Philadelphia
2,500,000
(3) Department of Conservation and Natural Resources
(i) Forest District 13
(A) Construct fire station replacement
750,000
(Base Project Allocation - $625,000)
(Design and Contingencies - $125,000)
(ii) Forest Districts 12 and 16
(A) Construct infrastructure to support Pine Creek Trail
3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(iii) Fort Indiantown Gap
(A) Construct forest fire protection equipment warehouse and training facility
3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(iv) Chapman Dam State Park
(A) Flood damage repairs, renovations and provide increased handicapped accessibility
550,000
(v) Cowans Gap State Park
(A) Repair dam control tower and gate valve
700,000
(vi) Delaware Canal State Park
(A) Small flood control project at Bock and Brock Creeks at Yardley Borough
656,000
(Base Project Allocation - $525,000)
(Design and Contingencies - $131,000)
(B) Design and build realignment of the canal at Morrisville Borough
219,000
(Base Project Allocation - $175,000)
(Design and Contingencies - $44,000)
(C) Small habitat restoration at Tullytown Borough
110,000
(Base Project Allocation - $88,000)
(Design and Contingencies - $22,000)
(D) Design and build new canal towpath access and related wall structures at Tullytown Borough
438,000
(Base Project Allocation - $350,000)
(Design and Contingencies - $88,000)
(E) Emergency streambank and shoreline protection at Paunacussing Creek at Solebury Township
438,000
(Base Project Allocation - $350,000)
(Design and Contingencies - $88,000)
(F) Land acquisition and improvements for park use which may include the construction of a visitors center
6,000,000
(vii) Forbes State Park
(A) Acquisition of the Henderson Tract in Donegal Township, Westmoreland County, including surface and mineral rights for protection of the Indian Creek headwaters and inclusion in State Park
750,000
(viii) Greenwood Furnace State Park
(A) Construct rental cabins and support facility
1,500,000
(ix) Greenwood Furnace and Whipple Dam State Park
(A) Rehabilitate beaches and accesses
1,000,000
(x) Jacobsburg Environmental Center
(A) Construct a replacement visitor, educational and administrative facility
4,000,000
(Base Project Allocation - $3,520,000)
(Design and Contingencies - $480,000)
(xi) Lackawanna State Park
(A) Construction of improvements and additional amenities
200,000
(xii) Lehigh Gorge State Park
(A) Park improvements
2,925,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $425,000)
(xiii) Lyman Run State Park
(A) Additional funds for DGS Project 170-11, rehabilitation and construction of a new dam
3,000,000
(xiv) Marsh Creek State Park
(A) Construct access road and recreational facilities
3,500,000
(Base Project Allocation - $3,500,000)
(xv) Oil Creek State Park
(A) Rehabilitate and enlarge train station
100,000
(B) Design, production and installation of exhibits
201,000
(C) Reconstruction and rehabilitation of historic buildings at Petroleum Center
2,000,000
(xvi) Poe Valley State Park
(A) Rehabilitate dam
5,000,000
(Base Project Allocation - $4,165,000)
(Design and Contingencies - $835,000)
(xvii) Presque Isle State Park
(A) Acquisition and development of property to expand walking and bike trails, make erosion control improvements and other environmental protection measures to protect Lake Erie and enhance Presque Isle State Park
20,000,000
(B) Additional funds for project DGS 163-34, construction of Presque Isle Center, including fixed exhibits
3,000,000
(C) State share of the cost of replenishing the sand on the lakeside shore
650,000
(Base Project Allocation - $650,000)
(D) Beach nourishment and breakwater maintenance
5,800,000
(E) Rehabilitation of comfort facilities and sewage system
1,800,000
(F) Rehabilitation of Presque Isle Marina
962,000
(xviii) Pymatuning State Park
(A) Linesville spillway improvements
2,407,000
(Base Project Allocation - $2,012,000)
(Design and Contingencies - $395,000)
(xix) Raccoon Creek State Park
(A) Construct a hike-and-bike trail along the northern edge of Raccoon Lake
2,500,000
(Base Project Allocation - $2,075,000)
(Design and Contingencies - $425,000)
(xx) Shawnee State Park
(A) Construct rental cabins and support facilities
1,500,000
(B) Additional funds for DGS 155-11, replacement of two bridges on main park road
900,000
(xxi) Shikellamy State Park
(A) Construction of a fish passage at the Fabridam in Sunbury. This project shall be construed as a supplement to the project authorized in section 4(1)(vi)(B) of the act of May 22, 2000 (P.L.104, No.22), known as the Capital Budget Debt Authorization and Project Itemization Act of 2000-2001
2,500,000
(Base Project Allocation - $2,500,000)
(B) Park entrance project
500,000
(Base Project Allocation - $500,000)
(C) For creation of permanent secondary access to the park, completion of needed repairs to existing restaurant facility and the acquisition of riverfront land on the west shore of the Susquehanna River for park expansion and rowing facilities
300,000
(xxii) Swatara State Park
(A) Rausch Creek Acid Mine Drainage Treatment Plant, additional treatment units and chemical feeding equipment to accommodate increased water flow due to the diversion of water from the Swatara Creek to the Rausch Creek
4,500,000
(Base Project Allocation - $3,800,000)
(Design and Contingencies - $700,000)
(xxiii) Yellow Creek State Park
(A) Replacement of underground electrical service and related facilities
1,000,000
(xxiv) Kinzua Bridge State Park
(A) Structural rehabilitation and painting of a historical landmark bridge
10,800,000
(Base Project Allocation - $9,000,000)
(Design and Contingencies - $1,800,000)
(xxv) East Coast Greenway - Pennsylvania section
(A) Construction of a 40-mile section from Bristol to Marcus Hook, including a combination of on-road bicycle lanes and off-road multipurpose trails
33,000,000
(Base Project Allocation - $25,000,000)
(Land Acquisition - $7,000,000)
(Design and Contingencies - $1,000,000)
(B) Planning and preliminary engineering for sections in Bucks, Philadelphia and Delaware Counties
500,000
(Base Project Allocation - $500,000)
(C) Construction of a ten-mile section from Morrisville to Bristol
9,000,000
(Base Project Allocation - $8,000,000)
(Land Acquisition - $500,000)
(Design and Contingencies - $500,000)
(xxvi) Elk County
(A) For acquisition, construction and rehabilitation of the Elk Viewing Center in Benezette Township
1,000,000
(xxvii) Norristown Farm Park
(A) Renovation of the Dairy Barn
163,000
(B) Renovation and repair of the maintenance center
150,000
(xxviii) City of Philadelphia
(A) For demolition, remediation, abatement and removal of all hazardous materials on two parcels totaling 44.8874 acres of the former Philadelphia State Hospital for recreation and open-green space
2,000,000
(xxix) Clearfield County
(A) Acquisition and construction of an ATV trail on land formerly used for mining in Clearfield
5,000,000
(4) Department of Corrections
(i) State Correctional Institution at Cambridge Springs
(A) Additional funds for DGS Project 1579-5 for electrical upgrades
510,000
(Base Project Allocation - $425,000)
(Design and Contingencies - $85,000)
(ii) State Correctional Institution at Camp Hill
(A) New construction for Diagnostic and Classification Center
1,008,000
(Base Project Allocation - $840,000)
(Design and Contingencies - $168,000)
(B) Main steam tunnel renovations
4,110,000
(Base Project Allocation - $3,425,000)
(Design and Contingencies - $685,000)
(C) Replacement of Group 1 plumbing components
4,110,000
(Base Project Allocation - $3,425,000)
(Design and Contingencies - $685,000)
(iii) State Correctional Institution at Cresson
(A) Construction of new water tower
1,814,000
(Base Project Allocation - $1,512,000)
(Design and Contingencies - $302,000)
(iv) State Correctional Institution at Dallas
(A) Construct new Reception and Control Complex
4,646,000
(Base Project Allocation - $3,872,000)
(Design and Contingencies - $774,000)
(B) Water main replacement
5,246,000
(Base Project Allocation - $4,372,000)
(Design and Contingencies - $874,000)
(C) Reconstruction of three boilers, installation of new controls and reconstruction of support structures and associated fuel handling equipment
5,640,000
(Base Project Allocation - $4,700,000)
(Design and Contingencies - $940,000)
(v) State Correctional Institution at Forest County
(A) Additional funds for DGS project 377-1, construction of a 1,000-cell facility to change the security level from medium to close
5,000,000
(vi) State Correctional Institution at Frackville
(A) Fire alarm and security panel replacements
1,260,000
(Base Project Allocation - $1,050,000)
(Design and Contingencies - $210,000)
(vii) State Correctional Institution at Graterford
(A) Boiler renovations and water treatment plant construction
7,182,000
(Base Project Allocation - $5,985,000)
(Design and Contingencies - $1,197,000)
(B) Secondary electrical system upgrades
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(C) Sprinkler installation and ventilation and smoke/fire alarm systems changes
4,320,000
(Base Project Allocation - $3,600,000)
(Design and Contingencies - $720,000)
(viii) State Correctional Institution at Greensburg
(A) Construct new Warehouse, Freight Terminal and Grounds Shop
2,112,000
(Base Project Allocation - $1,760,000)
(Design and Contingencies - $352,000)
(B) Life safety and ADA upgrades
4,680,000
(Base Project Allocation - $3,900,000)
(Design and Contingencies - $780,000)
(C) Upgrade electric utility system
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(ix) State Correctional Institution at Laurel Highlands
(A) Construction of a restricted housing, close supervision and Step-Down Unit
900,000
(Base Project Allocation - $750,000)
(Design and Contingencies - $150,000)
(B) Upgrades to Sewage Treatment Plant
2,100,000
(Base Project Allocation - $1,750,000)
(Design and Contingencies - $350,000)
(x) State Correctional Institution at Mercer
(A) Expansion of kitchen/dining, administration and program facilities along with utilities including water, sewer and electric
6,000,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $1,000,000)
(xi) State Correctional Institution at Muncy
(A) Addition of two new cell blocks for close security, expansion of infirmary, outside warehouse, electrical and boiler upgrades
26,364,000
(Base Project Allocation - $21,970,000)
(Design and Contingencies - $4,394,000)
(xii) State Correctional Institution at Rockview
(A) Construct additional water supply pipeline
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(B) Construct new warehouse facility
3,780,000
(Base Project Allocation - $3,150,000)
(Design and Contingencies - $630,000)
(C) Construction of 30-cell addition to existing restricted housing unit
240,000
(Design and Contingencies - $240,000)
(xiii) State Correctional Institution at Waymart
(A) Boiler plant renovations
4,740,000
(Base Project Allocation - $3,950,000)
(Design and Contingencies - $790,000)
(B) Electrical system upgrade
3,180,000
(Base Project Allocation - $2,650,000)
(Design and Contingencies - $530,000)
(xiv) State Correctional Institution at Waynesburg
(A) Additional funds for DGS Project 1577-5, sewage treatment plant expansion
785,000
(Base Project Allocation - $654,000)
(Design and Contingencies - $131,000)
(B) Construct Inmate Housing and Transfer Station
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(xv) Department of Corrections
(A) Purchase of the following State Correctional Institutions - Greene, Albion, Mahanoy, Somerset and Coal Township, which were constructed using proceeds from the 1993 Certificates of Participation
510,000,000
(5) Department of Education
(i) Scranton School for the Deaf
(A) Boiler replacement
4,140,000
(Base Project Allocation - $3,600,000)
(Design and Contingencies - $540,000)
(B) Renovation of gymnasium
4,000,000
(Base Project Allocation - $3,333,000)
(Design and Contingencies - $667,000)
(C) Campus safety and grounds improvements
2,300,000
(Base Project Allocation - $1,920,000)
(Design and Contingencies - $380,000)
(D) Campus safety improvements
161,000
(Base Project Allocation - $140,000)
(Design and Contingencies - $21,000)
(ii) Thaddeus Stevens College of Technology
(A) Steam Plant upgrade/boiler replacement
2,000,000
(Base Project Allocation - $1,700,000)
(Design and Contingencies - $300,000)
(B) Remodeling, refurbishing and refurnishing of Armstrong, Metzger, Bourne and Harrington Halls
325,000
(C) Installation of new roofs on the Snyder Shop Building and the Leonard Shop Building
260,000
(D) Additional funds for Phase II of DGS Project 417-31 for renovation of two fire towers
1,000,000
(E) Repair of high-voltage lines
200,000
(Base Project Allocation - $200,000)
(F) Additional funds for DGS Project 417-31, renovation of fire towers, at Brenner, Bourne and Metzger Halls
770,000
(Base Project Allocation - $700,000)
(Design and Contingencies - $70,000)
(G) Installation of sprinkler systems in five dormitories
4,600,000
(Base Project Allocation - $4,000,000)
(Design and Contingencies - $600,000)
(H) Additional funds for DGS Project 417-38, reconstruction of utilities tunnel along with steam and condensate lines
500,000
(iii) The Pennsylvania State University
(A) Construct multistory classroom at Altoona Campus
8,000,000
(B) Construction of new multipurpose activity building at Altoona Campus
4,750,000
(C) Construction of maintenance building at Behrend College
2,100,000
(Base Project Allocation - $1,750,000)
(Design and Contingencies - $350,000)
(D) Renovation and upgrades for the Otto Behrend Building at Behrend College
3,750,000
(E) Construction of a new classroom and lab building, Berks Campus
11,100,000
(Base Project Allocation - $11,100,000)
(F) Capital renewal projects, Central Campuses (Altoona, Mont Alto, Harrisburg, Schuylkill, York and Dickinson School of Law)
7,000,000
(Base Project Allocation - $7,000,000)
(G) Addition to and renovation of Smeal Building at DuBois Campus
1,700,000
(H) Capital renewal projects, Eastern Campuses (Worthington, Scranton, Wilkes-Barre, Hazleton, Lehigh Valley, Berks, Abington and Delaware County)
7,000,000
(Base Project Allocation - $7,000,000)
(I) Construction of a new multiuse building at Fayette Campus
5,000,000
(J) Construction of medical facilities for children's and cancer treatment, Hershey Medical Center
48,000,000
(Base Project Allocation - $48,000,000)
(K) Capital renewal projects, Western Campuses (Erie, Shenango, DuBois, Beaver, New Kensington, McKeesport and Fayette)
7,000,000
(Base Project Allocation - $7,000,000)
(L) Construct library/classroom at York Campus
11,900,000
(Base Project Allocation - $9,916,000)
(Design and Contingencies - $1,984,000)
(M) Renovation of Chandlee Laboratory at University Park
10,200,000
(N) Environmental improvements at University Park
20,000,000
(O) Renovation of Borland Laboratory at University Park
12,000,000
(P) Construction of a new forestry resources building at University Park
24,500,000
(Q) Construction of a new food science building at University Park
28,800,000
(R) Addition to and renovation of the Moore Building, University Park Campus
22,500,000
(Base Project Allocation - $22,500,000)
(S) Capital renewal projects, University Park Campus
40,000,000
(Base Project Allocation - $40,000,000)
(T) Construction of materials sciences building at University Park
80,000,000
(iv) Pennsylvania College of Technology
(A) Construction of a new library facility
7,000,000
(B) Capital improvements for the Community Arts Center
276,000
(v) University of Pittsburgh
(A) Upgrade and deferred maintenance for buildings and building systems, Phase I, at Oakland Campus
12,000,000
(B) Renovation of Trees Hall and Fitzgerald Field House, Phase I, at Oakland Campus
11,300,000
(C) Renovation of the Cathedral of Learning at Oakland Campus
150,000,000
(D) Additional funds for Hillman Library Renovation, Phase II, at Oakland Campus
9,600,000
(E) Communications, Art and Technology Building at Bradford Campus
7,700,000
(F) Additional funds for library renovations at Johnstown Campus
1,580,000
(G) Acquisition and application of green environmental technologies in the construction of a new children's hospital of the Medical Center
7,000,000
(H) Construction of Peterson Events Center - Student Recreation Center
10,000,000
(I) Construction of Biomedical Science Tower 3
50,000,000
(J) Additional funds for DGS 1103-63, for upgrade and deferred maintenance for buildings and building systems, including an addition to Clapp/Langley/Crawford Halls
20,000,000
(K) Upgrade and deferred maintenance for buildings and building systems, Phase II
14,000,000
(L) Center for Creative and Performing Arts
10,000,000
(vi) Temple University
(A) Design and construction of an Ambler Learning Center
14,550,000
(B) Design and construction of Mini-Arts Campus primarily for the arts at the Main Campus
55,880,000
(C) Design and construction of a new multipurpose health sciences building to include a medical school, research facility and library
50,000,000
(D) Addition and renovation of student center on main campus
15,000,000
(E) Main campus, College Hall renovations, Phase II
850,000
(F) Additional funds for DGS 1104-53, classroom and laboratory building
3,000,000
(G) Design and construction of an annex to and renovation of the Fox School of Business and Management Building on Main Campus
25,525,000
(H) Design and construction for the renovation or replacement of research facilities, Kresge Science Hall
17,647,000
(I) Design and construction for the renovation or replacement of research facilities, Medical Research Building
12,993,000
(J) Design and construction for the renovation or replacement of research facilities, Old Medical School
33,540,000
(K) Design and construction for the renovation of research facilities, Bio-Life Sciences Building
27,181,000
(L) Design and construction for the renovation of research facilities, Beury Hall
21,285,000
(M) Design and construction for the renovation of research facilities, Barton Hall
10,160,000
(N) Design and construction for restoration of the Historic Baptist Temple on Main Campus
22,045,000
(O) Design and construction for the renovation or replacement of research facilities, Pharmacy Building
8,135,000
(P) Design and construction of Athletic Facility to replace Temple Stadium
6,000,000
(vii) Lincoln University
(A) Construction of storm water drainage system, including piping and a detention basin to prevent hydraulic overload of the sewer system
1,084,000
(Base Project Allocation - $903,000)
(Design and Contingencies - $181,000)
(6) Department of Environmental Protection
(i) Allegheny County
(A) Greenwald Road flood control project, DGS 184-20
2,060,000
(B) Additional funds for DGS 184-20, culverts and debris basin along tributary to Grassers Run, Bethel Park Borough
1,113,000
(C) Logan Creek flood control project, Bethel Park Borough
1,000,000
(D) Lewis Run flood control project, Jefferson Hills Borough
1,000,000
(E) Comprehensive regional flood mitigation/storm water management plan, South Hills Area Council of Governments
3,000,000
(F) Additional funds for DGS 184-18, construction of levee, floodplain excavation and concrete retaining wall along Pine Creek, Shaler Township
360,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $60,000)
(G) Additional funds for DGS 183-15 to recut the channel in Long Run Watershed, City of McKeesport
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(ii) Beaver County
(A) Beaver River silt control and prevention program
500,000
(iii) Bedford County
(A) Borough of Hyndman, flood protection project
3,000,000
(iii.1) Berks County
(A) Replacement of Felix Dam
3,900,000
(iv) Blair County
(A) Mill Run Creek Flood Protection Project, City of Altoona, Logan and Allegheny Townships
11,224,000
(v) Bucks County
(A) Neshaminy Creek flood mitigation project
14,000,000
(B) Drainage improvements, Route 413 to Neshaminy Creek, Croydon and Bristol Townships
5,000,000
(C) Additional funds for DGS 181-12, rehabilitation of Morrisville flood protection project in the Borough of Morrisville
240,000
(Base Project Allocation - $200,000)
(Design and Contingencies - $40,000)
(D) Otter Creek flood mitigation project
14,000,000
(vi) Butler County
(A) Continuation of Sullivan Run streambank stabilization project in the City of Butler
500,000
(B) Continuation of the Sullivan Run Channel Improvement Project, City of Butler
3,600,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $600,000)
(C) Storm water flooding project, Butler Township
2,760,000
(Base Project Allocation - $2,760,000)
(vii) Cambria County
(A) Design and construction of a collapsible dam on the Conemaugh River to provide for recreational opportunities
5,000,000
(viii) Chester County (Reserved)
(ix) Chester and Montgomery Counties
(A) Demolition and removal of Vincent Dam on the Schuylkill River, East Vincent and Limerick Townships
420,000
(Base Project Allocation - $350,000)
(Design and Contingencies - $70,000)
(x) Clearfield County
(A) Channel improvements and restoration to Bell Run
3,000,000
(B) Channel improvements and restoration to Emigh Run
3,000,000
(C) Channel improvements and restoration to Clearfield Creek Tributaries
4,000,000
(D) Channel improvements and restoration to Hubler and Adler Runs
3,000,000
(E) Channel improvements and restoration to Anderson Creek, Curwensville Borough
3,000,000
(F) Stream channel clearing and restoration, Decatur Township, Woodward Township and Houtzdale Borough
5,000,000
(G) Flood control projects, including repair of the culvert box for the complete length of the canal, Osceola Mills Borough
3,000,000
(H) Stream channel clearing and restoration, Rush Township and Osceola Borough
5,000,000
(I) Stream channel clearing and restoration, Westover Borough and Chest Township
6,000,000
(J) Additional funds for DGS 182-14, construction of levees and flood walls, Coalport Borough
3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(K) Remediation of radioactive contamination and waste at the former Curtis Wright facility
10,000,000
(L) Construction of water impoundment structure in Beccaria Township
4,000,000
(M) Reconstruction of Brown's Run stream bed from damage caused by abandoned mine
750,000
(x.1) Delaware County
(A) Stony Creek Storm Water Management Project, design and construction of best management practices of management of storm water and improvement of storm water quality in Springfield Township
500,000
(Base Project Allocation - $500,000)
(xi) Fayette County
(A) Additional funds for DGS 180-23, construction of retaining walls and culverts and excavation to widen or deepen Dunbar Creek and Gist Run channel in Dunbar
396,000
(Base Project Allocation - $330,000)
(Design and Contingencies - $66,000)
(B) Repair and mitigation of flood-damaged facilities in Brownsville Borough due to flash flooding in 2002
1,000,000
(xii) Indiana County
(A) Blue Spruce Park renovation and Cummings Dam or Cummins Dam restoration project
1,000,000
(B) Borough of Indiana, flood protection project
1,320,000
(Base Project Allocation - $1,100,000)
(Design and Contingencies - $220,000)
(xiii) Lackawanna County
(A) Funds for DGS 184-22, Phase II, flood control project on Meadowbrook Creek, City of Scranton and Borough of Dunmore
6,200,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $1,200,000)
(B) Funds for DGS 184-22, flood control project on Leggetts Creek, City of Scranton
4,800,000
(C) Funds for DGS 184-22, flood control project on Keyser Creek, City of Scranton
4,800,000
(D) Funds for DGS 184-22, flood control project on Lucky-Run Creek, City of Scranton
2,400,000
(E) Funds for DGS 184-22, flood control project on Leach Creek, City of Scranton
2,400,000
(F) Stream restoration of Scott Creek in Dickson City Borough
800,000
(G) Rushbrook Creek Project in Jermyn Borough
4,500,000
(H) Additional funds for DGS flood control projects on Lucky Run Creek, Lindy Creek, Keyser Creek, Leach Creek, Meadowbrook Creek, Leggetts Creek, unnamed tributary of Keyser Creek adjacent to Oakwood Estates, Mountain Lake Creek, Stafford Meadowbrook Creek, Roaring Brook Creek and tributaries, City of Scranton
12,000,000
(Base Project Allocation - $10,000,000)
(Design and Contingencies - $2,000,000)
(I) Flood control project along the Lackawanna River and its tributaries, Borough of Moosic
12,000,000
(Base Project Allocation - $10,000,000)
(Design and Contingencies - $2,000,000)
(J) Flood control project along Leggetts Creek and its tributaries, South Abington Township
7,200,000
(Base Project Allocation - $6,000,000)
(Design and Contingencies - $1,200,000)
(K) Flood control project along Railroad Street in the Borough of Moosic
2,000,000
(L) Storm water abatement study in South Abington Township
1,000,000
(xiv) Luzerne County
(A) Construction of compact earth levee in area of Fox Hill in Plains Township, including grass-covered channel
240,000
(Base Project Allocation - $200,000)
(Design and Contingencies - $40,000)
(B) Flood wall improvement project, Newport Creek, Newport Township
240,000
(C) Additional funds for DGS Project 184-23, flood control project on Mill Creek, Dupont Borough
3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(D) Borough of Duryea, rehabilitation of flood protection project
1,800,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $300,000)
(E) Borough of Yatesville, flood protection project
1,320,000
(Base Project Allocation - $1,100,000)
(Design and Contingencies - $220,000)
(xiv.1) Lycoming County
(A) Removal of logging cribs and dredging of the Susquehanna River from the Arch Street Bridge in Williamsport to Jersey Shore, Lycoming County
3,500,000
(Base Project Allocation - $3,500,000)
(xv) McKean County
(A) Rehabilitation of the flood protection project along the west and main branches of the Tunungwant Creek
1,000,000
(xvi) Monroe County
(A) Restoration project for the Delaware Water Gap Station
1,000,000
(xvii) Montgomery County
(A) Sandy Run drainage shed flood control improvements
6,000,000
(B) Lower Moreland and Abington Townships flood control project, including the removal of the Old Huntingdon Pike Bridge over the Pennypack Creek
250,000
(C) Lower Moreland and Abington Townships flood control project, including the removal of an abandoned Conrail bridge over the Pennypack Creek
500,000
(xviii) Montour County
(A) Additional funds for DGS Project 181-5, flood protection project, Borough of Danville
1,440,000
(Base Project Allocation - $1,200,000)
(Design and Contingencies - $240,000)
(xix) Northumberland County
(A) Milton Borough flood control project
300,000
(B) Sunbury flood protection project, bank stabilization and reconstruction
540,000
(Base Project Allocation - $540,000)
(C) For flood control along the Little Shamokin Creek in Upper Augusta Township
190,000
(xx) Tioga County
(A) Flood protection project, Knoxville Borough
5,100,000
(Base Project Allocation - $4,250,000)
(Design and Contingencies - $850,000)
(xxi) Warren County
(A) Various flood protection projects
2,500,000
(xxii) Washington County
(A) Repair and mitigation of flood-damaged facilities in Charleroi Borough, Twilight Borough, California Borough and Fallowfield Township due to flash flooding in June 2002
3,000,000
(xxiii) Westmoreland County
(A) Additional funds for DGS Project 180-42, Mount Pleasant Street and Highland Avenue flood protection project, Greensburg Borough
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(B) Rehabilitation of the Greater Greensburg area flood protection project, South Greensburg Borough and Hempfield Township
10,800,000
(Base Project Allocation - $9,000,000)
(Design and Contingencies - $1,800,000)
(xxiv) York County
(A) City of York, Spring Garden Township and York Township, Tyler Run Flood Control Project
2,500,000
(B) Spring Garden Township, Springettsbury Township and York Township, Mill Creek Flood Control Project
5,000,000
(C) Yoe Borough and York Township, construction of retention basins on Mill Creek between Locust Avenue in York Township and Boundary Avenue in Yoe Borough
400,000
(D) Construction of flood retention basins, Dallastown Borough and York Township
350,000
(E) Construction of flood retention basins, Powder Mill and Tyler Run Roads
505,000
(7) Department of General Services
(i) Capitol Complex
(A) Renovations to the Forster Street Office Building
3,120,000
(Base Project Allocation - $2,600,000)
(Design and Contingencies - $520,000)
(B) Infrastructure renovations and upgrades to the State Museum of Pennsylvania and Archives Buildings and adjoining plaza
70,000,000
(Base Project Allocation - $61,000,000)
(Design and Contingencies - $9,000,000)
(C) Renovations and upgrades to exhibits and galleries at the State Museum of Pennsylvania
22,000,000
(Base Project Allocation - $19,000,000)
(Design and Contingencies - $3,000,000)
(D) Construction of the Pennsylvania Judicial Center, including parking facilities
123,000,000
(Base Project Allocation - $98,400,000)
(Design and Contingencies - $24,600,000)
(E) Restoration of Main Capitol Building, including life safety and utility upgrades
30,785,000
(F) ((F) repealed June 22, 2004, P.L.257, No.40)
(G) Additional funding for DGS Project 948-34, repair and restoration work for statuaries and north, south and center porticoes and plaza level entries of the Capitol Building to continue the repair and restoration of the masonry to the porches and porticoes of the Capitol Building
1,000,000
(Base Project Allocation - $800,000)
(Design and Contingencies - $200,000)
(H) Upgrade fire alarm and security systems in the State Museum and Archives Building
700,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $100,000)
(I) Upgrade and installation of new fire suppression system in the State Museum and Archives Buildings
1,875,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $375,000)
(J) ((J) repealed June 22, 2004, P.L.257, No.40)
(K) Additional funds for DGS Project 948-37, connecting Main Capitol Building to central chilled water plant
6,000,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $1,000,000)
(L) Replace elevator system at Northwest Office Building
600,000
(Base Project Allocation - $600,000)
(M) ((M) repealed June 22, 2004, P.L.257, No.40)
(ii) Commonwealth Mail Processing and Legislative Services Facility
(A) Construction of the House of Representatives portion of the facility
10,000,000
(iii) Governor's residence
(A) Additional funds for DGS Project 949-4, upgrade heating, ventilating and air conditioning systems
322,000
(Base Project Allocation - $268,000)
(Design and Contingencies - $54,000)
(iv) Pittsburgh State Office Building
(A) Interior and exterior renovations
10,428,000
(Base Project Allocation - $8,690,000)
(Design and Contingencies - $1,738,000)
(v) David L. Lawrence Convention Center
(A) Continued expansion of the convention center, including riverfront development and related improvements
35,000,000
(vi) Warner Theater, Erie County
(A) Conversion of the theater into a performing arts center, including additions to the stage area, improvements to mechanical systems and installation of elevators
12,000,000
(vii) Louis J. Tullio Convention Arena
(A) Repair facade and replace equipment
1,950,000
(viii) Philadelphia State Office Building
(A) Renovations and improvements to the Philadelphia State Office Building
30,500,000
(Base Project Allocation - $25,050,000)
(Design and Contingencies - $5,450,000)
(ix) Commonwealth Technology Center, Dauphin County
(A) Security and availability of operations improvements
6,047,000
(Base Project Allocation - $5,039,000)
(Design and Contingencies - $1,008,000)
(x) Philadelphia County
(A) Additional funds for DGS 522-2, Diagnostic and Rehabilitation Center in Philadelphia
4,000,000
(Base Project Allocation - $4,000,000)
(xi) Erie Convention Center Authority
(A) Jerry Uht Ballpark upgrades and equipment replacement
1,780,000
(8) Pennsylvania Historical and Museum Commission
(i) Anthracite Heritage Museum
(A) Replace heating, ventilating and air conditioning system
1,800,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $300,000)
(B) Installation of fire protection system
360,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $60,000)
(ii) Brandywine Battlefield Historic Park
(A) Installation of fire protection system
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(B) Construct new or renovate and expand existing visitor center
4,200,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $700,000)
(iii) Conrad Weiser Historic Park
(A) Installation of fire protection system
360,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $60,000)
(B) Restoration of pond at Conrad Weiser Homestead
412,000
(iv) Cornwall Iron Furnace
(A) Installation of fire protection system
360,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $60,000)
(v) Drake Well Museum
(A) Improvements to collection storage and research center
1,640,000
(Base Project Allocation - $1,367,000)
(Design and Contingencies - $273,000)
(B) Boomtown and other exhibit development and construction
5,000,000
(C) Installation of fire protection system
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(vi) Eckley Miners' Village
(A) Restoration of miners' houses
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(B) Installation of fire protection system
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(C) Replace existing wastewater treatment plant
1,440,000
(Base Project Allocation - $1,200,000)
(Design and Contingencies - $240,000)
(vii) Ephrata Cloister
(A) Installation of fire protection system
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(viii) Fort Pitt Museum
(A) Construction of gallery and permanent exhibits
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(ix) Old Economy Village
(A) Fabrication and installation of orientation exhibits in the visitor center
500,000
(Base Project Allocation - $417,000)
(Design and Contingencies - $83,000)
(x) Pennsbury Manor
(A) Permanent exhibits for DGS Project 971-5, construction of visitors center
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(B) Installation of fire protection system
720,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $120,000)
(C) Reconstruction and renovation of Pennsbury Manor
3,600,000
(xi) Pennsylvania Lumber Museum
(A) Installation of fire protection system
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(xii) Pennsylvania Military Museum
(A) Installation of fire protection system
180,000
(Base Project Allocation - $150,000)
(Design and Contingencies - $30,000)
(B) Museum expansion and visitor center
3,500,000
(Base Project Allocation - $2,917,000)
(Design and Contingencies - $583,000)
(xiii) Pithole State Museum
(A) Development and construction of exterior walkways, boardwalks and signage
100,000
(xiv) Railroad Museum of Pennsylvania
(A) Install upgraded HVAC System
5,000,000
(Base Project Allocation - $4,200,000)
(Design and Contingencies - $800,000)
(B) Installation of fire protection system
360,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $60,000)
(C) Construction of Round House
6,600,000
(Base Project Allocation - $6,000,000)
(Design and Contingencies - $600,000)
(D) Construction of exhibits
4,500,000
(xv) Somerset Historical Center
(A) Additional funds for DGS 990-2 for construction of fixed exhibits
150,000
(Base Project Allocation - $150,000)
(xvi) Thomas Hughes House
(A) Additional funds for DGS Project 979-25 for the restoration and improvement of the Thomas Hughes House
300,000
(Base Project Allocation - $250,000)
(Design and Contingencies - $50,000)
(xvii) Washington Crossing Historic Park
(A) Renovation of visitor center and new orientation exhibit
3,000,000
(Base Project Allocation - $2,557,000)
(Design and Contingencies - $443,000)
(B) Construction of pedestrian and maintenance bridge to soldiers' grave site
1,000,000
(Base Project Allocation - $1,000,000)
(C) Renovations to sewage treatment plants to meet current effluent and capacity standards for both upper and lower park
1,200,000
(Base Project Allocation - $1,200,000)
(D) Site improvements
7,800,000
(xviii) Installation of fire protection systems at each of the listed museums or parks:
(A) Daniel Boone Homestead
300,000
(Base Project Allocation - $250,000)
(Design and Contingencies - $50,000)
(B) Graeme Park
120,000
(Base Project Allocation - $100,000)
(Design and Contingencies - $20,000)
(C) Hope Lodge/Mather Mill
180,000
(Base Project Allocation - $150,000)
(Design and Contingencies - $30,000)
(D) Joseph Priestley House
150,000
(Base Project Allocation - $125,000)
(Design and Contingencies - $25,000)
(E) Landis Valley Museum
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(F) Old Economy Village
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(G) Washington Crossing Historic Park
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(xix) State Records Center
(A) Construct an addition to the State Records Center Annex
18,000,000
(Base Project Allocation - $15,000,000)
(Design and Contingencies - $3,000,000)
(xx) Point State Park
(A) Redevelopment
100,000,000
(xxi) Allegheny County
(A) Acquisition, renovation and construction of National Radio Museum in Forest Hills Borough
1,000,000
(xxii) Fayette County
(A) Renovation and repairs to the State Theatre
5,000,000
(9) Department of Military and Veterans Affairs
(i) Hollidaysburg Veterans Home, Blair County
(A) Install a backup water line
150,000
(Base Project Allocation - $125,000)
(Design and Contingencies - $25,000)
(B) Upgrade electrical distribution and plumbing in Eisenhower Hall and Dietary
708,000
(Base Project Allocation - $590,000)
(Design and Contingencies - $118,000)
(C) Steam line replacement and asbestos abatement
1,050,000
(Base Project Allocation - $875,000)
(Design and Contingencies - $175,000)
(D) Improvements to facility roadways and parking lots
1,000,000
(E) Installation of two elevators in Eisenhower Hall
240,000
(Base Project Allocation - $200,000)
(Design and Contingencies - $40,000)
(ii) Southeastern Veterans Center, Chester County
(A) Upgrade facility roadways
400,000
(Base Project Allocation - $400,000)
(iii) Pennsylvania Soldiers' and Sailors' Home, Erie County
(A) Roadway and parking area upgrades
325,000
(Base Project Allocation - $270,000)
(Design and Contingencies - $55,000)
(B) Addition of a dementia/Alzheimer's unit
6,000,000
(Base Project Allocation - $5,400,000)
(Design and Contingencies - $600,000)
(C) Construction of a dementia/Alzheimer's unit
2,302,000
(Base Project Allocation - $1,918,000)
(Design and Contingencies - $384,000)
(iv) Scotland School for Veterans' Children, Franklin County
(A) Renovation of Andrew Curtin Hall, junior high gymnasium and ten cottages
4,220,000
(Base Project Allocation - $3,517,000)
(Design and Contingencies - $703,000)
(B) Improvement and renovation of original farmhouse and cleanup and mitigation of hazards associated with a pond located on the property
200,000
(C) Renovation of student center, 13 cottages, Frey Gymnasium, a warehouse and maintenance building
4,716,000
(Base Project Allocation - $3,930,000)
(Design and Contingencies - $786,000)
(v) Combined Readiness Center/Operations Maintenance Shop, Adams County
(A) Land acquisition for a combined readiness center/operations maintenance shop
1,300,000
(Land Allocation - $1,300,000)
(vi) Readiness Center, Bedford or Huntington County
(A) Land acquisition for a readiness center
700,000
(Land Allocation - $700,000)
(vii) Readiness Center, Cambria or Centre County
(A) Land acquisition for a readiness center
700,000
(Land Allocation - $700,000)
(viii) Operations Maintenance Shop, Chester County
(A) Land acquisition for an operations maintenance shop
400,000
(Land Allocation - $400,000)
(ix) Readiness Center, Cumberland County
(A) Land acquisition for a readiness center
1,200,000
(Land Allocation - $1,200,000)
(x) Readiness Center, Delaware County
(A) Land acquisition for a readiness center
1,600,000
(Land Allocation - $1,600,000)
(xi) Combined Readiness Center/Operations Maintenance Shop, Erie County
(A) Land acquisition for a combined readiness center/operations maintenance shop
1,750,000
(Land Allocation - $1,750,000)
(xii) Northeastern Veterans Center, Lackawanna County
(A) Upgrade floor covering
510,000
(Base Project Allocation - $510,000)
(xiii) Combined Readiness Center/Operations Maintenance Shop, Lancaster County
(A) Land acquisition for a combined readiness center/operations maintenance shop
1,925,000
(Land Allocation - $1,925,000)
(xiv) Fort Indiantown Gap Readiness Center, Lebanon County
(A) Construction of a readiness center
4,400,000
(Base Project Allocation - $3,667,000)
(Design and Contingencies - $733,000)
(xv) Combined Readiness Center/Operations Maintenance Shop, McKean or Elk County
(A) Land acquisition for a combined readiness center/operations maintenance shop
825,000
(Land Allocation - $825,000)
(xvi) Operations Maintenance Shop, Mifflin County
(A) Land acquisition for an operations maintenance shop
700,000
(Land Allocation - $700,000)
(xvii) Combined Readiness Center/Operations Maintenance Shop, Northampton County
(A) Land acquisition for a combined readiness center/operations maintenance shop
1,400,000
(Land Allocation - $1,400,000)
(xviii) Combined Readiness Center/Operations Maintenance Shop, Philadelphia County
(A) Land acquisition for a combined readiness center/operations maintenance shop
2,525,000
(Land Allocation - $2,525,000)
(xix) Pennsylvania National Guard Readiness Center
(A) Construction and land acquisition to replace the existing National Guard Armory, Hermitage, Pennsylvania
1,900,000
(Base Project Allocation - $1,300,000)
(Land Allocation - $300,000)
(Design and Contingencies - $300,000)
(xx) Western Maneuver Training Area
(A) To acquire three parcels of land, 5,300 acres more or less, to establish a tracked vehicle maneuver training area in western Pennsylvania for the Pennsylvania National Guard
8,000,000
(xxi) Greene County Armory
(A) Construction, renovation and site improvements to Armory
1,250,000
(xxii) East Stroudsburg Armory, Monroe County
(A) For design, construction and renovations to the East Stroudsburg Armory, Monroe County
1,100,000
(xxiii) Easton Armory in Northampton County
(A) Construction of a new facility in Northampton County and supporting facilities to include military and off-street parking, access roads and sidewalks
1,370,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $70,000)
(Design and Contingencies - $300,000)
(xxiv) Armory at Tioga County
(A) Construction of a new armory in Tioga County to replace existing armories at Mansfield and Wellsboro
1,363,000
(Base Project Allocation - $1,163,000)
(Design and Contingencies - $200,000)
(xxv) Armory in Venango County
(A) Construction of new armory in the Oil City area
5,000,000
(10) Pennsylvania Infrastructure Investment Authority
(i) Water supply and wastewater system
(A) Development and construction of water supply and wastewater systems
1,000,000,000
(Base Project Allocation - $997,000,000)
(Design and Contingencies - $3,000,000)
(11) Department of Public Welfare
(i) Byberry State Hospital
(A) For demolition of all structures and cleanup of hazardous waste and debris
20,000,000
(ii) Clarks Summit State Hospital
(A) Install enclosed fire escapes
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(iii) Danville State Hospital
(A) Demolish deteriorated structures
964,000
(Base Project Allocation - $877,000)
(Design and Contingencies - $87,000)
(iv) Harrisburg State Hospital
(A) Install ceilings in Petry No.17 and Eaton No.54 buildings
912,000
(Base Project Allocation - $760,000)
(Design and Contingencies - $152,000)
(B) Upgrade and renovate building No.25 and adjacent grounds to convert into office space with associated parking facilities
2,400,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $400,000)
(v) Mayview State Hospital, Allegheny County
(A) Demolish deteriorated structures
1,377,000
(Base Project Allocation - $1,252,000)
(Design and Contingencies - $125,000)
(vi) Norristown State Hospital
(A) Additional funds for DGS Project 509-29, boiler reconstruction/replacement
960,000
(Base Project Allocation - $800,000)
(Design and Contingencies - $160,000)
(B) Demolish deteriorated structures
1,528,000
(Base Project Allocation - $1,389,000)
(Design and Contingencies - $139,000)
(C) Reconstruction or replacement of boilers to meet emissions requirements and upgrade the steam distribution system
3,924,000
(Base Project Allocation - $3,270,000)
(Design and Contingencies - $654,000)
(vii) South Mountain Restoration Center
(A) Demolish deteriorated structures
638,000
(Base Project Allocation - $580,000)
(Design and Contingencies - $58,000)
(B) Renovation of campus water supply lines
2,160,000
(Base Project Allocation - $1,800,000)
(Design and Contingencies - $360,000)
(viii) Torrance State Hospital
(A) Demolish deteriorated structures
1,319,000
(Base Project Allocation - $1,199,000)
(Design and Contingencies - $120,000)
(ix) Wernersville State Hospital
(A) Demolish deteriorated structures
880,000
(Base Project Allocation - $800,000)
(Design and Contingencies - $80,000)
(x) Ebensburg Center
(A) Additional funds for project DGS 583-11, replacement of steam lines
720,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $120,000)
(xi) Embreeville Complex
(A) Upgrade roof on central building, HVAC, electrical distribution, steam, condensate, water supply and wastewater systems
1,500,000
(Base Project Allocation - $1,250,000)
(Design and Contingencies - $250,000)
(B) Installation of HVAC and central air conditioning equipment in the Hilltop Building
500,000
(xii) Hamburg Center
(A) Demolish deteriorated structures
563,000
(Base Project Allocation - $512,000)
(Design and Contingencies - $51,000)
(xiii) Polk Center
(A) Additional funds for DGS Project 552-29, upgrade electrical system
3,480,000
(Base Project Allocation - $2,900,000)
(Design and Contingencies - $580,000)
(B) Demolish deteriorated structures
787,000
(Base Project Allocation - $715,000)
(Design and Contingencies - $72,000)
(C) Rehabilitation of buildings at Polk State Center for alternative usage
5,000,000
(xiv) Selinsgrove Center
(A) Renovate potable water system
3,000,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $500,000)
(B) Renovation of large ward areas in Central Complex into smaller single-bed type living arrangements
5,000,000
(Base Project Allocation - $5,000,000)
(C) Installation of HVAC and windows at the training center (Building 9)
1,600,000
(Base Project Allocation - $1,600,000)
(D) Installation of new HVAC system and occupancy redesign in Buildings 10, 11 and 12
1,600,000
(Base Project Allocation - $1,600,000)
(E) Install new HVAC system throughout Central Complex
9,240,000
(Base Project Allocation - $9,240,000)
(F) Demolish deteriorated structures
197,000
(Base Project Allocation - $179,000)
(Design and Contingencies - $18,000)
(xv) Loysville Youth Development Center
(A) Construction of a water filtration system
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(xvi) Southwest Secure Treatment Center
(A) Additional funds for DGS Project 513-29, upgrade HVAC system
480,000
(Base Project Allocation - $400,000)
(Design and Contingencies - $80,000)
(12) State Police
(i) Trevose Station, Bucks County
(A) Demolition of existing structure and construction of new building on site
2,000,000
(ii) Washington Headquarters, Washington County
(A) Construction of new headquarters building
5,655,000
(Base Project Allocation - $4,823,000)
(Design and Contingencies - $832,000)
(iii) Greensburg Headquarters, Westmoreland County
(A) Construction of new headquarters building
5,220,000
(Base Project Allocation - $4,350,000)
(Design and Contingencies - $870,000)
(iv) Indiantown Gap Military Reservation
(A) Construction of a Pursuit Driving Training Facility
7,600,000
(Base Project Allocation - $6,592,000)
(Design and Contingencies - $1,008,000)
(v) Montgomery County
(A) Construction of a new Regional Dispatch Center
6,000,000
(Base Project Allocation - $5,500,000)
(Design and Contingencies - $500,000)
(vi) Westmoreland County
(A) Construction of a new Regional Dispatch Center
6,000,000
(Base Project Allocation - $5,500,000)
(Design and Contingencies - $500,000)
(vii) Northeast Region
(A) Land acquisition and construction of a new Regional Dispatch Center
7,000,000
(Base Project Allocation - $6,500,000)
(Design and Contingencies - $500,000)
(viii) Northwest Region
(A) Land acquisition and construction of a new Regional Dispatch Center
7,000,000
(Base Project Allocation - $6,500,000)
(Design and Contingencies - $500,000)
(13) State System of Higher Education
(i) Bloomsburg University
(A) Renovation of pedestrian/vehicle safety areas
3,260,000
(B) Addition to Hartline Science Center
9,892,000
(ii) California University
(A) Addition to and renovation of Steele Auditorium
8,066,000
(B) Renovation of Vulcan Art Complex
3,143,000
(C) Demolition of three residence halls
1,200,000
(D) Renovation of Old Main and South Hall
9,804,000
(E) Renovation of Noss Hall
4,601,000
(F) Replacement of Duda World Culture Building
6,131,000
(G) Pedestrian and vehicular enhancements, Phase I
4,592,000
(H) Construction of a new dormitory
10,000,000
(I) Installation of water backflows preventers, campuswide
497,000
(J) ((J) repealed June 22, 2004, P.L.257, No.40)
(K) Infrastructure improvements and loop road construction
5,000,000
(iii) Cheyney University
(A) Renovation and upgrade of sewage treatment facility
4,959,000
(B) ((B) repealed June 22, 2004, P.L.257, No.40)
(C) Renovation of Baily Hall
4,755,000
(D) Campus infrastructure rehabilitation, Phase II
2,916,000
(E) Campus security and fire alarm repairs
5,200,000
(F) Water system repairs
7,500,000
(G) Lighting and infrastructure repairs
4,000,000
(H) Environmental controls and safety repairs
3,850,000
(I) Adaptive building repairs
7,250,000
(J) Roof and architectural repairs
4,300,000
(iv) Clarion University
(A) Replacement of steam distribution system, Phase III
7,752,000
(B) Upgrade communications and electrical distribution system, Phase II
3,086,000
(C) Renovation of Stevens Hall and Special Education Annex
5,974,000
(D) Renovation of Becker Hall
9,300,000
(E) Replace steam lines, Phase IV
7,100,000
(F) Addition to and renovation of Carlson Library
17,060,000
(v) Dixon University Center
(A) Construct educational buildings
3,200,000
(vi) East Stroudsburg University
(A) Renovation and replacement of Koehler Field House and Natatorium
28,728,000
(B) Design and renovation of Lenape Residence Hall
10,000,000
(C) Design and construction of business accelerator
1,500,000
(D) Design and construction of a university parking facility
4,500,000
(E) Design and renovation of Monroe Residence Hall
5,000,000
(F) Design and renovation of Shawnee Residence Hall
5,000,000
(G) Design and renovation of Minsi Residence Hall
5,000,000
(H) Design and construction of university athletic complex/stadium
75,000,000
(I) Design and renovation of Stroud Hall
2,750,000
(J) Design and renovation of Dansbury Commons
1,000,000
(vii) Edinboro University
(A) Construct an Institute for Human Services
5,000,000
(Base Project Allocation - $4,167,000)
(Design and Contingencies - $833,000)
(B) Renovation/replacement of Heather Hall
2,267,000
(C) Upgrade of infrastructure, Phase II
3,950,000
(D) Renovation of Academy Hall
1,100,000
(Base Project Allocation - $1,100,000)
(E) Renovation of Butterfield Hall
4,936,000
(viii) Indiana University
(A) Renovation and/or reconstruction of Cogswell Hall, Phase II
13,000,000
(B) Renovation of Davis Hall
13,074,000
(C) Renovation of Keith Hall
10,729,000
(D) Renovation of Leonard Hall
8,336,000
(E) Renovation of Weyandt Hall
30,659,000
(F) Renovation of Stabley Library
8,291,000
(G) Renovation of Walsh Hall
3,344,000
(H) Renovation of Memorial Field House
16,040,000
(I) Addition to and renovation of Sprowls Hall
21,655,000
(J) Renovation of Sutton Hall, Phase II
23,280,000
(K) Renovation of Pratt Hall
5,738,000
(L) Addition to Stapleton Library
9,100,000
(ix) Kutztown University
(A) Renovation and conversion of Risley Hall
5,846,000
(B) Upgrade of maintenance building and demolition and relocation of garage/heat plant
2,391,000
(C) Addition to and renovation of science buildings
18,662,000
(D) Renovation and upgrade of boiler plant
2,857,000
(E) Construction of advanced high-technology classroom
4,404,000
(F) Renewal and addition to Sharadin Arts Building
11,778,000
(G) ((G) repealed June 22, 2004, P.L.257, No.40)
(H) Replacement of coal-fired heat plant
12,000,000
(x) Lock Haven University
(A) Restoration of Lusk Run Conduit
1,440,000
(B) Upgrade of fiber optic infrastructure
3,720,000
(C) Renovation of Zimmerli Gym
15,930,000
(D) Addition to Jack Stadium, Phase IV
2,136,000
(E) Renovation of South Ulmer Science Building
8,566,000
(F) Construction of new academic facility on campus to provide additional technology equipped classrooms and administrative space
10,500,000
(G) Construction of student study/learning center at the Clearfield Campus
5,000,000
(H) Construction of indoor athletic facility
8,000,000
(I) Second phase development for the Clearfield Campus
5,000,000
(J) Construction of a Technology Center/Dormitory at Clearfield Campus
8,000,000
(xi) Mansfield University
(A) ((A) repealed June 22, 2004, P.L. 257 No.40)
(B) Renovation/replacement of South Hall
5,257,000
(C) Addition to and renovation of Grant Science
9,959,000
(D) Addition to and renovation of Home Economics Center
6,672,000
(xii) Millersville University
(A) Renovation of Wickersham Hall
2,863,000
(B) Upgrade of electrical utilities
7,128,000
(C) Renovation of education instruction building
9,631,000
(D) Renovation of Ganser Library
15,896,000
(E) Addition to and renovation of McComsey Hall
7,657,000
(xiii) Shippensburg University
(A) Addition to and renovation of Lehman Library
21,730,000
(B) Renovation of Huber Arts Center
4,960,000
(C) Construction of instructional arts facility
19,853,000
(D) Reconstruction of roadways, sidewalks and parking facilities
4,618,000
(E) Renovation of Horton Hall
7,571,000
(F) Renovation of Gilbert and Stewart Halls
5,185,000
(G) Upgrade steam plant boiler No.4
563,000
(xiv) Slippery Rock University
(A) Renovation of Vincent Science Building
20,803,000
(B) Construction of North Hills Education Alliance Facility
8,322,000
(C) Renovation of steam distribution, Phase II
7,680,000
(D) Renovation of Morrow Field House
13,800,000
(E) Reconstruction of roadways and parking lots
1,530,000
(xv) West Chester University
(A) Construct Business and Information Technology Center
22,000,000
(B) Renovation of Lawrence Hall
6,387,000
(C) Demolition of Ramsey Hall
708,000
(D) Relocate and widen Tigue Road
5,880,000
(E) Construction of Applied and Integrated Health Sciences Building
42,768,000
(F) Infrastructure renovations and code updates, Phase I
18,000,000
(G) Renovation of Francis Harvey Green Office/Classroom Building
7,800,000
(H) Increase capacity and upgrade boiler plant
5,156,000
(Base Project Allocation - $5,156,000)
(I) Electric utilities upgrade
5,048,000
(Base Project Allocation - $5,048,000)
(J) Construct new access road and improve surface
900,000
(Base Project Allocation - $900,000)
(K) Renovation of Schmucker Science Building, Phase III
15,842,000
(14) Department of Transportation
(i) Road signage
(A) Purchase and erection of highway signs in the surrounding and adjacent counties to promote the Allegheny National Forest and Kinzua Reservoir
500,000
(ii) Adams County
(A) Additional funds for DGS Project 657-6 to construct a new welcome center
540,000
(Base Project Allocation - $450,000)
(Design and Contingencies - $90,000)
(iii) Blair County
(A) For design and acquisition of both right-of-way and properties within the Ninth Avenue Corridor in the City of Altoona
900,000
(iv) Bucks County
(A) Construction of a County Maintenance Facility
6,600,000
(Base Project Allocation - $5,500,000)
(Design and Contingencies - $1,100,000)
(v) Dauphin County
(A) Renovations to the Harrisburg Engineering District 8-0 facility
2,000,000
(B) Construction of PennDOT Server Farm
6,326,000
(Base Project Allocation - $5,350,000)
(Design and Contingencies - 976,000)
(vi) Erie County Welcome Center
(A) Additional funds to construct a new welcome center
3,423,000
(Base Project Allocation - $2,759,000)
(Land Allocation - $120,000)
(Design and Contingencies - $544,000)
(vii) Luzerne County
(A) Construction of a County Maintenance Facility
6,600,000
(Base Project Allocation - $5,500,000)
(Design and Contingencies - $1,100,000)
(viii) McKean County
(A) Construction of new welcome center
350,000
(ix) Montour County
(A) Construction of a satellite maintenance building
1,200,000
(B) Additional funds for DGS Project 251-35, construction of transportation maintenance shed
500,000
(x) Philadelphia, Delaware and Bucks Counties
(A) Dredging of the channel of the Delaware River from 40 to 45 feet
15,000,000
(xi) Pike County
(A) Construction of a County Maintenance Facility
4,200,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $700,000)
(xii) Susquehanna County
(A) Additional funds for DGS Project 657-13 to construct welcome center in Great Bend Township
1,320,000
(Base Project Allocation - $1,100,000)
(Design and Contingencies - $220,000)
(xiii) Warren County
(A) Construction of new welcome center
350,000
(xiv) Washington County
(A) Construction of a County Maintenance Facility on PennDOT-owned property
7,200,000
(Base Project Allocation - $6,000,000)
(Design and Contingencies - $1,200,000)
(B) Preconstruction and construction of projects I and II of a shuttle system utilizing passive levitation technology with an air gap of greater than one inch. Funds would be used to match Federal funds.
15,000,000
(xv) Westmoreland County
(A) Construction of a County Maintenance Facility
7,800,000
(Base Project Allocation - $6,500,000)
(Design and Contingencies - $1,300,000)
(B) Construction of a County Maintenance Facility at Ligonier
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(xvi) Philadelphia Regional Port Authority
(A) Tioga Marine Terminal
(I) General improvements, including refrigerated capacity expansion, electrical upgrade, paving and overlay work, roofing improvements and improvements to the Tioga Administration Building
14,850,000
(II) For warehouse expansion - construction of an additional 100,000 square feet of refrigerated storage space and an additional 100,000 square feet of dry cargo covered space
13,150,000
(III) Capital Dredge Tioga Terminal RO-RO Berth
750,000
(Base Project Allocation - $750,000)
(IV) Demolition of Pier 179, Tioga Terminal
3,000,000
(Base Project Allocation - $3,000,000)
(B) Piers 38 and 40 South
(I) General improvements, including rail improvements, new roofs, window panels, door closures, sprinkler system replacement, paint removal and pier infrastructure reinforcement
5,850,000
(C) Piers 78, 78A, 80, 80A
(I) Demolish existing warehouses on Piers 78 and 80, enhance Pier 80 Annex Warehouse, construct two new warehouses totaling 1,000,000 sq. ft. and construct marginal berth
88,100,000
(D) Pier 82 South
(I) General improvements, including expansion of refrigerated capacity and infrastructure improvements
2,000,000
(E) Pier 84 South
(I) Construct new storage warehouse and provide for general improvements to existing facility
14,000,000
(II) Construction of at least a 160,300-foot square foot warehouse extension, railroad realignment, silo construction and related improvements to Pier 84 South on the Delaware River for the handling and storage of cocoa beans
12,000,000
(F) Pier 96 South, Pier 98A South
(I) General improvements, including demolition, site clearance, paving drainage, electrical upgrade and berth fender replacement. Land acquisition to accommodate site expansion.
14,000,000
(G) Packer Avenue Marine Terminal
(I) General improvements, including repaving and container crane enhancements. Also, acquisition of one Post Panamax Container Crane, expansion of chiller/freezer warehouse. Construction of a new gate complex, construction of new marginal bulkhead from Pier 90 South to Packer Avenue. Project includes all filling behind bulkhead, demolition, paving and land acquisition.
159,900,000
(H) Dredging
(I) Dredging of slips and berths, owned by the Philadelphia Regional Port Authority, over a 10-year period
11,000,000
(II) Rail spur to Fort Mifflin dredge disposal cells
3,000,000
(Base Project Allocation - $3,000,000)
(I) Land acquisition
(I) Land acquisition at a number of sites for expansion, improvement and development of Port facilities
35,000,000
(J) Acquisition of two container cranes
15,000,000
(K) PRPA Port fire prevention and safety improvements at various port facilities
6,000,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $1,000,000)
Compiler's Note: The Department of Public Welfare, referred to in this section, was redesignated as the Department of Human Services by Act 132 of 2014.