Section 68. Westmoreland County
(a) PA 56
(1) Seventh Street North to TR 780, Intersection Improvement and Signal Update
250,000
(Base Project Allocation - $217,000)
(Land Allocation - $13,000)
(Design and Contingencies - $20,000)
(b) I-70
(1) Washington County to Pennsylvania Turnpike, Pavement and Bridge Rehabilitation and Safety Improvements
858,000
(Base Project Allocation - $780,000)
(Design and Contingencies - $78,000)
(2) Smithton Interchange with I-70 with SR 3031, Interchange Improvements and Lengthening of the Acceleration and Deceleration Lanes
750,000
(Base Project Allocation - $610,000)
(Land Allocation - $100,000)
(Design and Contingencies - $40,000)
(c) US 22
(1) Pennsylvania Turnpike to Export, Reconstruction and Widening to Four Lanes with Turning Lanes and Safety Improvements
4,540,000
(Base Project Allocation - $3,060,000)
(Land Allocation - $1,200,000)
(Design and Contingencies - $280,000)
(2) Export to Delmont, Reconstruction and Widening to Four Lanes with Turning Lanes and Safety Improvements
4,450,000
(Base Project Allocation - $3,330,000)
(Land Allocation - $800,000)
(Design and Contingencies - $320,000)
(d) US 119
(1) Youngwood to SR 3099, Safety Improvements
340,000
(Base Project Allocation - $320,000)
(Land Allocation - $10,000)
(Design and Contingencies - $10,000)
(e) Center Avenue
(1) Center Avenue, New Stanton Borough, Two Lane Relocation
850,000
(Base Project Allocation - $700,000)
(Land Allocation - $50,000)
(Design and Contingencies - $100,000)
(f) PA 66
(1) Intersection with US 22 to Intersection with PA 356 and PA 28, Construct Four-Lane Limited Access Highway
400,000,000
(Base Project Allocation - $320,000,000)
(Land Allocation - $30,000,000)
(Design and Contingencies - $50,000,000)
(g) PA 28
(1) Allegheny Valley Connector, New Kensington to PA 28, Construction of New Connector
32,250,000
(Base Project Allocation - $30,000,000)
(Land Allocation - $1,500,000)
(Design and Contingencies - $750,000)
(h) SR 3031
(1) Smithton Interchange to Paint Kosor Road, Replace Base, Widen, Resurface, Replace Box Culvert, Improve Drainage and Guide Rail, Length of One Mile
2,000,000
(Base Project Allocation - $2,000,000)
(i) SR 4026
(1) Reconstruct, Widen and Resurface Mellon Road from US 22 to County Road in Penn Township
500,000
(Base Project Allocation - $450,000)
(Land Allocation - $10,000)
(Design and Contingencies - $40,000)
(j) Finley Road
(1) SR 0201 to the Norfolk and Western Railway Crossing, the Terminus of SR 3011, Pavement Rehabilitation and Safety Improvements, Bridge Widening
1,280,000
(Base Project Allocation - $963,000)
(Design and Contingencies - $317,000)
(k) Westmoreland County Airport
(1) ((1) repealed Oct. 10, 1997, P.L.392, No.47)