Lehigh County

Act 143 of 1992, § 43, under HIGHWAY-RAILROAD AND HIGHWAY BRIDGE CAPITAL BUDGET SUPPLEMENTAL ACT FOR 1991-1992 - ENACTMENT.

Act 143 of 1992, § 43

Section 43. Lehigh County.

(a) Local Bridges

(1) Washington Township, T-787, West Gant Street over Trout Creek, Bridge Replacement

175,000

(Base Construction Allocation - $135,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(2) Lowhill Township, T-649, Narris Road Bridge No.1 over Switzer Creek, Bridge Replacement

145,000

(Base Construction Allocation - $110,000)

(Land Allocation - $10,000)

(Design and Contingencies - $25,000)

(3) Whitehall Township, Peach Bottom Road over Spring Creek, Bridge Replacement

190,000

(Base Construction Allocation - $135,000)

(Land Allocation - $25,000)

(Design and Contingencies - $30,000)

(4) Whitehall Township, Eggert Road over Spring Creek, Bridge Replacement

235,000

(Base Construction Allocation - $180,000)

(Land Allocation - $25,000)

(Design and Contingencies - $30,000)

(5) Whitehall Township, Overlook Lane over Spring Creek, Bridge Replacement

215,000

(Base Construction Allocation - $160,000)

(Land Allocation - $25,000)

(Design and Contingencies - $30,000)

(6) Whitehall Township, Columbia Street over Coplay Creek, Bridge Replacement

385,000

(Base Construction Allocation - $250,000)

(Land Allocation - $100,000)

(Design and Contingencies - $35,000)

(7) Lowhill Township, T-649, Narris Road Bridge No.2 over Switzer Creek, Bridge Replacement

170,000

(Base Construction Allocation - $130,000)

(Land Allocation - $10,000)

(Design and Contingencies - $30,000)

(8) Macungie Borough, Hickory Lane over Tributary of Swabia Creek, Bridge Replacement

160,000

(Base Construction Allocation - $110,000)

(Land Allocation - $25,000)

(Design and Contingencies - $25,000)

(9) City of Allentown, Union Boulevard over Lehigh River, Bridge Replacement

5,520,000

(Base Construction Allocation - $5,000,000)

(Land Allocation - $20,000)

(Design and Contingencies - $500,000)

(10) City of Allentown, Reading Road over Cedar Creek, Bridge Replacement

1,010,000

(Base Construction Allocation - $865,000)

(Land Allocation - $20,000)

(Design and Contingencies - $125,000)

(11) City of Allentown, Ward Street (15th Street) over Little Lehigh Creek, Bridge Replacement

3,800,000

(Base Construction Allocation - $3,400,000)

(Land Allocation - $20,000)

(Design and Contingencies - $380,000)

(12) City of Allentown, 15th Street Bridge over Conrail and Little Lehigh Creek, Bridge Rehabilitation

750,000

(Base Construction Allocation - $500,000)

(Land Allocation - $100,000

(Design and Contingencies - $150,000)

(13) North Whitehall Township, T-687, Lehigh Street Bridge, Bridge Replacement

150,000

(Base Construction Allocation - $135,000)

(Design and Contingencies - $15,000)

(14) North Whitehall Township, T-695, Walnut Street Bridge No.1, Bridge Rehabilitation

83,000

(Base Construction Allocation - $65,000)

(Design and Contingencies - $18,000)

(15) North Whitehall Township, T-695, Walnut Street Bridge No.2, Bridge Rehabilitation

105,000

(Base Construction Allocation - $85,000)

(Design and Contingencies - $20,000)

(16) North Whitehall Township, T-712, Bridge at Overlook Road and Neffs-Laurys Road, Bridge Replacement

141,000

(Base Construction Allocation - $120,000)

(Design and Contingencies - $21,000)

(17) North Whitehall Township, T-702, Bridge at Riverview Road and Neffs-Laurys Road, Bridge Replacement

118,000

(Base Construction Allocation - $100,000)

(Design and Contingencies - $18,000)

(18) North Whitehall Township, T-665, Excelsior Road Bridge over Coplay Creek, Bridge Replacement

173,000

(Base Construction Allocation - $153,000)

(Design and Contingencies - $20,000)

(19) North Whitehall Township, T-691, Wood Street Bridge over Coplay Creek, Bridge Replacement

173,000

(Base Construction Allocation - $153,000)

(Design and Contingencies - $20,000)

(20) North Whitehall Township, T-674C, Coplay Creek Road Bridge over Coplay Creek, Bridge Replacement

185,000

(Base Construction Allocation - $163,000)

(Design and Contingencies - $22,000)

(21) Heidelberg Township, T-778, Hunters Hill Road Bridge, Bridge Replacement

137,000

(Base Construction Allocation - $125,000)

(Design and Contingencies - $12,000)

(b) State Bridges

(1) S.R.0145 over Abandoned Conrail Line, Whitehall Township, Bridge Replacement

240,000

(Base Construction Allocation - $200,000)

(Land Allocation - $20,000)

(Design and Contingencies - $20,000)

(2) S.R.3001 over Iron Run, Lower Macungie Township, Bridge Replacement

624,000

(Base Construction Allocation - $480,000)

(Land Allocation - $96,000)

(Design and Contingencies - $48,000)

(3) I-78 over Iron Run, Weisenberg Township, Bridge Replacement

120,000

(Base Construction Allocation - $100,000)

(Design and Contingencies - $20,000)

(4) S.R.0378 under Easton Avenue, City of Bethlehem, Bridge Replacement

812,000

(Base Construction Allocation - $738,000)

(Design and Contingencies - $74,000)

(5) S.R.0145 over Tributary of Coplay Creek, Whitehall Township, Bridge Replacement

225,000

(Base Construction Allocation - $187,000)

(Land Allocation - $19,000)

(Design and Contingencies - $19,000)

(6) S.R.0378 under Catasaqua Road, City of Bethlehem, Bridge Replacement

742,000

(Base Construction Allocation - $674,000)

(Design and Contingencies - $68,000)

(7) S.R.1015 over S.R.0022, Whitehall Township, Bridge Replacement

569,000

(Base Construction Allocation - $517,000)

(Design and Contingencies - $52,000)

(8) S.R.2032 over Spring Creek, Upper Saucon Township, Bridge Replacement

140,000

(Base Construction Allocation - $100,000)

(Land Allocation - $20,000)

(Design and Contingencies - $20,000)

(9) S.R.0145 over Jordan Creek, City of Allentown, Bridge Replacement

2,660,000

(Base Construction Allocation - $2,000,000)

(Land Allocation - $460,000)

(Design and Contingencies - $200,000)

(10) S.R.2055, Alburtis Meyers Bridge over Harrison St., Lawrence St., Little Lehigh Creek and Railroad, City of Allentown, Bridge Replacement

2,200,000

(Base Construction Allocation - $2,000,000)

(Design and Contingencies - $200,000)

(11) S.R.2030, Centennial Bridge over Saucon Creek, Upper Saucon Township, Bridge Replacement

950,000

(Base Construction Allocation - $830,000)

(Land Allocation - $25,000)

(Design and Contingencies - $95,000)

(12) Tilghman Street Bridge over Lehigh River, City of Allentown, Bridge Rehabilitation

4,100,000

(Base Construction Allocation - $3,550,000)

(Land Allocation - $100,000)

(Design and Contingencies - $450,000)

(13) S.R.0022, Bridge over Lehigh River, Whitehall Township, Bridge Rehabilitation

1,250,000

(Base Construction Allocation - $1,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $200,000)

(14) S.R.0022, Bridge over Lehigh Canal, Hanover Township, Bridge Rehabilitation

1,250,000

(Base Construction Allocation - $1,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $200,000)

(15) S.R.2055, 8th Street Bridge over Little Lehigh Creek, City of Allentown, Bridge Rehabilitation

1,250,000

(Base Construction Allocation - $1,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $200,000)