Section 35. Huntingdon County.

(a) Local Bridges (Reserved)

(b) State Bridges

(1) SR 0022, Bridge over Quarry Haul Road, Brady Township, Bridge Replacement

1,675,000

(Base Construction Allocation - $1,400,000)

(Land Allocation - $25,000)

(Design and Contingencies - $250,000)

(2) SR 0026, Bridge over Little Juniata River, Huntingdon Borough, Bridge Rehabilitation

2,400,000

(Base Construction Allocation - $2,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $350,000)

(3) SR 0035, Bridge over Trough Spring, Tell Township, Bridge Replacement

575,000

(Base Construction Allocation - $425,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(4) SR 0350, Bridge over Warriors Mark Run, Warriors Mark Township, Bridge Replacement

550,000

(Base Construction Allocation - $375,000)

(Land Allocation - $50,000)

(Design and Contingencies - $125,000)

(5) SR 0550, Bridge over Logan Spring Run, Warriors Mark Township, Bridge Replacement

625,000

(Base Construction Allocation - $450,000)

(Land Allocation - $25,000)

(Design and Contingencies - $150,000)

(6) SR 0641, Bridge over Tributary of Tannery Run, Dublin Township, Bridge Replacement

525,000

(Base Construction Allocation - $375,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(7) SR 0641, Bridge over Branch of Shade Creek, Dublin Township, Bridge Replacement

500,000

(Base Construction Allocation - $350,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(8) SR 0655, Bridge over North Spring Creek, Saltillo Borough, Bridge Replacement

700,000

(Base Construction Allocation - $475,000)

(Land Allocation - $75,000)

(Design and Contingencies - $150,000)

(9) SR 0655, Bridge over Mill Creek, Brady Township, Bridge Replacement

550,000

(Base Construction Allocation - $375,000)

(Land Allocation - $50,000)

(Design and Contingencies - $125,000)

(10) SR 0913, Bridge over Shoups Run, Carbon Township, Bridge Replacement

525,000

(Base Construction Allocation - $375,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(11) SR 0994, Bridge over Sugar Creek, Todd Township, Bridge Replacement

550,000

(Base Construction Allocation - $400,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(12) SR 0994, Bridge over Jordans Creek, Rockhill Borough, Bridge Replacement

575,000

(Base Construction Allocation - $375,000)

(Land Allocation - $75,000)

(Design and Contingencies - $125,000)

(13) SR 2012, Bridge over Licking Creek, Shirley Township, Bridge Replacement

500,000

(Base Construction Allocation - $350,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(14) SR 2019, Bridge over Fort Run, Shirley Township, Bridge Replacement

475,000

(Base Construction Allocation - $325,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(15) SR 3027, Bridge over Little Trough Creek, Cass Township, Bridge Rehabilitation

650,000

(Base Construction Allocation - $500,000)

(Land Allocation - $25,000)

(Design and Contingencies - $125,000)

(16) SR 0913, Bridge in Coalmont Borough, Bridge Replacement

575,000

(Base Construction Allocation - $375,000)

(Land Allocation - $75,000)

(Design and Contingencies - $125,000)

(17) SR 1019, Bridge over Standing Stone Creek, Miller Township, Bridge Replacement

1,074,000

(Base Construction Allocation - $861,000)

(Land Allocation - $35,000)

(Design and Contingencies - $178,000)

(18) SR 2009, Bridge over Tuscarora Creek, Tell Township, Bridge Replacement

710,000

(Base Construction Allocation - $556,000)

(Land Allocation - $25,000)

(Design and Contingencies - $129,000)

(19) SR 4009, Bridge over Shavers Creek, Logan Township, Bridge Replacement

1,084,000

(Base Construction Allocation - $874,000)

(Land Allocation - $30,000)

(Design and Contingencies - $180,000)

(20) SR 4031, Bridge over Fair Brook Creek, Franklin Township, Bridge Replacement

550,000

(Base Construction Allocation - $405,000)

(Land Allocation - $35,000)

(Design and Contingencies - $110,000)

(21) SR 3003, Weavers Falls Bridge over Raystown Lake, Bridge Replacement

1,425,000

(Base Construction Allocation - $1,050,000)

(Land Allocation - $75,000)

(Design and Contingencies - $300,000)

(22) SR 0022, Bridge over Frankstown Branch of Juniata River, Bridge Replacement

950,000

(Base Construction Allocation - $700,000)

(Land Allocation - $50,000)

(Design and Contingencies - $200,000)