Section 60. Somerset County.
(a) Local Bridges
(1) Allegheny Township, New Baltimore Covered Bridge over Raystown Bridge, Juniata River, Bridge Rehabilitation
685,000
(Base Construction Allocation - $600,000)
(Land Allocation - $10,000)
(Design and Contingencies - $75,000)
(2) Lower Turkeyfoot Township, T-313, Anglers Bridge over Harbaugh Run, Bridge Replacement
310,000
(Base Construction Allocation - $250,000)
(Land Allocation - $10,000)
(Design and Contingencies - $50,000)
(3) Ogle Township, T-835, Two Mile Run Bridge over Roaring Fork Creek, Bridge Replacement
370,000
(Base Construction Allocation - $300,000)
(Land Allocation - $10,000)
(Design and Contingencies - $60,000)
(4) Stonycreek Township, Glessner Covered Bridge over Stony Creek, Bridge Rehabilitation
685,000
(Base Construction Allocation - $600,000)
(Land Allocation - $10,000)
(Design and Contingencies - $75,000)
(b) State Bridges
(1) SR 0219, Northbound Bridge over Pennsylvania Turnpike, Somerset Township, Bridge Rehabilitation - Painting
135,000
(Base Construction Allocation - $110,000)
(Design and Contingencies - $25,000)
(2) SR 0219, Southbound Bridge over Pennsylvania Turnpike, Somerset Township, Bridge Rehabilitation - Painting
135,000
(Base Construction Allocation - $110,000)
(Design and Contingencies - $25,000)
(3) SR 0601, Bridge over Quemahoning Creek, Boswell Borough, Bridge Replacement
1,225,000
(Base Construction Allocation - $961,000)
(Land Allocation - $50,000)
(Design and Contingencies - $214,000)
(4) SR 0281, Bridge over Laurel Hill Creek, Confluence Borough, Bridge Replacement
1,500,000
(Base Construction Allocation - $1,261,000)
(Land Allocation - $50,000)
(Design and Contingencies - $189,000)
(5) SR 3025, Bridge over Tributary of Coxes Creek, Somerset Borough, Bridge Replacement
455,000
(Base Construction Allocation - $327,000)
(Land Allocation - $25,000)
(Design and Contingencies - $103,000)
(6) SR 0281, Bridge over TR 30, Stoystown Borough, Bridge Replacement
990,000
(Base Construction Allocation - $756,000)
(Land Allocation - $100,000)
(Design and Contingencies - $134,000)
(7) SR 3047, Bridge over Laurel Hill Creek, Ursina Borough, Bridge Replacement
1,385,000
(Base Construction Allocation - $1,148,000)
(Land Allocation - $25,000)
(Design and Contingencies - $212,000)
(8) SR 1015, Bridge over Hillegas Run, Allegheny Township, Bridge Replacement
520,000
(Base Construction Allocation - $380,000)
(Land Allocation - $25,000)
(Design and Contingencies - $115,000)
(9) SR 3010, Bridge over Millers Run, Brothersvalley Township, Bridge Replacement
565,000
(Base Construction Allocation - $417,000)
(Land Allocation - $25,000)
(Design and Contingencies - $123,000)
(10) SR 2018, Bridge over Buffalo Creek, Brothersvalley Township, Bridge Replacement
725,000
(Base Construction Allocation - $558,000)
(Land Allocation - $25,000)
(Design and Contingencies - $142,000)
(11) SR 2027, Bridge over Buffalo Creek, Brothersvalley Township, Bridge Replacement
760,000
(Base Construction Allocation - $566,000)
(Land Allocation - $50,000)
(Design and Contingencies - $144,000)
(12) SR 4041, Bridge over Tributary of Stony Creek, Conemaugh Township, Bridge Replacement
615,000
(Base Construction Allocation - $397,000)
(Land Allocation - $100,000)
(Design and Contingencies - $118,000)
(13) SR 0985, Bridge over Tributary of Bens Creek, Conemaugh Township, Bridge Replacement
535,000
(Base Construction Allocation - $328,000)
(Land Allocation - $100,000)
(Design and Contingencies - $107,000)
(14) SR 0985, Bridge over Mill Creek, Conemaugh Township, Bridge Replacement
510,000
(Base Construction Allocation - $328,000)
(Land Allocation - $75,000)
(Design and Contingencies - $107,000)
(15) SR 2014, Bridge over Casselman River, Elk Lick Township, Bridge Replacement
925,000
(Base Construction Allocation - $746,000)
(Land Allocation - $25,000)
(Design and Contingencies - $154,000)
(16) SR 4001, Bridge over Kooser Run, Jefferson Township, Bridge Replacement
540,000
(Base Construction Allocation - $356,000)
(Land Allocation - $75,000)
(Design and Contingencies - $109,000)
(17) SR 0031, Bridge over Tributary of Laurel Hill Creek, Jefferson Township, Bridge Replacement
565,000
(Base Construction Allocation - $395,000)
(Land Allocation - $50,000)
(Design and Contingencies - $120,000)
(18) SR 4013, Bridge over Beaverdam Run, Jenner Township, Bridge Replacement
475,000
(Base Construction Allocation - $341,000)
(Land Allocation - $25,000)
(Design and Contingencies - $109,000)
(19) SR 0601, Bridge over Roaring Run, Jenner Township, Bridge Replacement
930,000
(Base Construction Allocation - $690,000)
(Land Allocation - $75,000)
(Design and Contingencies - $165,000)
(20) SR 0601, Bridge over Pine Run, Jenner Township, Bridge Replacement
420,000
(Base Construction Allocation - $277,000)
(Land Allocation - $50,000)
(Design and Contingencies - $93,000)
(21) SR 3003, Bridge over Drake Run, Lower Turkeyfoot Township, Bridge Replacement
530,000
(Base Construction Allocation - $389,000)
(Land Allocation - $25,000)
(Design and Contingencies - $116,000)
(22) SR 3003, Bridge over Tributary of Drake Run, Lower Turkeyfoot Township, Bridge Replacement
485,000
(Base Construction Allocation - $351,000)
(Land Allocation - $25,000)
(Design and Contingencies - $109,000)
(23) SR 3007, Bridge over Paddy Run Creek, Lower Turkeyfoot Township, Bridge Replacement
510,000
(Base Construction Allocation - $351,000)
(Land Allocation - $50,000)
(Design and Contingencies - $109,000)
(24) SR 3039, Bridge over Laurel Hill Creek, Middlecreek Township, Bridge Replacement
780,000
(Base Construction Allocation - $583,000)
(Land Allocation - $50,000)
(Design and Contingencies - $147,000)
(25) SR 3033, Bridge over Lost Creek, Middlecreek Township, Bridge Replacement
440,000
(Base Construction Allocation - $312,000)
(Land Allocation - $25,000)
(Design and Contingencies - $103,000)
(26) SR 3019, Bridge over South Glades Run, Milford Township, Bridge Replacement
455,000
(Base Construction Allocation - $324,000)
(Land Allocation - $25,000)
(Design and Contingencies - $106,000)
(27) SR 0281, Bridge over Middle Creek, Milford Township, Bridge Replacement
855,000
(Base Construction Allocation - $670,000)
(Land Allocation - $25,000)
(Design and Contingencies - $160,000)
(28) SR 2015, Bridge over Wills Creek, Northampton Township, Bridge Replacement
785,000
(Base Construction Allocation - $591,000)
(Land Allocation - $50,000)
(Design and Contingencies - $144,000)
(29) SR 1037, Bridge over Biscuit Spring Run, Ogle Township, Bridge Replacement
510,000
(Base Construction Allocation - $351,000)
(Land Allocation - $50,000)
(Design and Contingencies - $109,000)
(30) SR 0601, Bridge over Shade Creek, Paint Township, Bridge Replacement
1,145,000
(Base Construction Allocation - $874,000)
(Land Allocation - $75,000)
(Design and Contingencies - $196,000)
(31) SR 1012, Bridge over Pokey Run, Shade Township, Bridge Replacement
600,000
(Base Construction Allocation - $445,000)
(Land Allocation - $25,000)
(Design and Contingencies - $130,000)
(32) SR 0403, Bridge over Pokeytown Run, Shade Township, Bridge Replacement
420,000
(Base Construction Allocation - $297,000)
(Land Allocation - $25,000)
(Design and Contingencies - $98,000)
(33) SR 1003, Bridge over Wells Creek, Somerset Township, Bridge Replacement
575,000
(Base Construction Allocation - $427,000)
(Land Allocation - $25,000)
(Design and Contingencies - $123,000)
(34) SR 1007, Bridge over Stony Creek, Stonycreek Township, Bridge Replacement
805,000
(Base Construction Allocation - $625,000)
(Land Allocation - $25,000)
(Design and Contingencies - $155,000)
(35) SR 1007, Bridge over Glade Run, Stonycreek Township, Bridge Replacement
795,000
(Base Construction Allocation - $596,000)
(Land Allocation - $50,000)
(Design and Contingencies - $149,000)
(36) SR 0219, Bridge over Bluelick Creek, Summit Township, Bridge Replacement
660,000
(Base Construction Allocation - $498,000)
(Land Allocation - $25,000)
(Design and Contingencies - $137,000)
(37) SR 2004, Bridge over Elk Lick Creek, Summit Township, Bridge Replacement
1,110,000
(Base Construction Allocation - $865,000)
(Land Allocation - $50,000)
(Design and Contingencies - $195,000)
(38) SR 2037, Bridge over Bigby Run, Summit Township, Bridge Replacement
500,000
(Base Construction Allocation - $363,000)
(Land Allocation - $25,000)
(Design and Contingencies - $112,000)
(39) TR 219, Bridge over SR 8001, Somerset Township, Bridge Rehabilitation
5,245,000
(Base Construction Allocation - $4,500,000)
(Land Allocation - $25,000)
(Design and Contingencies - $715,000)
(40) SR 0985, Bridge over Roaring Run, Jenner Township, Bridge Replacement
565,000
(Base Construction Allocation - $427,000)
(Land Allocation - $25,000)
(Design and Contingencies - $113,000)
(41) SR 0985, Bridge over North Fork of Ben's Run, Conemaugh Township, Bridge Replacement
798,000
(Base Construction Allocation - $623,000)
(Land Allocation - $35,000)
(Design and Contingencies - $140,000)
(42) SR 1002, Bridge over Wells Creek, Somerset Township, Bridge Replacement
841,000
(Base Construction Allocation - $665,000)
(Land Allocation - $30,000)
(Design and Contingencies - $146,000)
(43) SR 2010, Bridge over Big Piney Run, Greenville Township, Bridge Replacement
787,000
(Base Construction Allocation - $622,000)
(Land Allocation - $25,000)
(Design and Contingencies - $140,000)
(44) SR 4022, Bridge over Stoney Creek River, Conemaugh Township, Bridge Replacement
1,317,000
(Base Construction Allocation - $1,092,000)
(Land Allocation - $25,000)
(Design and Contingencies - $200,000)
(45) SR 0653, Bridge over South Glade Run, Milford Township, Bridge Replacement
620,000
(Base Construction Allocation - $474,000)
(Land Allocation - $30,000)
(Design and Contingencies - $116,000)
(46) SR 0669, Bridge over Tub Mill Run, Elk Lick Township, Bridge Replacement
920,000
(Base Construction Allocation - $732,000)
(Land Allocation - $30,000)
(Design and Contingencies - $158,000)