Section 306. Berks County.
(a) SR 61
(1) Reconstruction, Safety Improvements and Relocation of Mountain Road, SR 61 in Vicinity of I-78 and Associated Intersections in the Hamburg Area, Tilden Township
4,000,000
(Base Project Allocation - $3,000,000)
(Land Allocation - $500,000)
(Design and Contingencies - $500,000)
(b) SR 78
(1) Upgrade and Reconfiguration of Interchange, I-78 Lenhartsville Interchange, Greenwich Township
3,100,000
(Base Project Allocation - $2,600,000)
(Land Allocation - $200,000)
(Design and Contingencies - $300,000)
(c) SR 100
(1) Median Barrier and Safety Improvements, SR 100 Median Barrier, Colebrookdale Township
1,000,000
(Base Project Allocation - $1,000,000)
(d) SR 183
(1) Intersection Improvements, SR 183 and SR 4030 (Plum Creek), Penn and Bern Townships
300,000
(Base Project Allocation - $100,000)
(Land Allocation - $50,000)
(Design and Contingencies - $150,000)
(e) SR 222
(1) Resurface SR 222 Kutztown Bypass, Maxatawny and Richmond Townships
1,117,000
(Base Project Allocation - $807,000)
(Land Allocation - $250,000)
(Design and Contingencies - $60,000)
(2) Resurface SR 222 from Penn Avenue to Exeter Township Business 422, Cumru, Exeter, Reading and West Reading Townships
1,150,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $100,000)
(Design and Contingencies - $50,000)
(f) SR 422
(1) Restoration of SR 422 from West Shore Bypass to West Wyomissing Spring, West Lawn, Wyomissing, West Wyomissing Townships
1,310,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $250,000)
(Design and Contingencies - $60,000)
(2) Intersection and Safety Improvements, SR 422 and SR 662 Intersection, Amity Township
620,000
(Base Project Allocation - $500,000)
(Land Allocation - $60,000)
(Design and Contingencies - $60,000)
(g) SR 501
(1) Reconstruction and Safety Improvements to SR 501 in the Vicinity of Interchange of I-78 and PA 501, Bethel Township
3,000,000
(Base Project Allocation - $2,400,000)
(Land Allocation - $300,000)
(Design and Contingencies - $300,000)
(h) SR 724
(1) Reconfiguration of Intersection, SR 10 and SR 724 Intersection, Cumru Township
21,000
(Base Project Allocation - $21,000)
(i) SR 2012
(1) Existing Signal Improvement, Second, Walnut, Eleventh and Chestnut Streets, City of Reading
213,000
(Base Project Allocation - $213,000)
(j) Pedestrian Bridge
(1) Construction of a Pedestrian Bridge Crossing Over the Reading, Blue Mountain and Northern Railroads in Tilden Township
1,000,000
(Base Project Allocation - $900,000)
(Land Allocation - $25,000)
(Design and Contingencies - $75,000)