Section 307. Blair County.
(a) SR 6036
(1) Roadway Extension, 9th Avenue Extension between 8th Street in Juniata and PA 36, City of Altoona
8,360,000
(Base Project Allocation - $6,000,000)
(Land Allocation - $2,100,000)
(Design and Contingencies - $260,000)
(2) Construction of a New Roadway, Park Avenue Extension, SR 4010 Southward to SR 1009, Logan Township
880,000
(Base Project Allocation - $600,000)
(Land Allocation - $100,000)
(Design and Contingencies - $180,000)
(b) SR 453
(1) Restoration of SR 453, I-99 to the Pemberton Bridge, Warriors Mark and Snyder Townships
2,630,000
(Base Project Allocation - $2,200,000)
(Land Allocation - $90,000)
(Design and Contingencies - $340,000)
(c) SR 22
(1) Truck Lane Replacement, Restoration of Concrete Pavement, Cambria County Line to SR 8004 Interchange (Cross Keys)
2,670,000
(Base Project Allocation - $2,200,000)
(Land Allocation - $30,000)
(Design and Contingencies - $440,000)
(d) SR 4010
(1) Safety and Traffic Improvements at Various Intersections, 17th Street and Frankstown Road, Logan Township
680,000
(Base Project Allocation - $600,000)
(Land Allocation - $20,000)
(Design and Contingencies - $60,000)
(2) Intersection and Signalization Improvement, Intersection of 17th Street and Logan Town Center, Logan Township
582,000
(Base Project Allocation - $582,000)
(3) Intersection and Signalization Improvement, 17th Street and Valley View Boulevard and 17th Street and Pleasant Valley Boulevard, Logan Township
1,350,000
(Base Project Allocation - $1,350,000)
(e) I-99
(1) Restoration, Grazierville to Bald Eagle, Antis, Snyder and Tyrone Townships
1,350,000
(Base Project Allocation - $1,100,000)
(Land Allocation - $30,000)
(Design and Contingencies - $220,000)
(f) SR 1009
(1) Intersection and Signalization Improvement, Frankstown Road and I-99 Ramp and Park Avenue, Logan Township
712,000
(Base Project Allocation - $712,000)
(2) Intersection and Signalization Improvement, Frankstown Road and 4th Avenue (Amelia Avenue), Logan Township
700,000
(Base Project Allocation - $700,000)
(3) Intersection and Signalization Improvement, Frankstown Road, Fairview Drive and I-99 Southbound Ramp, Logan Township
582,000
(Base Project Allocation - $582,000)
(g) SR 1001
(1) Add Left Turn Lane, 2nd Street to Kettle Street, City of Altoona
170,000
(Base Project Allocation - $110,000)
(Land Allocation - $20,000)
(Design and Contingencies - $40,000)
(h) Street Improvements
(1) Addition of Left Turn Lane, County Road 102 Improvement, City of Altoona
170,000
(Base Project Allocation - $110,000)
(Land Allocation - $20,000)
(Design and Contingencies - $40,000)