Clarion County

Act 149 of 2004, § 316, under HIGHWAY AND TRANSPORTATION ASSISTANCE CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2003-2004 - ENACTMENT.

Act 149 of 2004, § 316

Section 316. Clarion County.

(a) SR 68

(1) New Intersection, Widen, Turning Lanes and Signalization, SR 68 South of I-80 and PA 68 Interchange and North of Williamsburg, Monroe Township

260,000

(Base Project Allocation - $260,000)

(2) Widening of SR 0068 and Improvements to SR 0068 Between I-80 and Commerce Road, Monroe Township

825,000

(Base Project Allocation - $750,000)

(Design and Contingencies - $75,000)

(b) SR 208

(1) Retaining Wall Improvements, Between Maple Street and Beatty Avenue, Knox Borough

105,000

(Base Project Allocation - $80,000)

(Land Allocation - $19,000)

(Design and Contingencies - $6,000)

(2) General Maintenance to Retaining Wall, Knox Borough

124,000

(Base Project Allocation - $80,000)

(Land Allocation - $14,000)

(Design and Contingencies - $30,000)

(c) SR 80

(1) Restoration, I-80 East Resurface, Beaver and Monroe Townships

4,550,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $50,000)

(2) Restoration, I-80 Resurface, Beaver Township

6,050,000

(Base Project Allocation - $6,000,000)

(Design and Contingencies - $50,000)

(3) Resurface, Turkey Run Bridge to Clarion River Bridge, Eastbound, and from East of Weigh Station to Cross Over East of Exit 62 Westbound, Beaver, Paint, Monroe and Clarion Townships

873,000

(Base Project Allocation - $873,000)

(4) Resurfacing and Preventive Maintenance to I-80 East, Beaver and Monroe Townships

4,550,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $50,000)

(5) Resurfacing and Preventive Maintenance to I-80, Beaver Township

6,050,000

(Base Project Allocation - $6,000,000)

(Design and Contingencies - $50,000)

(6) Resurfacing Companion and Preventive Maintenance to I-80 East, Beaver and Monroe Townships

130,000

(Base Project Allocation - $130,000)

(d) SR 368

(1) Intersection Improvements, PA 368 and T-310 Intersection, Licking Township

560,000

(Base Project Allocation - $300,000)

(Land Allocation - $100,000)

(Design and Contingencies - $160,000)