Section 335. Lackawanna County.

(a) I-81

(1) Preventive Maintenance, Resurfacing and Safety Improvements, Interstate 81 in Luzerne and Lackawanna Counties

1,200,000

(Base Project Allocation - $1,200,000)

(2) Corridor Study, SR 81, SR 297 and I-81, Nanticoke to Clarks Summit Borough

100,000

(Design and Contingencies - $100,000)

(3) Widen and Reconstruct I-81, Central Scranton Expressway to Davis Street, City of Scranton

7,100,000

(Base Project Allocation - $6,000)

(Land Allocation - $500,000)

(Design and Contingencies - $600,000)

(4) Interchange Improvement, I-81 Northbound and River Street Interchange, City of Scranton

120,000

(Base Project Allocation - $100,000)

(Design and Contingencies - $20,000)

(5) Construct Sound Barriers on I-81 South Abington Township

1,760,000

(Base Project Allocation - $1,700,000)

(Design and Contingencies - $60,000)

(6) Restore SR 81 and SR 217 between Exits 190 and 197 Northbound and Southbound

320,000

(Base Project Allocation - $300,000)

(Design and Contingencies - $20,000)

(b) SR 11

(1) Signal Improvement, Birney Plaza, Moosic Borough

400,000

(Base Project Allocation - $400,000)

(c) SR 435 and SR 690

(1) Signalization, Widening, Curbs, Sidewalks, Parking, Landscape, Signage and Restoration of Intersection of Main and Church Streets, Moscow Borough

38,000

(Base Project Allocation - $35,000)

(Design and Contingencies - $3,000)

(d) Gravel Pond Road

(1) Resurface, Drainage and Shoulders, Gravel Pond Road, Glenburn Township

40,000

(Base Project Allocation - $40,000)

(e) Miscellaneous

(1) Sidewalk Restoration, Moosic Road, Borough of Old Forge

20,000

(Base Project Allocation - $20,000)

(2) Handicap Ramp Restoration, Moosic Road and Main Street, Borough of Old Forge

4,000

(Base Project Allocation - $4,000)

(3) Install Larger Drainage Pipe, Old Lackawanna Trail Road, Glenburn Township

10,000

(Base Project Allocation - $10,000)

(4) Install Larger Drainage Pipe, Kiley Property on Church Hill Road, Glenburn Township

4,000

(Base Project Allocation - $4,000)

(5) Improve Drainage and Resurface, Waverly Road, Glenburn Township

20,000

(Base Project Allocation - $20,000)

(6) Engineering Study, Old State Road, Glenburn Township

50,000

(Base Project Allocation - $50,000)

(7) Repair Walkways and Curbing, Downtown Area, City of Carbondale

69,000

(Base Project Allocation - $69,000)