Section 348. Northampton County.
(a) I-78
(1) Restoration of I-78, Lower Saucon Township and Bethlehem
665,000
(Base Project Allocation - $600,000)
(Land Allocation - $25,000)
(Design and Contingencies - $40,000)
(2) Reconstruct Interstate I-78, Black River Road Bridge Overpass and Saucon Park Bridge, Lower Saucon Township
695,000
(Base Project Allocation - $600,000)
(Land Allocation - $25,000)
(Design and Contingencies - $70,000)
(b) SR 115
(1) Restoration and Safety Improvements within City Limits, City of Easton
3,620,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $120,000)
(c) SR 412
(1) Safety and Highway Improvements on SR 412, Hellertown Borough
5,858,000
(Base Project Allocation - $5,358,000)
(Design and Contingencies - $500,000)
(2) Construct New 412 Park and Ride Facility, Phase II, Northampton Borough and Bethlehem Township
160,000
(Base Project Allocation - $80,000)
(Design and Contingencies - $80,000)
(d) SR 2009
(1) Construct New Stockpile Facility, 412 Park and Ride, Phase I, Northampton Borough and Bethlehem Township
140,000
(Base Project Allocation - $80,000)
(Design and Contingencies - $60,000)
(e) SR 33
(1) Southbound Bridge Replacement over Bushkill Creek, Stream Lining and Sinkhole Remediation, Palmer Township
2,510,000
(Base Project Allocation - $2,410,000)
(Design and Contingencies - $100,000)
(f) SR 378
(1) Redesign of Traffic Patterns on Route 378 at 5 Points and Parallel City Streets to Create One-way Pairs, City of Bethlehem
2,500,000
(Base Project Allocation - $2,500,000)
(g) SR 2002
(1) Broadway, Reconstruction from Borough Line to the City of Bethlehem
624,000
(Base Project Allocation - $624,000)
(h) SR 33 and SR 2018
(1) Construction Improvements to SR 33 and SR 2018 (Freemansburg Avenue), Bethlehem Township
12,500,000
(Base Project Allocation - $10,625,000)
(Design and Contingencies - $1,875,000)