Section 365. Westmoreland County.
(a) SR 22
(1) Reconstruction and Widening of SR 22, Murrysville and Export Boroughs and Salem Township
12,618,000
(Base Project Allocation - $8,500,000)
(Land Allocation - $3,300,000)
(Design and Contingencies - $818,000)
(b) SR 30
(1) Widening and Safety Improvements to SR 30 from Irwin Turnpike Interchange to the Allegheny County Line, North Huntingdon
1,200,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $100,000)
(Design and Contingencies - $100,000)
(2) Intersection Improvement to SR 30/981, Intersection near Latrobe Airport, Unity Township
2,959,000
(Base Project Allocation - $2,199,000)
(Land Allocation - $200,000)
(Design and Contingencies - $560,000)
(3) Construction for Improvements to US 30 and SR 3020, North Huntingdon Township
6,680,000
(Base Project Allocation - $4,680,000)
(Land Allocation - $1,000,000)
(Design and Contingencies - $1,000,000)
(c) SR 31
(1) Safety Improvement, SR 31 Three Mile Hill, South Huntingdon Township
3,400,000
(Base Project Allocation - $3,400,000)
(2) Intersection Improvement, SR 31 at Exit 9 Donegal, Donegal Township
372,000
(Base Project Allocation - $250,000)
(Land Allocation - $50,000)
(Design and Contingencies - $72,000)
(d) SR 51
(1) Safety Improvement to SR 51, Rostraver Township
613,000
(Base Project Allocation - $550,000)
(Land Allocation - $23,000)
(Design and Contingencies - $40,000)
(e) SR 56
(1) Signal Improvement and Add Lanes to SR 56 at SR 4048, Hyde Park Road, Allegheny Township
760,000
(Base Project Allocation - $300,000)
(Land Allocation - $225,000)
(Design and Contingencies - $235,000)
(f) I-70
(1) Interchange Improvement, I-70, New Stanton Borough
1,900,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $250,000)
(Design and Contingencies - $150,000)
(2) Lane Expansion, Ramp Upgrade and Bridge Replacement, I-70 and SR 201 Upgrades, Rostraver Township
9,617,000
(Base Project Allocation - $7,000,000)
(Land Allocation - $1,600,000)
(Design and Contingencies - $1,017,000)
(g) SR 119
(1) Reconstruction and Interchange Improvement to SR 119, Sony Interchange, Westmoreland County
2,420,000
(Base Project Allocation - $2,000,000)
(Land Allocation - $120,000)
(Design and Contingencies - $300,000)
(2) Resurface, Upgrade Signals and Replace Curbs to SR 119, Youngwood Borough
630,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $30,000)
(h) SR 130
(1) Restoration of SR 130 from SR 4002 to Toll 66, Hempfield Township
540,000
(Base Project Allocation - $500,000)
(Land Allocation - $15,000)
(Design and Contingencies - $25,000)
(Design and Contingencies - $25,000)
(2) Intersection Improvement, SR 130 Improvements, Penn Township
350,000
(Land Allocation - $150,000)
(Design and Contingencies - $200,000)
(3) Intersection Improvement of SR 130 at Pleasant Valley Road Intersection, Penn Township
550,000
(Base Project Allocation - $100,000)
(Land Allocation - $250,000)
(Design and Contingencies - $200,000)
(i) SR 136
(1) Intersection Improvements and Resurface, Willow Crossing Road to Toll Road, Hempfield Township
1,430,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $120,000)
(Design and Contingencies - $110,000)
(j) SR 356
(1) Intersection Improvement, PA 356, Allegheny Township
700,000
(Base Project Allocation - $200,000)
(Land Allocation - $200,000)
(Design and Contingencies - $300,000)
(k) SR 366
(1) Signal and Safety Improvement to SR 366 from SR 56 to Tarentum Bridge: North from SR 56 LA Murrysville, New Kensington and Washington Townships
1,200,000
(Base Project Allocation - $600,000)
(Land Allocation - $250,000)
(Design and Contingencies - $350,000)
(2) Reconstruction, Parnassus Triangle Phase II, Cities of Lower Burrell and New Kensington
1,220,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $120,000)
(Design and Contingencies - $100,000)
(l) SR 1045
(1) Two Lane Relocation of SR 1045 at St. Vincent College, Unity Township
2,225,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $125,000)
(Design and Contingencies - $1,100,000)
(m) SR 4002
(1) Reconstruction, SR 4002 North Greengate Road, Hempfield Township
1,830,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $240,000)
(Design and Contingencies - $90,000)
(2) Widening, Between SR 30 and Railroad Underpass, Hempfield Township
1,150,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $100,000)
(Design and Contingencies - $50,000)
(n) SR 3111
(1) Widening and Constructing New Two-Lane Roadway, Center Avenue, New Stanton Borough
2,800,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $1,000,000)
(Design and Contingencies - $300,000)