Section 2

Act 155 of 1974, § 2, under PROJECT 70 LAND TRANSFERRED TO DEPARTMENT OF TRANSPORTATION.

Act 155 of 1974, § 2

Section 2. The land to be transferred by the City of Bethlehem to the Department of Transportation for right-of-way for construction of Highway Project, L.R. 1045, Section F03, to locate Interstate 78 is more particularly described as follows:

Description of Highway Project

Project L.R. 1045, Section F03, beginning at a point in the City of Bethlehem, Northampton County, approximately 2,200 feet west of the intersection of William Street, crossing Saucon Creek and tracks of the Reading Company. Continuing, the line crosses L.R. 530, Traffic Route 412 (Hellertown Road), immediately north of Silvex Road, terminating at a point immediately west of L.R. 48006 (Easton Road), 900 feet northeast of the intersection of L.R. 48006 and L.R. 48097 (Cherry Lane), in the City of Bethlehem, Northampton County, a distance of approximately 1.5 miles.

Description of Required Project 70 Land

The Project 70 land required for the above highway comprises approximately 3.29 acres, located approximately as follows:

(1) Between Stations 339 + 83 and 342 + 00 on the eastbound centerline.

(2) Between Stations 340 + 25 and 343 + 10 on the westbound centerline.

(3) Between Stations 340 + 63 and 342 + 48 on Ramp ZA.

(4) Between Stations 340 + 15 and 343 + 25 on Ramp ZB.

The highway right-of-way will have a maximum width of 800 feet, more or less.