Itemization of flood control projects

Act 22 of 2000, § 8, under CAPITAL BUDGET ACT OF 2000-2001.

Act 22 of 2000, § 8

Section 8. Itemization of flood control projects.

Additional capital projects in the category of flood control projects to be constructed by the Department of Environmental Protection, its successors or assigns, and to be financed by the incurring of debt are hereby itemized, together with their respective estimated costs, as follows:

Project

Total

Project

Allocation

(1) Department of Environmental Protection

(i) Erie County

(A) Cascade Street storm sewer replacement, City of Erie

750,000

(ii) Lycoming County

(A) McClure's Run Stream Restoration Project, including culvert replacement, Loyalsock Township

117,000

(B) Muncy Creek Stream Restoration Project, Muncy Creek Township

740,000

(C) Hagerman's Run Flood Control Project, including the rehabilitation and upgrade of conduit, South Williamsport Borough

1,000,000

(D) Integrated flood forecasting system - urban area topography study, including hydrologic studies, stream and rain gauging and flood inundation mapping

1,500,000

(E) Lower Lycoming Creek Flood Mitigation

3,100,000

(F) Countywide flood hazard mitigation program

500,000

(G) Ralston flood mitigation project, Village of Ralston

300,000

(iii) Somerset County, Benson Borough Federal Flood Control Project

(A) Additional Funds for the Benson Federal Flood Control Project

260,000

(Base Project Allocation - $260,000)

(iv) Somerset County, Hooversville Borough Federal Flood Control Project

(A) Additional Funds for the Hooversville Federal Flood Control Project

326,000

(Base Project Allocation - $326,000)

(v) Sullivan County

(A) Flood Control Project to prevent runoff from Loyalsock Creek, Dushore Borough

566,000

(vi) Lackawanna County

(A) Construction of pumping stations for U.S. Army Corps of Engineers flood control project along the Lackawanna River in the areas of the plot section, the lower Green Ridge section and the Albright Avenue section in the City of Scranton

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(8 added June 22, 2000, P.L.136, No.27)