Additional capital projects in the category of public improvement projects to be acquired or constructed by the Department of General Services, its successors or assigns, and to be financed by the incurring of debt, are hereby itemized, together with their respective estimated financial costs, as follows:

Project

Total Project

Allocation

(1) Department of Agriculture

(i) Farm Show Complex

(A) Renovations of the underground (Cameron Street) pedestrian/cyclist walk from Department of Agriculture to the Farm Show Complex and associated pathways

Project Allocation

3,000,000

(ii) Samuel E. Hayes Jr. Livestock Evaluation Center

(A) Renovations to the Livestock Evaluation Center

Project Allocation

2,000,000

(iii) Health Diagnostic Laboratory

(A) Renovations, additions and new construction, including site and infrastructure improvements for design and construction to satisfy modern testing procedures

Project Allocation

25,000,000

(2) Department of Conservation and Natural Resources

(i) Clear Creek Forest District

(A) New maintenance shop and equipment storage

Project Allocation

4,000,000

(ii) Cornplanter Forest District

(A) Office renovation

Project Allocation

3,000,000

(ii.1) Cowans Gap State Park

(A) Rehabilitate Cowans Gap Dam

Project Allocation

9,200,000

(iii) Delaware State Forest

(A) Lilly Pond Dam spillway repair/ replacement

Project Allocation

1,350,000

(iii.1) Hickory Run State Park

(A) Additional funding to replace pit latrines with modern comfort stations

Project Allocation

700,000

(iii.2) Kooser State Park

(A) Day-use improvements and dam rehabilitation

Project Allocation

6,250,000

(iii.3) Laurel Hill State Park

(A) Rehabilitate Penn Scenic View Dam

Project Allocation

5,000,000

(iii.4) Leonard Harrison State Park

(A) Turkey Path Trail rehabilitation and realignment

Project Allocation

3,750,000

(iii.5) McKeever Center

(A) Land acquisition, construction and infrastructure costs

Project Allocation

1,000,000

(iii.6) Memorial Lake State Park

(A) Rehabilitate dam

Project Allocation

9,800,000

(iv) Norristown Farm Park

(A) Replace multiple vehicular and pedestrian bridges

Project Allocation

6,250,000

(iv.1) Parker Dam State Park

(A) Dam repairs and lake dredging

Project Allocation

11,250,000

(v) Pinchot State Forest

(A) Remove Turtle Creek Dam

Project Allocation

1,875,000

(vi) Pinchot Forest District

(A) Remove Race Run Dam

Project Allocation

2,000,000

(B) Remove Dam 148-118 SGL 260

Project Allocation

2,000,000

(vi.1) Point State Park

(A) Portal bridge replacement and park sidewalk rehabilitation and ADA compliance

Project Allocation

3,750,000

(vi.2) Prince Gallitzin State Park

(A) Rehabilitate Sandy Run Dam

Project Allocation

12,000,000

(vi.3) Promised Land State Park

(A) Rehabilitate Promised Land Dam

Project Allocation

5,000,000

(vi.4) Pymatuning State Park

(A) Rehabilitate park and campground facilities

Project Allocation

5,000,000

(vi.5) Raccoon Creek State Park

(A) Extend toe drain at Raccoon Creek Lake Dam

Project Allocation

1,250,000

(vi.6) Shikellamy State Park

(A) Rehabilitate dam

Project Allocation

15,000,000

(vii) Tiadaghton & Tioga Forest Districts

(A) Pine Creek Rail Trail-truss bridges over Pine Creek

Project Allocation

6,700,000

(vii.1) Yellow Creek State Park

(A) Construction, infrastructure, renovations and other related costs for improvements and upgrades

Project Allocation

5,850,000

(viii) Various State Parks - Statewide

(A) Campground facility amenities - construct washhouses, including utility and site work

Project Allocation

12,500,000

(B) Rehabilitate historic structures

Project Allocation

12,500,000

(C) Statewide critical regulatory system repairs and replacements at multiple water and wastewater treatment plants

Project Allocation

12,500,000

(D) New and replacement of roofed overnight colonies and support infrastructure at five State parks

Project Allocation

6,250,000

(E) Construct solar arrays at various State park facilities

Project Allocation

15,000,000

(ix) Bureau of Forestry

(A) New Regional Air Operations facilities

Project Allocation

9,600,000

(B) New Fire Cache/Forestry warehouse - replace main building

Project Allocation

7,200,000

(C) Construct solar arrays at various forestry facilities

Project Allocation

3,750,000

(3) Department of Corrections

(i) Elizabethtown Training Facility

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

3,982,700

(ii) Quehanna Boot Camp

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

2,793,000

(iii) State Correctional Institution at Albion

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

4,362,000

(iv) State Correctional Institution at Benner

(A) Design and construction of a transportation hub, including land development and site infrastructure improvements

Project Allocation

3,000,000

(B) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

5,933,490

(v) State Correctional Institution at Cambridge Springs

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

15,354,000

(vi) State Correctional Institution at Camp Hill

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

37,425,000

(vii) State Correctional Institution at Chester

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

6,848,000

(viii) State Correctional Institution at Coal Township

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

12,567,000

(ix) State Correctional Institution at Dallas

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

1,657,000

(x) State Correctional Institution at Fayette

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

15,679,200

(xi) State Correctional Institution at Forest

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

14,394,000

(xii) State Correctional Institution at Frackville

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

6,397,900

(xiii) State Correctional Institution at Graterford

(A) Design and construction of code, permit and site/utility/infrastructure-related issues

Project Allocation

650,000

(xiv) State Correctional Institution at Greene

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

7,462,000

(xv) State Correctional Institution at Houtzdale

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

11,897,500

(xvi) State Correctional Institution at Huntingdon

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

14,292,350

(xvii) State Correctional Institution at Laurel Highlands

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

6,738,300

(xviii) State Correctional Institution at Mahanoy

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

20,493,500

(xix) State Correctional Institution at Mercer

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

7,908,500

(xx) State Correctional Institution at Muncy

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

14,342,980

(xxi) State Correctional Institution at Pine Grove

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

8,596,000

(xxii) State Correctional Institution at Retreat

(A) Design and construction of facility upgrades, including land development and site infrastructure improvements and new construction

Project Allocation

1,500,000

(xxiii) State Correctional Institution at Rockview

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

10,131,000

(xxiv) State Correctional Institution at Smithfield

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

8,375,270

(xxv) State Correctional Institution at Somerset

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

8,403,610

(xxvi) State Correctional Institution at Waymart

(A) Design and construction of building expansion, new construction, renovations and alterations, including land development and site infrastructure improvements

Project Allocation

19,787,295

(4) Department of Education

(i) Department of Education Headquarters (Reserved)

(ii) Lincoln University

(A) Infrastructure replacement, upgrade and improvements

Project Allocation

26,000,000

(B) Renovation of Houston Hall

Project Allocation

12,000,000

(iii) The Pennsylvania State University

(A) Davey Laboratory Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Davey Laboratory at the University Park campus. The project scope includes building systems renewal, including mechanical, electrical, plumbing and sprinkler systems and code upgrades. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

100,000,000

(B) Osmond Laboratory Renovation - Phase II (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Phase II of Osmond Laboratory at the University Park campus. This project will complete the renovation of Osmond Laboratory. The project will renew the remainder of facility by replacing worn systems, improving the thermal envelope, replacing windows and interior finishes. Interior space modifications will be made to meet the needs of the departments and activities currently housed there and into the future. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

40,000,000

(C) Carpenter Building Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the Carpenter Building at the University Park campus. The Carpenter Building requires building-wide renewal to include building, life safety system and accessibility upgrades. The project includes building systems and envelope renewal/replacement. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

40,000,000

(D) Student Support and Services Center (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for a Student Support and Services Center at the University Park campus. A new multistory building will be constructed to provide functional spaces for student support and engagement, admissions and administration. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

90,000,000

(E) Electrical Engineering West Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Electrical Engineering West at the University Park campus. This project addresses the continuing needs of the College of Engineering. The project scope includes building-wide systems renewal, including mechanical, electrical, plumbing and sprinkler systems to improve efficiency and performance. The building exterior improvements include masonry repair, roof and window replacement. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

65,000,000

(F) Electrical Engineering East Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Electrical Engineering East at the University Park campus. This project addresses the continuing needs of the College of Engineering. The project scope includes building systems renewal, including mechanical, electrical, plumbing and fire suppression systems to improve efficiency and performance. The building exterior improvements include glazing, curtain wall and door replacement. Interior and accessibility improvements are needed. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

45,000,000

(G) Pattee Library/Paterno Library Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Pattee Library/Paterno Library at the University Park campus. This project will address aging systems, accessibility concerns, reliability issues and safety concerns. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

60,000,000

(H) Sparks Building Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the Sparks Building at the University Park campus. The project will include building system and envelope renewal and renovation to address programmatic and system needs. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

65,000,000

(I) Applied Research Laboratory Renovation (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the Applied Research Laboratory at the University Park campus. The ARL Building requires building-wide renewal to include building systems and envelope renewal/replacement. The project scope also includes life safety system and accessibility upgrades. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

50,000,000

(J) Capital Renewal, Phase X (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Capital Renewal, Phase X at the University Park campus. This project will allow the University to replace, install or upgrade as appropriate systems in major academic, research and administrative buildings across campus that were not addressed in the other phases of renewal. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

40,000,000

(K) Chilled Water Plant (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for a Chilled Water Plant at the University Park campus. Scope includes new building construction along with the initial chilled water, condenser water and electrical equipment and plant infrastructure. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

80,000,000

(L) Advanced Water Treatment System (University Park Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for an Advanced Water Treatment System at the University Park campus. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

15,000,000

(M) Classroom-Library Building Renovation (and Nursing Addition) (Scranton Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the Classroom-Library Building Renovation (and Nursing Addition) at the Scranton campus. A total renovation is needed to address a multitude of deficiencies. An addition for the expansion of the Nursing program is planned. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

20,000,000

(N) Kelly Library Renovation and Addition (Greater Allegheny Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the Kelly Library Renovation and Addition at the Greater Allegheny campus. A total renovation is needed to address a multitude of deficiencies. An addition for an auditorium is planned. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

20,000,000

(O) Classroom/Class Lab Teaching and Learning Building (Harrisburg Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for a Classroom/Class Lab Teaching and Learning Building at the Harrisburg campus. A new multistory Classroom/Class Lab Teaching and Learning Building will be constructed to provide modern classrooms, instructional laboratories, faculty offices, instructional support and flexible/adaptable space to support both general and technology instructional programs, as well as campus engagement activities. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

50,000,000

(P) Teaching and Administrative Support Building (Hershey Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for a Teaching and Administrative Support Building at the Hershey campus. This project will provide space for key administrative units on campus. The program will include new administrative and support spaces, offices and meeting rooms. The facility will be equipped with state-of-the-art technology. The facility will be located on the core campus adjacent to clinical, administrative, research and academic facilities easily accessible by students, faculty and visitors. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

80,000,000

(Q) Capital Renewal (Hershey Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for Capital Renewal at the Hershey campus. This project is part of a continuing effort to make significant comprehensive upgrades to infrastructure in the College of Medicine buildings at the Hershey campus. This project will allow the University to replace, install or upgrade as appropriate systems in major academic, research and administrative buildings across campus that were not addressed in routine renewal programs. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

30,000,000

(R) Academic and Research Building (Hershey Campus) design, construction (new space or addition to and/or renovation of existing space; including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for an Academic and Research Building at the Hershey campus. This project will include new wet and dry research laboratories, comparative medicine spaces, support spaces, instructional spaces, seminar rooms, offices and administration space. The facility will be equipped with state-of-the-art instructional technology. The facility will be located on the core campus adjacent to academic, clinical and other research facilities easily accessible by students, faculty and visitors. Funding will be used for both design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for both occupant and program relocation or interim facilities will be included. The construction will both meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

160,000,000

(S) North Wing of Chambers Building (University Park Campus) design, construction (new space or addition to and/or renovation of existing space, including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for the North Wing of Chambers Building at the University Park campus. This project involves the renovation, demolition and reconstruction of Chambers Building. Funding will be used for design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for occupant and program relocation or interim facilities will be included. The construction will meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

60,000,000

(T) Demolition Program (University Park Campus) design, construction (new space or addition to and/or renovation of existing space, including demolition, abatement of hazardous materials, extensions and/or upgrading of utilities and other infrastructure needs) and other related costs for a Demolition Program at the University Park campus. This project involves the demolition of campus facilities. Funding will be used for design and construction costs, as well as necessary utility upgrades and extensions, site improvements and code-related upgrades. All costs for occupant and program relocation or interim facilities will be included. The construction will meet all current building code requirements and provide for barrier-free access as required by the Americans with Disabilities Act and related codes

Project Allocation

10,000,000

(U) Critical infrastructure improvements to athletic facilities at University Park campus

Project Allocation

150,000,000

(V) Acquisition, reclamation, infrastructure improvements and construction to land and facilities at the Pennsylvania College of Technology in the City of Williamsport

Project Allocation

10,000,000

(iv) Temple University

(A) Design, infrastructure, abatement of hazardous materials and construction of an academic/administrative building, including utility upgrades and extensions, site improvements and code-related upgrades, including ADA compliance-related upgrades, at the main campus of Temple University

Project Allocation

250,000,000

(B) Design, infrastructure, abatement of hazardous materials and construction of an academic/administrative building, including utility upgrades and extensions, site improvements and code-related upgrades, including ADA compliance-related upgrades, at the main campus of Temple University

Project Allocation

185,000,000

(C) New classroom building, addition, renovation - design, infrastructure, abatement of hazardous materials and construction of a classroom building academic complex. This will involve renovating and adding to an existing building or building a stand-alone classroom building

Project Allocation

125,000,000

(C.1) New Science, Technology, Engineering and Mathematics (STEM) academic building, addition, renovation - design, infrastructure, abatement of hazardous materials and construction of a STEM academic complex. This will involve renovating and adding to an existing building or building a stand-alone building

Project Allocation

125,000,000

(D) Design, infrastructure, abatement of hazardous materials, renovation and construction of expansion to Ritter Hall, including utility upgrades and extensions, site improvements, code-related upgrades, including ADA compliance-related upgrades

Project Allocation

40,000,000

(E) Construction, renovation, acquisition, infrastructure improvements, equipment and other related costs for the development of an ambulatory care facility, including related administrative, clinical, patient, community research, educational and exterior facilities of Temple University Hospital and affiliated physician practices

Project Allocation

60,000,000

(F) Construction, renovation, infrastructure improvements, equipment and other related costs for the development and modernization of patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities of Temple University Health System

Project Allocation

60,000,000

(G) Construction, renovation, infrastructure improvements, equipment and other related costs for the modernization of administrative facilities and related clinical, patient, community, research, educational and exterior facilities of Temple University Health System

Project Allocation

30,000,000

(H) Construction, renovation, acquisition, infrastructure improvements, equipment and other related costs for the modernization of patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities for Temple University Hospital-Boyer Pavilion

Project Allocation

40,000,000

(I) Construction, renovation, infrastructure improvements, equipment and other related costs for the development of and modernization of women's health and patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities of Temple University Hospital

Project Allocation

60,000,000

(J) Construction, renovation, acquisition, infrastructure improvements, equipment and other related costs for the modernization of patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities for Temple University Hospital

Project Allocation

60,000,000

(K) Construction, renovation, infrastructure improvements, equipment and other related costs for the modernization of patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities for Temple University Hospital Episcopal Campus

Project Allocation

40,000,000

(L) Construction, renovation, acquisition, infrastructure improvements, equipment and other related costs for the modernization of patient care and research facilities, including related administrative, clinical, community, educational and exterior facilities for Fox Chase Cancer Center

Project Allocation

60,000,000

(M) Construction, renovation, acquisition, infrastructure improvements, equipment and other related costs for the modernization of patient care facilities, including related administrative, clinical, community, research, educational and exterior facilities for Temple University Hospital Jeanes Campus

Project Allocation

40,000,000

(N) Construction, infrastructure, acquisition, redevelopment and other related costs to be used for academic space at Temple University Main Campus

Project Allocation

1,300,000

(v) Thaddeus Stevens College of Technology

(A) Hartzell renovations

Project Allocation

4,000,000

(B) Jones renovations

Project Allocation

5,000,000

(C) Mellor renovations

Project Allocation

20,000,000

(D) Dorm renovations

Project Allocation

7,000,000

(E) Shop addition

Project Allocation

5,000,000

(F) Student Center addition

Project Allocation

5,000,000

(G) Campus improvements to meet current and future demands, including, but not limited to, land acquisition, site and building infrastructure improvements, new construction, renovations and building system upgrades and improvements

Project Allocation

18,000,000

(H) Branch Campus improvements to meet current and future demands, including, but not limited to, land acquisition, site and building infrastructure improvements, new construction, renovations and building system upgrades and improvements

Project Allocation

8,000,000

(I) Roof - Renovations, alterations, infrastructure upgrades and associated design and construction expenses at the Bourne, Brenner, Kreider, Hartzell and Metzger Buildings

Project Allocation

3,500,000

(J) Snyder Building - Renovations, alterations, additions, infrastructure upgrades, site improvements and associated design and construction expenses

Project Allocation

5,000,000

(K) ALMS House - Renovations, repairs, alterations, additions, infrastructure upgrades and associated design and construction expenses

Project Allocation

25,000,000

(L) Orange Street Campus - Renovations, repairs, alterations, additions, infrastructure upgrades and associated design and construction expenses

Project Allocation

3,500,000

(M) Main Campus - Sidewalks/road repair

Project Allocation

1,500,000

(vi) University of Pittsburgh

(A) New Integrated Health Sciences Building, Oakland Campus

Project Allocation

200,000,000

(B) New Academic Student Support Center Building, Oakland Campus

Project Allocation

80,000,000

(C) New One Bigelow Academic Teaching and Research Complex, Oakland Campus

Project Allocation

300,000,000

(D) Posvar Hall addition and renovation, Oakland Campus

Project Allocation

100,000,000

(E) Posvar Hall Chiller Plant expansion and upgrade, Oakland Campus

Project Allocation

50,000,000

(F) Programmatic and infrastructure upgrades to buildings, Oakland Campus

Project Allocation

50,000,000

(G) Crabtree Hall renovations, Oakland Campus

Project Allocation

110,000,000

(vii) Butler County Community College

(A) Construction, infrastructure and other related costs for construction of a two-story building for additional instructional space

Project Allocation

1,750,000

(5) Pennsylvania Emergency Management Agency (Reserved)

(6) Department of Environmental Protection

(i) Carbon County

(A) Quakake Treatment Facility - Additional funds for construction of acid mine treatment facility

Project Allocation

6,000,000

(ii) Clarion County

(A) Mill Creek Treatment Facility - Construction of treatment facility

Project Allocation

14,000,000

(iii) Clearfield County

(A) Additional funds for additional culvert alignment under borough streets at Stinky Run

Project Allocation

1,000,000

(iv) Fayette County

(A) Phillips Discharge Treatment Facility - Construction of treatment facility

Project Allocation

12,000,000

(v) Jefferson County

(A) Weisner Hollow - Additional funds to decertify high-hazard dam and construct permanent drainage channel. Regrade and revegetate site

Project Allocation

6,500,000

(vi) Lycoming County

(A) Grafius Run and Freedom Road Tributary - Improve existing culverts in the City of Williamsport

Project Allocation

3,500,000

(vii) Westmoreland County

(A) West Newton Coal Logistics Slope - Embankment stabilization and coal refuse slurry impoundment capping

Project Allocation

23,000,000

(7) Department of General Services

(i) Berks County

(A) Renovations, alterations, new construction, site improvements, infrastructure upgrades and land acquisition for DGS-owned buildings in the Reading area

Project Allocation

15,000,000

(ii) Dauphin County

(A) Renovations, alterations, new construction, site improvements, infrastructure upgrades and land acquisition for DGS-owned buildings in the Harrisburg area

Project Allocation

200,000,000

(B) Upgrade and expansion of IT infrastructure and automation system redundancy

Project Allocation

100,000,000

(C) Renovations and alterations for upgrades and infrastructure improvements to the Finance Building

Project Allocation

100,000,000

(iii) Lackawanna County

(A) Renovations, alterations, new construction, site improvements, infrastructure upgrades and land acquisition for DGS-owned buildings in Scranton

Project Allocation

15,000,000

(iv) Statewide

(A) Professional services for the development of agency facility strategic master plans and capital planning

Project Allocation

15,000,000

(B) Renovations, alterations, new construction, site improvements and infrastructure upgrades for Commonwealth child-care centers

Project Allocation

7,000,000

(7.1) Department of Health

(i) Bureau of Laboratories

(A) Construct new laboratory, including site and infrastructure improvements

Project Allocation

60,000,000

(8) Department of Human Services

(i) Clarks Summit State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(ii) Danville State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(iii) Ebensburg Center

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(iv) Loysville Youth Development Center

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(v) Norristown State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(B) Additional funds for the design and construction of a psychiatric forensic building on existing lands of the Commonwealth at Norristown State Hospital in West Norriton Township to be utilized for the care and treatment of clients admitted to the institution

Project Allocation

190,000,000

(vi) North Central Secure Treatment Unit

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

7,000,000

(vii) Selinsgrove Center

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(viii) South Mountain Secure Treatment Unit

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

5,000,000

(ix) South Mountain Restoration Center

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(x) Torrance State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(xi) Warren State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(xii) Wernersville State Hospital

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(xiii) Youth Forestry Camp No.2

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

9,000,000

(xiv) Youth Forestry Camp No.3

(A) Renovate the institution, including new construction, alterations, renovations, site improvements and infrastructure upgrades, and land acquisition

Project Allocation

5,000,000

(xv) Northeast Juvenile Justice Facility

(A) New construction, renovation, rehabilitation, acquisition of land and facility and associated costs in northeastern Pennsylvania

Project Allocation

25,000,000

(9) Pennsylvania Historical and Museum Commission

(i) State Museum

(A) Exhibit upgrades

Project Allocation

20,000,000

(ii) Brandywine Battlefield Park

(A) Building, site and infrastructure improvements

Project Allocation

5,000,000

(iii) Daniel Boone Homestead

(A) Building, site and infrastructure improvements

Project Allocation

5,000,000

(iv) Drake Well

(A) Building, site and infrastructure improvements

Project Allocation

3,000,000

(v) Erie Maritime Museum

(A) Building, site and infrastructure improvements

Project Allocation

2,000,000

(vi) Graeme Park

(A) Building, site and infrastructure improvements

Project Allocation

3,500,000

(B) Exhibit upgrades

Project Allocation

1,000,000

(vii) Railroad Museum of Pennsylvania

(A) Building, site and infrastructure improvements

Project Allocation

13,000,000

(10) Department of Military and Veterans Affairs

(i) Delaware Valley Veterans Home

(A) Construct new adult day health care and 48-bed nursing care addition with additional parking area

Project Allocation

20,000,000

(B) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(ii) Gino J. Merli Veterans Center

(A) Construct new adult day health care addition with parking area, including demolition as required

Project Allocation

13,500,000

(B) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(iii) Hollidaysburg Veterans Home

(A) Construct new adult day health care addition with additional parking area

Project Allocation

8,040,000

(B) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(iv) Pennsylvania Soldiers' & Sailors' Home, Erie

(A) Construct new adult day health care addition with additional parking area

Project Allocation

10,720,000

(B) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(v) Southeastern Veterans' Center, Spring City

(A) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(vi) Southwestern Veterans' Center, Pittsburgh

(A) Construct new adult day health care addition with additional parking area

Project Allocation

14,740,000

(B) Rehabilitate Veterans' Home

Project Allocation

10,000,000

(vii) Statewide Veterans' Homes

(A) Provide safety measures and physical security upgrades, including new construction, renovations, electronic security systems and equipment, and site work

Project Allocation

30,000,000

(B) Provide additional funding to rehabilitate PA Veterans' Homes, including to remedy life safety and regulatory deficiencies

Project Allocation

30,000,000

(viii) Allentown Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(ix) Beaver Falls Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(x) Berks County Readiness Centers

(A) Renovate DMVA facilities in Berks County, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

20,000,000

(xi) Cambridge Springs Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

12,500,000

(xii) Cumberland County Readiness Centers

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades for all DMVA facilities in Cumberland County

Project Allocation

27,500,000

(xiii) Chambersburg Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xiv) Coatesville Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xv) Easton Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xvi) Everett Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xvii) Fort Indiantown Gap DMVA facilities and infrastructure

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

37,500,000

(xviii) Greensburg Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xviii.1) Hiller Army Reserve Center, Fayette County

(A) Rehabilitate various buildings, including an unheated storage facility and parking

Project Allocation

2,500,000

(xix) Huntingdon Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xx) Lebanon Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

12,500,000

(xxi) Lewisburg Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

12,500,000

(xxii) Lewistown Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

12,500,000

(xxiii) Luzerne County Readiness Centers

(A) Renovate DMVA facilities in Luzerne County, including demolition, new construction, correcting structure and infrastructure deficiencies, and security system upgrades

Project Allocation

25,000,000

(xxiv) Philadelphia/Delaware Counties Readiness Center

(A) Renovate the facility, including demolition, new construction, correcting structure and infrastructure deficiencies, and security system upgrades for Readiness Center

Project Allocation

20,000,000

(xxv) Punxsutawney Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

7,500,000

(xxvi) South Mountain Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

7,500,000

(xxvii) Tamaqua Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

15,000,000

(xxviii) Wellsboro Readiness Center

(A) Renovate the Readiness Center, including demolition, new construction, correcting structure and infrastructure deficiencies and security system upgrades

Project Allocation

10,000,000

(xxix) New Readiness Center

(A) Land and/or building acquisition for new readiness center to relocate existing center in Dauphin and/or Lebanon counties

Project Allocation

20,000,000

(B) Acquisition of land and or facilities to build or renovate buildings for a new readiness center in southeastern Pennsylvania

Project Allocation

33,000,000

(xxx) Horsham Air Guard Station

(A) Acquisition, construction and other related costs for a capital improvement project

Project Allocation

15,000,000

(11) Office of Administration

(i) Commonwealth Technology Center (Reserved)

(12) Pennsylvania State Police

(i) Statewide

(A) Capital renewal of existing facilities, including site and building envelop improvements, interior renovations, building system upgrades and code-required improvements

Project Allocation

25,000,000

(B) Land acquisition or purchase of existing facility to replace existing troop headquarter buildings or provide new facilities

Project Allocation

29,000,000

(ii) Regional Forensic Laboratory

(A) Renovate and construct new laboratory in central Pennsylvania, including site and infrastructure improvements

Project Allocation

30,000,000

(iii) Pennsylvania State Police Academy and BESO Complex

(A) Additional funding for construction and other related costs for the Pennsylvania State Police Academy and BESO Complex in Derry Township, Dauphin County

Project Allocation

8,000,000

(iv) Erie Headquarters

(A) Additional funding for construction and other related costs for new headquarters in Erie County

Project Allocation

5,500,000

(v) DNA Laboratory

(A) Additional funding for design and construction of a new DNA laboratory in the City of Greensburg, Westmoreland County

Project Allocation

5,500,000

(13) State System of Higher Education

(i) Bloomsburg University

(A) Acquisition or construction of student housing

Project Allocation

98,000,000

(B) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

25,000,000

(C) Additional funding for Waller Administration Building renovations

Project Allocation

11,000,000

(ii) California University

(A) Acquisition or construction of student housing, additional funds

Project Allocation

33,000,000

(B) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(C) Renovations and rehabilitation of athletic facilities

Project Allocation

2,000,000

(iii) Cheyney University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(iv) Clarion University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(v) East Stroudsburg University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(vi) Edinboro University

(A) Hamilton Hall renovation

Project Allocation

25,000,000

(B) Demolition of underutilized and obsolete buildings

Project Allocation

15,000,000

(C) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(D) Renovation and rehabilitation of athletic facilities

Project Allocation

2,000,000

(vii) Indiana University

(A) Upgrade of campus utilities infrastructure

Project Allocation

40,000,000

(B) Demolition of underutilized and obsolete buildings, additional funds

Project Allocation

15,000,000

(C) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

35,000,000

(viii) Kutztown University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(B) Beeky Education Building renovation

Project Allocation

19,000,000

(ix) Lock Haven University

(A) Acquisition or construction of student housing, additional funds

Project Allocation

20,000,000

(B) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(x) Mansfield University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(B) Renovation, replacement or upgrade of campus utilities infrastructure, additional funds

Project Allocation

5,000,000

(xi) Millersville University

(A) Renovation, replacement or upgrade of campus utilities infrastructure, additional funds

Project Allocation

21,000,000

(B) Stadium renovation

Project Allocation

15,000,000

(xii) Shippensburg University

(A) Heiges Field House renovation and addition

Project Allocation

40,000,000

(B) Old Main renovation

Project Allocation

15,000,000

(C) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

20,000,000

(xiii) Slippery Rock University

(A) Additional funds for McKay Building renovation/addition

Project Allocation

15,000,000

(B) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

29,000,000

(xiv) West Chester University

(A) Provide for deferred maintenance needs and capital renewal repairs, additional funds

Project Allocation

32,000,000

(14) Department of Transportation

(i) Adams County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(ii) Allegheny County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 11-0

Project Allocation

10,000,000

(B) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at the western training facility

Project Allocation

5,000,000

(C) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(D) Provide for the construction or renovation of maintenance facility at Fort Pitt Tunnel, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(E) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 11

Project Allocation

5,000,000

(F) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 12

Project Allocation

5,000,000

(G) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(iii) Armstrong County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(iv) Beaver County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(v) Bedford County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(vi) Berks County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(vii) Blair County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 9-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(viii) Bradford County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(ix) Bucks County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site P

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(x) Butler County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xi) Cambria County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xii) Cameron County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xiii) Carbon County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xiv) Centre County

(A) Provide for the construction or renovation of Bellefonte Maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Provide for the construction or renovation of Phillipsburg Maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 29

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 30

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xv) Chester County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xvi) Clarion County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xvii) Clearfield County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 2-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xviii) Clinton County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 33

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 34

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xix) Columbia County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 37

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 38

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xx) Crawford County

(A) Provide for the construction or renovation of Centerville maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Provide for the construction or renovation of Meadville maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 19

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 20

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxi) Cumberland County

(A) Provide for the construction or renovation of Carlisle maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Provide for the construction or renovation of Lemoyne maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 45

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 46

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxii) Dauphin County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 8-0

Project Allocation

10,000,000

(B) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at the material testing lab

Project Allocation

8,000,000

(C) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at the fleet management facility

Project Allocation

5,000,000

(D) Construction or renovation of sign shop facility. May include site acquisition and development, design and construction of buildings and utility work

Project Allocation

5,000,000

(E) Provide for the construction or renovation of Harrisburg maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(F) Provide for the construction or renovation of Elizabethville maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(G) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 47

Project Allocation

5,000,000

(H) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 48

Project Allocation

5,000,000

(I) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxiii) Delaware County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site N

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxiv) Elk County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxv) Erie County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site L

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site M

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxvi) Fayette County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 12-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxvii) Forrest County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxviii) Franklin County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site G

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxix) Fulton County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site B

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 3

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxx) Greene County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site D

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxi) Huntingdon County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxii) Indiana County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 10-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxiii) Jefferson County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 25

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 26

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxiv) Juniata County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxv) Lackawanna County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 4-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 55

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxvi) Lancaster County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxvii) Lawrence County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 15

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 16

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxviii) Lebanon County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at the eastern training facility

Project Allocation

5,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xxxix) Lehigh County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 5-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xl) Luzerne County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 39

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 53

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 54

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xli) Lycoming County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 3-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlii) McKean County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xliii) Mercer County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site E

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 17

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 18

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xliv) Mifflin County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlv) Monroe County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site F

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 41

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlvi) Montgomery County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 6-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlvii) Montour County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 35

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 36

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlviii) Northampton County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(xlix) Northumberland County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(l) Perry County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(li) Philadelphia County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lii) Pike County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site K

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot, and sewage plant upgrades, at roadside rest area - Site 61

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 62

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(liii) Potter County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(liv) Schuylkill County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lv) Snyder County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lvi) Somerset County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lvii) Sullivan County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lviii) Susquehanna County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site H

Project Allocation

5,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 56

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition, or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lix) Tioga County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site T

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lx) Union County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxi) Venango County

(A) Renovation and expansion for code compliance, upgraded building systems, improved program requirements and energy efficiency at District Office 1-0

Project Allocation

10,000,000

(B) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 21

Project Allocation

5,000,000

(D) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at roadside rest area - Site 22

Project Allocation

5,000,000

(E) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxii) Warren County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxiii) Washington County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Provide for the construction or renovation of West Brownsville maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(C) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site A

Project Allocation

5,000,000

(D) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxiv) Wayne County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxv) Westmoreland County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxvi) Wyoming County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000

(lxvii) York County

(A) Provide for the construction or renovation of maintenance facility, including site acquisition and development, design and construction of buildings, systems and utility work

Project Allocation

7,000,000

(B) Renovation, expansion or replacement, including land acquisition, roof replacement, building systems, sidewalks, curbing, steps, parking lot and sewage plant upgrades, at welcome center - Site J

Project Allocation

5,000,000

(C) Construction of a new stockpile facility with land acquisition or renovation of an existing facility to meet code and program requirements

Project Allocation

5,000,000