Section 7. Itemization of flood control projects.

Additional capital projects in the category of flood control projects to be constructed by the Department of Environmental Protection, its successors or assigns, and to be financed by the incurring of debt are hereby itemized, together with their respective estimated costs, as follows:

Project

Total Project

Allocation

(1) Department of Environmental Protection

(i) Allegheny County

(A) Construction, infrastructure and other related costs for a storm water line replacement, including storm sewer, manhole and replacement of a failing inlet, to reduce excessive runoff and flooding in Ben Avon Heights Borough

Project Allocation

50,000

(B) Construction, infrastructure and other related costs for drainage improvement and flood control on Harmony Road in Ohio Township, including installation of inlet boxes, cast iron frames, safety grates, culvert piping, outlets, earth work and wall erosion and sediment control

Project Allocation

158,000

(C) Construction, redevelopment and other related costs for a detention pond retrofit at Northridge, including earth work, maintenance and protection of traffic, culvert pipe installation, outlet removal and removal and replacement, erosion and sediment control, fencing and landscape restoration in Ohio Township

Project Allocation

169,000

(D) Construction, infrastructure and other related costs for a pollutant reduction plan project, including storm water detention pond improvements and sediment reduction in South Fayette Township

Project Allocation

250,000

(E) Construction, rehabilitation and other related costs for the Werner Avenue Slope Stabilization project, including a new retaining wall, roadway improvements and installation of storm sewer and catch basins for erosion prevention in Bridgeville Borough

Project Allocation

700,000

(F) Construction, infrastructure and other related costs for detention pond construction to alleviate flooding in the Broughton area of South Park Township

Project Allocation

900,000

(G) Construction, infrastructure, rehabilitation and other related costs for a flood mitigation project in Oakdale Borough

Project Allocation

1,000,000

(H) Construction, infrastructure, rehabilitation and other related costs for Phase I of the McLaughlin Run Flood Control project, including construction of a levee with pumps along Carol Avenue and replacement of the Commercial Street culverts in Bridgeville Borough

Project Allocation

5,600,000

(ii) Bucks County

(A) Core Creek Dam flood control - rehabilitation

Project Allocation

1,700,000

(B) Acquisition, rehabilitation, infrastructure, flood mitigation and related costs for a riverfront redevelopment project

Project Allocation

10,000,000

(C) Construction, acquisition, infrastructure, renovation, rehabilitation and other costs related to waterway bank restoration projects and storm water management projects

Project Allocation

5,000,000

(iii) Crawford County

(A) Rainbow Dam flood control - rehabilitation

Project Allocation

3,800,000

(iii.1) Delaware County

(A) Construction and other costs relating to the South Wayne Avenue Flood Reduction Project in Radnor Township

Project Allocation

1,000,000

(iii.2) Lackawanna County

(A) Acquisition, construction, infrastructure and other related costs to mitigate flooding

Project Allocation

10,000,000

(iv) Luzerne County

(A) Construction, infrastructure, rehabilitation and other related costs for the West Pittston flood mitigation levee project

Project Allocation

15,000,000

(B) Acquisition, construction, infrastructure and other related costs to mitigate flooding

Project Allocation

5,000,000

(v) Lycoming County

(A) Construction, infrastructure and other related costs for the Lawshee Run culvert replacement project in Jersey Shore Borough

Project Allocation

15,000,000

(B) Acquisition, site development, construction, infrastructure, redevelopment, equipment, abatement of hazardous materials and other related costs for a flood control project

Project Allocation

20,000,000

(v.1) Monroe County

(A) Acquisition, construction, infrastructure and other related costs to mitigate flooding

Project Allocation

5,000,000

(vi) Montgomery County

(A) Construction, infrastructure and other related costs for a storm water arch rehabilitation project located under 1200 High Street in the Borough of Pottstown

Project Allocation

750,000

(B) Construction, infrastructure and other related costs for a storm water arch rehabilitation project in the Borough of Pottstown

Project Allocation

3,750,000

(vii) Pike County

(A) Kintz Creek Dam flood control - rehabilitation

Project Allocation

2,300,000

(viii) Tioga County

(A) Hamilton Dam flood control - rehabilitation

Project Allocation

1,800,000

(ix) Washington County

(A) Construction, infrastructure and other related costs for a storm water management and backflow prevention project in West Brownsville Borough

Project Allocation

500,000

(B) Construction, infrastructure, rehabilitation and other related costs for a two-stage flood plain restoration project located along Tributary 1 of Catfish Creek upstream of SR 18 in the City of Washington, including realignment of the stream, recreation of historical floodplain, stabilization of existing incised banks and natural plan stabilization

Project Allocation

700,000

(x) York County

(A) Acquisition, demolition, site preparation, environmental remediation, infrastructure, construction and other related costs for rehabilitation of Silver Lake

Project Allocation

2,000,000