Priority of lien over other liens

Act 40 of 1872, § 4, under WAGE PREFERENCE LAW.

Act 40 of 1872, § 4

Section 4. Priority of lien over other liens

No mortgage, or other instrument by which a lien is hereafter credited, shall operate to impair or postpone the lien and preference given and secured to the wages and moneys mentioned in the first section of this act: Provided, That no lien of mortgage or judgment entered before such labor is performed, shall be effected or impaired thereby. 1872, April 9, P.L. 47, Sec. 4.