Itemization of flood control projects

Act 41 of 2008, § 7, under CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 2007-2008 - ENACTMENT.

Act 41 of 2008, § 7

Section 7. Itemization of flood control projects.

Additional capital projects in the category of flood control projects to be constructed by the Department of Environmental Protection, its successors or assigns and to be financed by the incurring of debt are hereby itemized, together with their respective estimated costs, as follows:

Total

Project

Project

Allocation

(1) Department of Environmental Protection

(i) Allegheny County

(A) Construction, infrastructure, abatement of hazardous materials and other costs related to the North Hills flood prevention project

2,000,000

(B) Construction, infrastructure and other related costs for the Penn Hills stormwater management project

1,200,000

(C) Additional funds for the Girtys Run Federal Flood Protection Project in the Borough of Millvale and Shaler and Ross Townships

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(D) Additional funds for the Pine Creek Federal Flood Protection Project in Etna Borough and Shaler Township

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(E) Additional funds for the Saw Mill Run Federal Flood Protection Project in the City of Pittsburgh

3,600,000

(Base Project Allocation - $3,000,000)

(Design and Contingencies - $600,000)

(F) Pine Creek watershed, stormwater management and flood protection for Lower Allison Park

4,623,000

(i.1) Blair County

(A) Construction, infrastructure and other related costs for the Mill Run Rehabilitation Project

76,000

(i.2) Carbon County

(A) Construction, infrastructure and other related costs for the Towamensing Trails Dam rehabilitation project

1,250,000

(ii) Chester County

(A) Construction, infrastructure and other related costs for the Business 30 Flood Control Project

900,000

(ii.1) Clearfield County

(A) Construction, infrastructure and other related costs for flood protection projects in Chester Hill Borough

3,000,000

(B) Construction, infrastructure and other related costs for flood protection projects in Coalport Borough

300,000

(ii.2) Clinton County

(A) Pine Creek Township, construction, redevelopment and other costs related to the Chatham Run levee project

7,500,000

(iii) Columbia County

(A) Fishing Creek Flood Control Project, including gravel bar removal

1,000,000

(iv) Crawford County

(A) Conneautville Dam rehabilitation

750,000

(iv.1) Derry Township

(A) Stormwater control project in Derry Township

8,000,000

(B) Stormwater control project in Lower Swatara Township

6,000,000

(iv.2) Indiana County

(A) Acquisition and construction of a flood control project designed by the Army Corps of Engineers

2,000,000

(iv.3) Lackawanna County

(A) Additional funds for the Greenridge portion of the Scranton Federal Flood Protection Project in the City of Scranton

6,000,000

(Base Project Allocation - $5,000,000)

(Design and Contingencies - $1,000,000)

(v) Monroe County

(A) Additional funds to refurbish Brady's Lake Dam

3,600,000

(B) Flood control project in Paradise Township

1,500,000

(v.1) Montgomery County

(A) Construction, infrastructure and other related costs for the Jenkintown flood control project

1,200,000

(vi) Northumberland County

(A) Construction, infrastructure and other related costs for the Susquehanna River Clearing and Grubbing Project

200,000

(B) Construction, infrastructure and other related costs for the Reagan Street Underpass Flooding Abatement Project

2,200,000

(C) Shoreline stabilization for flood control system in Sunbury Borough

750,000

(vi.1) Potter County

(A) Repair and rehabilitation of the North Fork Dam

2,000,000

(vii) Schuylkill County

(A) Repairs to the two Owl Creek dams, including breast repairs and spillway construction in Borough of Tamaqua

3,000,000

(B) Reconstruction of Wabash Creek storm water tunnel and diversion system in Borough of Tamaqua

5,000,000

(C) Construction, infrastructure and other costs related to Klingertown flood control

8,100,000

(viii) Somerset County

(A) Construction, infrastructure and other related costs for the East Main Street flood protection project

5,000,000

(ix) Washington County

(A) Reconstruction and stabilization of Canonsburg Dam, including spillway and breast works

8,000,000

(x) Westmoreland County

(A) Construction and other related costs for a flood control project at Little Puketa Creek on State Route 56, including creek basin dredging and bank stabilization

250,000