Section 7. Itemization of redevelopment assistance projects.
Additional capital projects in the category of redevelopment assistance projects for capital grants by the Department of Community Affairs, its successors or assigns, authorized under the provisions of the act of May 20, 1949 (P.L.1633, No.493), known as the Housing and Redevelopment Assistance Law, and to be financed by the incurring of debt are hereby itemized, together with their estimated financial costs, as follows:
Total
Project
Project
Allocation
(1) Allegheny County
(i) City of Pittsburgh
(A) Acquisition and renovation of five additional properties at 500 Sampsonia Way for the Mattress Factory Art Institution
500,000
(Base Project Allocation - $500,000)
(B) Feasibility study to evaluate construction of moving sidewalk to connect the City of Pittsburgh with the Northside
500,000
(Design and Contingencies - $500,000)
(C) Lawrenceville Industrial Park Project - Phase II site development
3,000,000
(Base Project Allocation - $3,000,000)
(D) Fifth and Forbes, infrastructure and public space improvements
9,000,000
(Base Project Allocation - $9,000,000)
(E) Women's Research Institute, restoration of land and renovation and rehabilitation of buildings
5,000,000
(F) Carnegie Museum of Art for the Andy Warhol Museum
6,000,000
(G) Redevelopment of the Bank Center Building into a "Library Center" in downtown Pittsburgh
1,000,000
(H) Cultural District Development - Phase II
17,750,000
(I) Pittsburgh Regional History Center
7,000,000
(J) Federal/North Development
3,000,000
(K) Renovation and reconstruction of Pittsburgh Ballet Theatre
1,000,000
(L) Redevelopment of approximately 8.31 acres of riverfront property by South Side Riverfront Development
3,000,000
(M) Keystone Commons Development
2,100,000
(N) Rehabilitation and expansion of community center in Homewood-Brushton
1,800,000
(O) Regent Square Theatre Project
200,000
(P) Construction of multipurpose community center serving Lincoln, Lemington, Larimer and Belmar
3,000,000
(Q) Pittsburgh Children's Museum, renovations and building expansion
5,000,000
(R) Restoration, rehabilitation and construct parking for New Granada Theatre
5,000,000
(S) Pittsburgh Zoo, construction of an education complex
250,000
(Base Project Allocation - $250,000)
(T) Phipps Conservatory, renovation of the Palm Court
150,000
(Base Project Allocation - $150,000)
(U) National Aviary, renovations
100,000
(Base Project Allocation - $100,000)
(V) Boys and Girls Club of Western Pennsylvania, renovation and construction of juvenile justice and youth development facilities
2,500,000
(Base Project Allocation - $2,500,000)
(W) Rehabilitation and expansion of the MacIntosh and Hempfield Building for the Pittsburgh Filmmakers
500,000
(ii) City of Duquesne and City of McKeesport
(A) Center City of Duquesne/McKeesport Industrial Center
3,485,000
(iii) Moon Township
(A) Conversion of the abandoned terminal at the Greater Pittsburgh International Airport into an air and space museum
10,000,000
(iv) Borough of Wilkinsburg
(A) Construction of multipurpose center serving Wilkinsburg
3,000,000
(v) City of McKeesport
(A) McKees Point Marina and Park
2,600,000
(vi) Borough of Braddock
(A) For additional construction of Braddock Industrial Park
1,200,000
(vii) Harrison Township
(A) Natrona River and housing development project
2,000,000
(viii) Rankin Borough
(A) Rankin Marina and fishing docks on Monongahela River
500,000
(ix) Swissvale, Rankin, Munhall and Homestead Boroughs
(A) Steel Industry Heritage Center
18,900,000
(x) Millvale Borough
(A) Replacement of potable water storage facility
275,000
(xi) Aspinwall Borough
(A) Construction of potable water well for public consumption
125,000
(xii) County of Allegheny
(A) Additional funds for Allegheny River Boulevard
300,000
(2) Bedford County
(i) Bedford County Center
(A) Construct facility
1,000,000
(3) Berks County
(i) City of Reading
(A) Repair and renovation of Reading Public Museum
1,700,000
(ii) Bern Township
(A) Construction of new county juvenile detention facility
3,500,000
(iii) Berks County
(A) Develop Allegheny Aqueduct Historical Park
125,000
(4) Blair County
(i) Allegheny Ridge State Heritage Park
(A) Altoona Railroaders Memorial Museum
7,000,000
(B) Altoona Discovery Center
4,000,000
(C) Fourteenth Street Park, Altoona
1,500,000
(D) Dudley House, Altoona
500,000
(E) Flatiron Building Visitor Center, Brownsville
1,000,000
(F) Braemer Cottage, Cresson
500,000
(G) Hollidaysburg Canal Park/Gateway
3,000,000
(H) Johnstown Discovery Center
4,000,000
(I) Wagner-Ritter House, Johnstown
500,000
(J) National Road Toll Houses
3,000,000
(K) Portage Gateway Center
1,000,000
(L) Scalp Level Power House
8,000,000
(M) Scalp Level Miner's House
200,000
(N) Arcadia Theater, Windber
3,500,000
(5) Bucks County
(i) Middletown Township
(A) Public Works Department, building addition
121,000
(B) Public Works substation and operation site
169,000
(C) Public Works Department, underground storage tank replacements
320,000
(D) Police Department building renovations
130,000
(E) Fire companies apparatus replacement and refurbishment plan
1,700,000
(F) Development of community park in northern area of township
2,000,000
(G) Beechwood Community Park development
250,000
(H) Twin Oaks Recreational Facility rehabilitation
200,000
(I) Mill Creek and Queen Anne Creek drainage improvements
2,207,000
(J) Langhorne Gables area drainage improvements
451,000
(ii) Bristol Township
(A) Improvements to drainage and road surface in township
2,000,000
(iii) Langhorne Borough
(A) Expansion of Borough Hall/Fire House
200,000
(6) Butler County
(i) Community Development Corporation
(A) Construction of a youth athletic center
1,500,000
(ii) County of Butler
(A) Improvements to Alameda Park, consisting of road construction and rehabilitation of grounds, riverfront and facilities
1,000,000
(iii) Chicora Borough and Donegal Township
(A) Joint sewer project
2,000,000
(7) Cambria County
(i) Johnstown
(A) Renovations to Johnstown Point Stadium
1,300,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $300,000)
(ii) County of Cambria
(A) Construction of a collapsible dam on Stoneycreek River
3,000,000
(8) Cameron County
(i) Emporium Borough/Shippen Township
(A) Sewage treatment plant improvements
1,500,000
(9) Clearfield County
(i) Philipsburg
(A) Improvements to Philipsburg Area Hospital to provide for an acute-care nursing home
2,000,000
(ii) Cooper Township
(A) Redevelopment of Severin Church site
1,000,000
(iii) Morris Township
(A) Department of Environmental Resources mandated improvements to water distribution system
1,000,000
(iv) Graham Township
(A) Infrastructure and water system improvements
1,000,000
(v) City of DuBois
(A) Replacement/renovation of south side sewer interceptor
900,000
(10) Crawford County
(i) Crawford County Fairgrounds
(A) Restoration of grounds
200,000
(ii) Meadville
(A) Demolition, restoration, reconstruction of dilapidated housing
1,150,000
(iii) Titusville
(A) Demolition, restoration, reconstruction of dilapidated housing
1,150,000
(iv) Spartansburg Borough
(A) Rails to Trails Project
1,000,000
(11) Elk County
(i) Benzinger Township
(A) Construction of sewage system
1,100,000
(B) Construction of solids-handling facility for water treatment plant
500,000
(ii) Fox Township
(A) Sewer extension to Fairview subdivision
200,000
(B) Upgrade sewage treatment plant for removal of toxic metals
700,000
(C) Expansion of sewage treatment plant
800,000
(D) Sewer line extension to trailer park
200,000
(iii) Highland Township
(A) Sewage collection and treatment plant for James City
800,000
(iv) Jay Township Water Authority
(A) Renovations to Jay Township water system
2,000,000
(B) Water storage tank construction in Village of Weedville
250,000
(C) Engineering study for backup source water system
500,000
(v) Jones Township
(A) Sanitary sewer collection system from Wilcox to Johnsonburg Borough facility
3,800,000
(vi) Johnsonburg Municipal Authority
(A) Construction of Third Avenue reservoir tank No. 2
400,000
(B) Construction of water storage reservoir and Silver Creek water line extension
900,000
(12) Erie County
(i) Corry Redevelopment Authority
(A) Acquisition of abandoned industrial building for multitenant facility
1,000,000
(Base Project Allocation - $1,000,000)
(13) Fayette County
(i) Brownsville
(A) Architectural work and construction on Flatiron Building
375,000
(Base Project Allocation - $375,000)
(14) Forest County
(i) Tionesta Township
(A) Acquisition of 25 acres, including 3 commercial buildings, for creation of an industrial park
243,000
(Base Project Allocation - $243,000)
(ii) Tionesta Borough
(A) Acquisition of 11 acres for an incubator project
395,000
(Base Project Allocation - $395,000)
(iii) Jenks Township
(A) Acquisition of 90 acres for an industrial park
100,000
(Base Project Allocation - $100,000)
(15) Greene County
(i) Rices Landing Borough
(A) Planning, design and construction of W. A. Young Machine Shop
250,000
(Base Project Allocation - $250,000)
(16) Jefferson County
(i) Brockway Borough
(A) Reline existing sanitary sewer lines along Green Way
86,000
(B) Installation of an elevator in Toby Terrace apartment building
55,000
(C) Improvements to roadway to Brockway Industrial Park
200,000
(ii) Brookville Borough
(A) Restoration of Jefferson County Courthouse and acquisition of annex
700,000
(iii) Corsica Borough
(A) Water line improvements/access road
550,000
(iv) Pine Creek Township
(A) Restoration of Jefferson County Service Center
450,000
(B) Establish incubator/multitenant building
750,000
(v) Snyder Township
(A) Construction of sanitary sewer lines along Kearney Road, Broad Street and Arch Street
243,000
(17) Lackawanna County
(i) Civic center and hotel complex
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
55,000,000
(Base Project Allocation - $50,000,000)
(Design and Contingencies - $5,000,000)
(ii) Heritage Valley Visitors Center
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
3,960,000
(Base Project Allocation - $3,600,000)
(Design and Contingencies - $360,000)
(iii) Heritage Valley Trolley Museum
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
3,960,000
(Base Project Allocation - $3,600,000)
(Design and Contingencies - $360,000)
(iv) Northeast Environmental Reclamation and Renewal Facility
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
4,400,000
(Base Project Allocation - $4,000,000)
(Design and Contingencies - $400,000)
(v) Lackawanna Coal Mine
(A) Expenditures, including, but not limited to, renovation, rehabilitation and restoration of land and buildings at McDade Park
4,400,000
(Base Project Allocation - $4,000,000)
(Design and Contingencies - $400,000)
(vi) Slocum Hollow Park Project
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
5,500,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $500,000)
(vii) Lackawanna County Park System
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs, renovation, rehabilitation and restoration of land and/or building within the Lackawanna County Park System
5,500,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $500,000)
(viii) Montage Trolley Excursion Project
(A) Expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs, renovation, rehabilitation and restoration of land, tunnels, bridges, trolley track and buildings
6,600,000
(Base Project Allocation - $6,000,000)
(Design and Contingencies - $600,000)
(ix) Lackawanna River Corridor Association
(A) Greenway feasibility study
3,300,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $300,000)
(x) City of Scranton
(A) Jason Miller Public Theater expenditures, including, but not limited to, property and land acquisition, design, construction and start-up costs
3,300,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $300,000)
(B) Scranton Park System expenditures, including, but not limited to, design, construction, renovation and restoration to parks and museums within the City of Scranton
7,700,000
(Base Project Allocation - $7,000,000)
(Design and Contingencies - $700,000)
(xi) Lackawanna County Prison
(A) Including, but not limited to, design, construction, rehabilitation and expansion of county prison
5,500,000
(Base Project Allocation - $5,000,000)
(Design and Contingencies - $500,000)
(xii) Dalton Borough
(A) Repair retaining wall on Lily Lake Road
300,000
(Base Project Allocation - $300,000)
(xiii) Newton Township
(A) Drain pond and reconstruct dam on Ford's Pond Road
100,000
(Base Project Allocation - $100,000)
(xiv) South Abington Township
(A) Expand railroad culvert on Shady Lane Road in Chinchilla
3,000,000
(Base Project Allocation - $3,000,000)
(B) Stream maintenance project on Leggett's Creek in Chinchilla
2,000,000
(Base Project Allocation - $2,000,000)
(18) Lancaster County
(i) City of Lancaster
(A) Rehabilitation of the historic Fulton Opera House
3,000,000
(19) Luzerne County
(i) City of Wilkes-Barre
(A) ((A) repealed July 8, 1994, P.L.444, No.74)
(B) Acquisition, renovation, rehabilitation and restoration of land and buildings for the Wyoming Valley Regional Food Bank
1,000,000
(ii) City of Pittston
(A) Acquisition and development of Riverfront/downtown property
6,500,000
(B) Construction of a downtown parking garage
2,800,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $300,000)
(iii) Hughestown Borough
(A) Indoor/covered ice skating rink
1,500,000
(iv) Avoca Borough
(A) Development of Avoca Flats Park
1,000,000
(v) Dupont Borough
(A) Development of Borough Park
800,000
(vi) Jenkins Township
(A) Development/improvements to Spadi Park
1,000,000
(vii) Duryea Borough
(A) Development of baseball field and tennis/basketball courts
1,200,000
(viii) Yatesville Borough
(A) Recreation improvements
750,000
(ix) Pittston Township
(A) Acquisition of land and park development in Suscon
800,000
(B) Recreational park
100,000
(x) City of Nanticoke
(A) Development of Industrial Park of Greater Nanticoke
2,500,000
(B) Reconstruct sidewalks to provide accessibility ramps
30,000
(C) Demolition or rehabilitation of low-income housing
1,370,000
(xi) Swoyersville Borough
(A) Construction of senior citizens' recreation building
350,000
(20) Mercer County
(i) Springfield Township
(A) Improvements to water system
898,000
(Base Project Allocation - $690,000)
(Land Allocation - $104,000)
(Design and Contingencies - $104,000)
(21) Monroe County
(i) Borough of Mount Pocono
(A) Extension of sewer line
275,000
(B) Reconstruction of central water distribution system
5,350,000
(ii) County of Monroe
(A) Construction of countywide fire training school and center
965,000
(22) ((22) repealed July 8, 1994, P.L.444, No.74)
(23) Philadelphia County
(i) City of Philadelphia
(A) North Broad Street streetscape
3,150,000
(B) South Broad Street streetscape
1,400,000
(C) Renovations and improvements to the Port of History building at Penn's Landing in Philadelphia so that the building can serve as the home of the Philadelphia Maritime Museum
2,200,000
(D) Schuylkill Waterfront Economic Rehabilitation
14,026,000
(E) Rehabilitation and improvements to the Urban Education Development Research and Retreat Center
3,500,000
(F) Renovation of the Pennsylvania Academy of the Fine Arts
7,500,000
(G) Renovation and rehabilitation of the International House of Philadelphia
3,679,000
(H) Renovation and expansion of the Philadelphia Dance Company
2,100,000
(I) Renovation and expansion of the Movement Theatre International into the Performing Arts Center
3,500,000
(J) Americans with Disabilities Accessibility renovations to the Annenberg Center for the Performing Arts
1,000,000
(K) Renovations, including Americans with Disabilities Accessibility to the Harrison Auditorium, University Museum of Archaeology and Anthropology
2,916,000
(L) Dredge Schuylkill River between Fairmount Dam and Falls Bridge
15,000,000
(M) Recreation Department to be allocated as follows: outdoor lighting - 350,000; roof repairs - 125,000; heating systems and controls - 125,000; outdoor basketball and tennis courts - 500,000; site improvements - 500,000; swimming pools - 250,000; replacement of Pepper Middle School - 250,000; reconstruction of Francis Myers Recreational Center - 560,000; replacement of L. Young Recreational Center - 950,000
3,610,000
(N) Construction of the Ogontz Community Public Library
1,731,000
(O) Furniture and equipment for library
300,000
(P) Rehabilitation of 150 homes for habitation
700,000
(Q) Renovations of the Lonnie Young Recreation Center
1,900,000
(R) Conversion of Fairmont Park Stable Building into the Cobbs Creek Community Environmental Education Center
540,000
(S) Construction of education building and amphitheatre at the Philadelphia Zoo
5,380,000
(24) Potter County
(i) Austin Borough
(A) Construction of complete sewer system in Austin Borough
2,750,000
(ii) Coudersport Borough
(A) Demolition, excavation and removal of dilapidated structure, tannery vats and abandoned industrial structures in the industrial park
630,000
(B) Upgrade and expansion of Coudersport Borough sewer system; elimination of infiltration inflow and plant expansion
550,000
(C) Extension of borough flood control to borough limits
4,500,000
(iii) Genesee Village
(A) Repair, replacement and expansion of water system, including fire protection and potable water line distribution
475,000
(25) Venango County
(i) Sandy Creek Township
(A) Acquisition of 11-acre tract to supplement Sandy Creek Industrial Park
200,000
(B) Extension of water lines to new 11-acre tract
10,000
(C) Construction of access road through 11-acre tract
50,000
(26) Warren County
(i) City of Warren
(A) Acquisition, renovation and site preparation of former Warren Components building for economic opportunities
200,000
(ii) Pleasant Township
(A) Provide a rail spur to former Phillips Building at the Warren Industrial Complex
100,000
(27) Washington County
(i) Northwest Economic Development Project
(A) Installation of water line
1,000,000
(ii) Marianna Borough
(A) Engineering and design and correction work for slide problem
200,000
(iii) Carroll Township and Monongahela City
(A) Sewage treatment system
2,000,000
(iv) Smith Township
(A) Eliminate acid mine drainage problem
750,000
(28) Westmoreland County
(i) Westmoreland Trust
(A) Cultural district redevelopment, including the renovation and rehabilitation of Greensburg Train Station and the Palace Theatre
5,100,000
(ii) Rostraver
(A) Acquisition and/or construction of a combination public library and senior citizen center
1,300,000
(iii) Hempfield Township
(A) Install new water line extension to Stone Church Hill
180,000
(iv) Mt. Pleasant Township
(A) Install new water line to the junction of Routes 819 and 981
200,000
(v) Ligonier Township
(A) Replace water lines in Loyalhanna Cottages
150,000
(vi) Seward Borough
(A) Replace existing water lines
220,000
(vii) North Irwin Borough
(A) Town Hall renovation
150,000
(viii) North Huntingdon Township
(A) Winchester Road main water line extension
145,000
(B) Murrysville Road main water line extension
116,000
(C) Elevation of Winchester Road and Murrysville Road
210,000
(29) York County
(i) City of York
(A) Construction of new indoor Ice Arena/Convention Center at Memorial Park
1,200,000
(Base Project Allocation - $1,200,000)
(B) Construction of George Street Revitalization Corridor
1,642,000
(Base Project Allocation - $1,642,000)
(ii) County of York, Rails to Trails Project
(A) Trail improvements, Maryland Line to Hanover Junction
500,000
(B) Trail improvements, Hanover Junction to York
800,000
(C) Station renovations at Hanover Junction
150,000
(D) Station renovations at New Freedom
150,000
(E) Relocation and renovation of Railroad House
100,000