Centre County

Act 53 of 1999, § 18, under HIGHWAY-RAILROAD AND HIGHWAY BRIDGE CAPITAL BUDGET SUPPLEMENTAL ACT FOR 1999-2000.

Act 53 of 1999, § 18

Section 18. Centre County.

(a) Local Bridges

(1) Greene Township, T-350, Stover Road Bridge, Bridge Replacement

230,000

(Base Construction Allocation - $180,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(2) Howard Township, T-398 over Bullit Run, Bridge Rehabilitation

11,000

(Base Construction Allocation - $9,000)

(Design and Contingencies - $2,000)

(3) Halfmoon Township, T-307 over Loveville Creek, Bridge Replacement

21,000

(Base Construction Allocation - $19,000)

(Design and Contingencies - $2,000)

(4) Penn Township, T-839 over Pine Creek, Bridge Rehabilitation

80,000

(Base Construction Allocation - $60,000)

(Design and Contingencies - $20,000)

(5) Port Matilda Borough, Pedestrian Bridge over Bald Eagle Creek, Bridge Rehabilitation

200,000

(Base Construction Allocation - $175,000)

(Design and Contingencies - $25,000)

(6) Spring Township, T-367, Hill Road Bridge, Bridge Replacement

200,000

(Base Construction Allocation - $150,000)

(Land Allocation - $10,000)

(Design and Contingencies - $40,000)

(7) Taylor Township, T-308, McMonagle Road over Sparrow Run, Bridge Replacement

330,000

(Base Construction Allocation - $275,000)

(Land Allocation - $5,000)

(Design and Contingencies - $50,000)

(8) Rush Township, Six Mile Road Bridge over Six Mile Run, Bridge Replacement

155,000

(Base Construction Allocation - $137,000)

(Land Allocation - $5,000)

(Design and Contingencies - $13,000)

(9) Taylor Township, T-300, Big Fill Run Bridge over Big Fill Run, Bridge Replacement

310,000

(Base Construction Allocation - $200,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(10) Taylor Township, T-305, Bald Eagle Creek Bridge over Bald Eagle Creek, Bridge Replacement

360,000

(Base Construction Allocation - $250,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(11) Ferguson Township, T-307, West Gatesburg Road Bridge, Bridge Replacement

100,000

(Base Construction Allocation - $89,000)

(Design and Contingencies - $11,000)

(12) Ferguson Township, T-703, Scott Road Bridge, Bridge Rehabilitation

90,000

(Base Construction Allocation - $75,000)

(Design and Contingencies - $15,000)

(b) State Bridges

(1) SR 0080, I-80 Viaduct over Moshannon Creek and Conrail, Rush Township, Bridge Rehabilitation

14,510,000

(Base Construction Allocation - $13,210,000)

(Design and Contingencies - $1,300,000)

(2) SR 1002, Marsh Creek Bridge over Marsh Creek, Boggs Township, Bridge Replacement

760,000

(Base Construction Allocation - $630,000)

(Land Allocation - $20,000)

(Design and Contingencies - $110,000)

(3) SR 1002, Little Marsh Creek Bridge over Little Marsh Creek, Curtin Township, Bridge Replacement

700,000

(Base Construction Allocation - $600,000)

(Land Allocation - $20,000)

(Design and Contingencies - $80,000)

(4) SR 2012, Penns Creek Bridge Northwest of the Village of Spring Mills, Gregg Township, Bridge Replacement

470,000

(Base Construction Allocation - $360,000)

(Land Allocation - $20,000)

(Design and Contingencies - $90,000)

(5) SR 0220, SR 0220 over Laurel Run, Port Matilda Borough, Bridge Rehabilitation

450,000

(Base Construction Allocation - $400,000)

(Design and Contingencies - $50,000)

(6) SR 0053, Moshannon Creek Bridge over Moshannon Creek, Philipsburg Borough, Bridge Replacement

2,250,000

(Base Construction Allocation - $2,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $200,000)

(7) SR 0144, Bald Eagle Creek Bridge over Bald Eagle Creek, Boggs Township, Bridge Replacement

1,210,000

(Base Construction Allocation - $950,000)

(Land Allocation - $10,000)

(Design and Contingencies - $250,000)

(8) SR 0879, Susquehanna Bridge over West Branch of Susquehanna River, Burnside Township, Bridge Replacement

3,700,000

(Base Construction Allocation - $3,200,000)

(Land Allocation - $100,000)

(Design and Contingencies - $400,000)

(9) SR 0970, Bridge over Moshannon Creek, Rush Township, Bridge Painting

310,000

(Base Construction Allocation - $300,000)

(Design and Contingencies - $10,000)

(10) SR 1005, Nittany Creek Bridge over Nittany Creek, Marion Township, Bridge Replacement

260,000

(Base Construction Allocation - $150,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(11) SR 2007, Spruce Creek Bridge over Spruce Creek, Gregg Township, Bridge Replacement

260,000

(Base Construction Allocation - $150,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(12) SR 2011, Penns Creek Bridge over Penns Creek, Penn Township, Bridge Replacement

1,040,000

(Base Construction Allocation - $830,000)

(Land Allocation - $10,000)

(Design and Contingencies - $200,000)

(13) SR 2012, Spring Bridge over Penns Creek, Gregg Township, Bridge Replacement

670,000

(Base Construction Allocation - $500,000)

(Land Allocation - $20,000)

(Design and Contingencies - $150,000)

(14) SR 2018, Mill Race Bridge over Mill Race, Penn Township, Bridge Painting

8,000

(Base Construction Allocation - $7,000)

(Design and Contingencies - $1,000)

(15) SR 3027, Trout Run Bridge over Trout Run, Rush Township, Bridge Replacement

270,000

(Base Construction Allocation - $160,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(16) SR 3034, Cold Stream Run Bridge over Cold Stream Run, Rush Township, Bridge Replacement

746,000

(Base Construction Allocation - $576,000)

(Land Allocation - $20,000)

(Design and Contingencies - $150,000)

(17) SR 4004, Wallace Run Bridge over Wallace Run, Boggs Township, Bridge Replacement

455,000

(Base Construction Allocation - $345,000)

(Land Allocation - $10,000)

(Design and Contingencies - $100,000)

(18) SR 4005, Bridge over I-80, Snow Shoe Township, Bridge Replacement

2,400,000

(Base Construction Allocation - $2,000,000)

(Land Allocation - $100,000)

(Design and Contingencies - $300,000)

(19) SR 4006, Moshannon Creek Bridge over Moshannon Creek, Rush Township, Bridge Replacement

1,000,000

(Base Construction Allocation - $780,000)

(Land Allocation - $20,000)

(Design and Contingencies - $200,000)

(20) SR 0504, Black Moshannon Creek Bridge, Moshannon State Park, Rush Township, Bridge Rehabilitation

13,000

(Base Construction Allocation - $11,000)

(Design and Contingencies - $2,000)

(21) SR 0550, Bridge over Half Moon Creek, Halfmoon Township, Bridge Replacement

230,000

(Base Construction Allocation - $200,000)

(Land Allocation - $10,000)

(Design and Contingencies - $20,000)

(22) SR 0504, Black Moshannon Creek Bridge in Moshannon State Park, Rush Township, Bridge Replacement

540,000

(Base Construction Allocation - $410,000)

(Land Allocation - $40,000)

(Design and Contingencies - $90,000)

(23) SR 0026, Bridge Overpass, over NBER Railroad, Spring Township, New Bridge Construction

1,150,000

(Base Construction Allocation - $1,000,000)

(Land Allocation - $50,000)

(Design and Contingencies - $100,000)

(24) SR 3026, Bridge on T-965, Tadpole Road, Ferguson Township, Bridge Replacement

105,000

(Base Construction Allocation - $90,000)

(Design and Contingencies - $15,000)

(25) SR 3013, Bridge on T-966, Marengo Road, Ferguson Township, Bridge Replacement

105,000

(Base Construction Allocation - $90,000)

(Design and Contingencies - $15,000)