Section 301. Adams County.
Projects are as follows:
(1) SR 94 and SR 1019, Realignment of SR 94 and SR 1029, Berlin Road Intersection, Hamilton Township
4,200,000
(Base Project Allocation - $3,000,000)
(Land Allocation - $600,000)
(Design and Contingencies - $600,000)
(2) SR 234, Widening, Safety Improvements and Signalization along SR 234 to SR 3001 and SR 3001 to North Oxford Road, Tyrone and Huntington Townships
3,200,000
(Base Project Allocation - $1,750,000)
(Land Allocation - $1,200,000)
(Design and Contingencies - $250,000)
(3) US 15, Construction of Interchange at US 15 and Hunterstown Road, Strabane Township
13,200,000
(Base Project Allocation - $10,100,000)
(Design and Contingencies - $3,100,000)