Section 345. Monroe County.
Projects are as follows:
(1) SR 447, Widening and other Improvements to PA 447 and Brushy Mountain Road, Stroud Township
675,000
(Base Project Allocation - $435,000)
(Land Allocation - $90,000)
(Design and Contingencies - $150,000)
(2) SR 447, Widening and Installation of Southbound Left Turn Lane Approaching Brushy Mountain Road, Northbound Right Turn Lane Approaching Brushy Mountain Road, Northbound Left Turn Lane Approaching the United Steel Driveway, Drainage Improvements, Installation of Traffic Signal and Associated Work
675,000
(Base Project Allocation - $575,000)
(Design and Contingencies - $100,000)
(3) SR 611, Highway Reconstruction, Ramp Reconstruction, Bartonsville Interchange HOP, Stroud Township
3,000,000
(Base Project Allocation - $3,000,000)
(4) SR 611, Highway Intersection Improvements, 5-Point HOP, Mount Pocono Borough
500,000
(Base Project Allocation - $500,000)
(5) SR 80, CCL-115, Including Interchange, Tobyhanna Township
300,000
(Land Allocation - $100,000)
(Design and Contingencies - $200,000)
(6) SR 80, Construction, I-80 Eastbound, 115 to 380 4" Mill and Overlay, Tobyhanna Township
773,000
(Base Project Allocation - $703,000)
(Design and Contingencies - $70,000)
(7) SR 80, Bridge Repairs, I-80, Pocono and Smithfield Townships, Stroudsburg Borough
290,000
(Base Project Allocation - $250,000)
(Design and Contingencies - $40,000)
(8) SR 80, Bridge Repair, Overlay, I-80 Eastbound, I-380 to SR 33, Jackson and Pocono Townships
1,380,000
(Base Project Allocation - $1,080,000)
(Land Allocation - $100,000)
(Design and Contingencies - $200,000)
(9) SR 611, Congested Corridor Improvement Project, 611 CCIP Phase 2, Stroudsburg Borough
260,000
(Base Project Allocation - $200,000)
(Land Allocation - $60,000)
(10) I-80, Upgrades and Improvements
3,750,000
(Base Project Allocation - $3,750,000)