Section 3. Itemization of public improvement projects.
Additional capital projects in the category of public improvement projects to be constructed or acquired by the Department of General Services, its successors or assigns, and to be financed by the incurring of debt, are hereby itemized, together with their respective estimated financial costs, as follows:
Total
Project
Project
Allocation
(1) Department of Corrections
$15,096,000
(i) State Correctional Institution - Cambridge Springs
(A) Life safety code improvements
2,458,000
(Base Project Allocation - $2,048,000)
(Design and Contingencies - $410,000)
(B) Improvements to the water line from the water plant to the existing tank
590,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $90,000)
(C) Construction of a 500,000-gallon water storage tank
367,000
(Base Project Allocation - $250,000)
(Land Allocation - $37,000)
(Design and Contingencies - $80,000)
(D) Replacement of sewer line from the Cambridge Springs Correctional Facility to the sewer plant
575,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $75,000)
(E) Improvements to the water filtration plant
402,000
(Base Project Allocation - $350,000)
(Design and Contingencies - $52,000)
(F) Increase of hydraulic capacity of sewage treatment plant to eliminate discharge into French Creek
978,000
(Base Project Allocation - $850,000)
(Design and Contingencies - $128,000)
(G) Renovate Kosciuszko Hall
4,422,000
(Base Project Allocation - $3,685,000)
(Design and Contingencies - $737,000)
(ii) State Correctional Institution - Clearfield
(A) Construction of access road
2,000,000
(iii) State Correctional Institution - Graterford
(A) Additional funds for DGS 577-24 - new kitchen and dining facilities
2,791,000
(Base Project Allocation - $2,326,000)
(Design and Contingencies - $465,000)
(iv) State Correctional Institution - Waynesburg
(A) Construct perimeter road and expand parking
513,000
(Base Project Allocation - $427,000)
(Design and Contingencies - $86,000)
(2) Department of Education
$560,573,000
(i) Thaddeus Stevens State School of Technology
(A) Renovation of two fire towers
511,000
(Base Project Allocation - $426,000)
(Design and Contingencies - $85,000)
(B) Asbestos removal
868,000
(Base Project Allocation - $868,000)
(ii) The Pennsylvania State University
(A) University Park Campus
(I) Alteration of facilities for ADA compliance - Phase I
20,000,000
(II) Utility Expansion for West Campus Development - Phase I
15,000,000
(III) Waste water system improvements
10,000,000
(IV) Classroom building - Phase II
11,000,000
(V) Renovation of and addition to Ferguson Building
9,000,000
(VI) Academic support services complex - Phase I
16,500,000
(VII) Site Development of West Campus - Phase I
5,000,000
(VIII) Modernization of Sparks Building
5,500,000
(IX) Renovation and addition to Support Services Facilities
7,200,000
(X) Expansion and improvements to Telecommunications Infrastructure
15,800,000
(XI) Construction of Engineering Center - Phase I
36,100,000
(XII) Electrical network, service and standby development
3,100,000
(XIII) Library Depository Facility
10,000,000
(XIV) Renovation of the Animal Diagnostics Laboratory and incinerator
2,000,000
(Base Project Allocation - $1,818,000)
(Design and Contingencies - $182,000)
(B) Allentown Campus
(I) Construction of multipurpose building
2,040,000
(C) Altoona Campus
(I) Construct multistory Classroom Building
4,900,000
(II) Alteration of facilities for ADA compliance
1,400,000
(D) Beaver Campus
(I) Alteration of facilities for ADA compliance
1,100,000
(E) Behrend College, Erie
(I) Alteration of facilities for ADA compliance
1,800,000
(F) Berks Campus
(I) Construct Academic Building
4,600,000
(II) Alteration of facilities for ADA compliance
1,600,000
(G) Capital College, Harrisburg
(I) Renovation to utility systems
12,000,000
(II) Alteration of facilities for ADA compliance
3,200,000
(H) Delaware County Campus
(I) Alteration of facilities for ADA compliance
1,100,000
(I) DuBois Campus
(I) Alteration of facilities for ADA compliance
1,000,000
(J) Fayette Campus
(I) Improvements of utility systems
3,000,000
(II) Alteration of facilities for ADA compliance
1,000,000
(K) Great Valley Center
(I) Addition to building and parking deck
5,200,000
(L) Hazleton Campus
(I) Alteration of facilities for ADA compliance
1,400,000
(II) Construction of maintenance building
1,200,000
(M) Hershey Medical Center
(I) Construction of Nursing Education and Medical Research Facility
18,900,000
(II) Alteration of facilities for ADA compliance - Phase I
1,000,000
(N) McKeesport Campus
(I) Alteration of facilities for ADA compliance
1,200,000
(O) Mont Alto Campus
(I) Renovation of General Studies Building
3,200,000
(II) Alteration of facility for ADA compliance
1,000,000
(P) New Kensington Campus
(I) Alteration of facilities for ADA compliance
1,000,000
(Q) Ogontz Campus
(I) Alteration of facilities for ADA compliance
2,200,000
(II) Renovation of Sutherland and Lares Buildings - Phase II
8,100,000
(R) Schuylkill Campus
(I) Alteration of facility for ADA compliance
1,100,000
(S) Shenango Campus
(I) Alteration of facility for ADA compliance
1,100,000
(II) Construction of multipurpose center
5,000,000
(T) Wilkes-Barre Campus
(I) Alteration of facility for ADA compliance
1,200,000
(U) Worthington Scranton Campus
(I) Alteration of facilities for ADA compliance
1,000,000
(V) York Campus
(I) Construct library addition and auditorium and classroom building
11,900,000
(II) Construct Maintenance Building
1,200,000
(III) Alteration of facilities for ADA compliance
1,200,000
(iii) University of Pittsburgh
(A) All Locations
(I) Renovations and code compliance, including ADA, for State-owned buildings
7,200,000
(II) Replacement of CFC chillers with non-CFC machines
5,000,000
(III) Deferred maintenance for buildings and building systems of State-owned buildings
7,000,000
(IV) Replace and upgrade electrical systems
3,150,000
(B) Johnstown Campus
(I) Underground Telecommunications Systems
1,000,000
(II) Library Renovations
4,080,000
(C) Oakland Campus
(I) Renovation and addition to Trees Hall - Phase II
10,000,000
(II) Hillman Library Renovation - Phase II
15,400,000
(III) Salk Hall - Phase II
7,500,000
(IV) Renovation/addition to Field House
10,000,000
(V) Additional funds for DGS 1103-48, Convocation Center and Field House Complex
7,800,000
(Base Project Allocation - $6,500,000)
(Design and Contingencies - $1,300,000)
(D) Titusville Campus
(I) Underground Telecommunications Systems
500,000
(E) Bradford Campus
(I) Fine Arts Building
12,300,000
(Base Project Allocation - $12,000,000)
(Land Allocation - $300,000)
(II) ((II) repealed June 22, 2000, P.L.136, No.27)
(III) Sports Center Expansion
7,000,000
(Base Project Allocation - $7,000,000)
(IV) Maintenance Building
1,800,000
(Base Project Allocation - $1,800,000)
(V) Construction of academic building classrooms, offices, laboratories
2,600,000
(Base Project Allocation - $2,600,000)
(iv) Temple University
(A) Library and Learning Resources Center - H.S.C. Campus
31,800,000
(Base Construction Allocation - $26,500,000)
(Design and Contingencies - $5,300,000)
(B) Renovations to Beury Hall - Main Campus
9,120,000
(Base Construction Allocation - $7,600,000)
(Design and Contingencies - $1,520,000)
(C) Renovations to Barton Hall - Main Campus
11,160,000
(Base Construction Allocation - $9,300,000)
(Design and Contingencies - $1,860,000)
(D) Renovations to Bio-Life Sciences Building - Main Campus
19,730,000
(Base Construction Allocation - $16,400,000)
(Design and Contingencies - $3,330,000)
(E) Renovations to original Dental School Building - Health Sciences Center Facility - H.S.C. Campus
13,450,000
(Base Construction Allocation - $11,200,000)
(Design and Contingencies - $2,250,000)
(F) Education Center - Ambler Campus
5,760,000
(Base Construction Allocation - $4,800,000)
(Design and Contingencies - $960,000)
(G) Tomlinson Theatre Renovations and Expansion - Part I - Main Campus
2,580,000
(Base Construction Allocation - $2,150,000)
(Design and Contingencies - $430,000)
(H) Renovation of Mitten Hall
2,600,000
(Base Construction Allocation - $2,170,000)
(Design and Contingencies - $430,000)
(I) Renovation of Curtis Hall
3,840,000
(Base Construction Allocation - $3,200,000)
(Design and Contingencies - $640,000)
(J) Emergency Fire and Safety Renovations - Phase II - Main Campus
3,985,000
(Base Project Allocation - $3,320,000)
(Design and Contingencies - $665,000)
(K) Renovations for A.D.A. Compliance - Various Campuses
22,700,000
(Base Project Allocation - $18,900,000)
(Design and Contingencies - $3,800,000)
(L) Security System - Main Campus
7,000,000
(Base Project Allocation - $5,800,000)
(Design and Contingencies - $1,200,000)
(M) Electric Utility Distribution System Renovations - Main Campus
8,400,000
(Base Project Allocation - $7,000,000)
(Design and Contingencies - $1,400,000)
(N) Telecommunication Infrastructure Expansion
9,600,000
(Base Project Allocation - $8,000,000)
(Design and Contingencies - $1,600,000)
(O) Conversion of fluorescent lighting systems - all campuses
4,080,000
(Base Project Allocation - $3,400,000)
(Design and Contingencies - $680,000)
(P) In DGS Projects, upgrade certain HVAC systems, replace certain roofs and rehabilitate two lecture halls
5,040,000
(Base Project Allocation - $4,200,000)
(Design and Contingencies - $840,000)
(v) Lincoln University
(A) Campus security system
1,251,000
(Base Project Allocation - $1,251,000)
(B) Construction of an international cultural center
13,091,000
(Base Project Allocation - $10,808,000)
(Design and Contingencies - $2,283,000)
(vi) University of Pennsylvania
(A) Incinerator construction at New Bolton Center
937,000
(Base Project Allocation - $852,000)
(Design and Contingencies - $85,000)
(3) Department of Environmental Resources
$55,585,000
(i) Cook Forest State Park
(A) Additional funds for DGS 191-40 - renovating and construction of Sawmill Center
1,500,000
(B) Saw Mill Center construction of rustic lodge
3,000,000
(Base Project Allocation - $2,700,000)
(Design and Contingencies - $300,000)
(ii) Little Buffalo State Park
(A) Construction of an arts building
7,000
(Base Project Allocation - $7,000)
(iii) Laurel Hill State Park
(A) Construction of an environmental education/visitor center
2,530,000
(iv) Lehigh Gorge State Park
(A) Development of Rockport access area
2,129,000
(Base Project Allocation - $1,774,000)
(Design and Contingencies - $355,000)
(v) Prince Gallitzin State Park
(A) Construction of access road from SR 1021
11,273,000
(vi) Raccoon Creek State Park
(A) Access road from SR 3000 and improvements to facilities
2,000,000
(vii) Sproul State Forest
(A) Rehabilitation of Hyner View Road
1,100,000
(viii) Swatara State Park
(A) Additional funds for DGS 152-1, construction of dam and reservoir
8,000,000
(B) Additional funds for DGS 194-45 - Phase II relocation of roads and utilities
2,500,000
(ix) State Forest District Number 15
(A) Capping and revegetating of Thompson-Hollow Landfill
2,000,000
(Base Project Allocation - $2,000,000)
(x) Borough of Conshohocken, Montgomery County
(A) Additional funds for DGS 181-7, Plymouth Creek improvement
500,000
(xi) Borough of Pitcairn
(A) Concrete channel protection system
6,922,000
(Base Project Allocation - $5,768,000)
(Design and Contingencies - $1,154,000)
(xii) Borough of Nanty Glo
(A) Additional funds for DGS 184-6, widen Black Lick Creek flood protection
1,404,000
(Base Project Allocation - $1,170,000)
(Design and Contingencies - $234,000)
(xiii) Clearfield Borough
(A) Restoration of bank along Little Susquehanna Creek
1,000,000
(xiv) Gulich Township
(A) Improvements to Janesville Dam
500,000
(xv) Bigler Township
(A) Restoration of Little Muddy Run
1,000,000
(xvi) Berks County
(A) Rehabilitation of Felix Dam
500,000
(xvii) Delaware County
(A) Ridley Park Borough - replacement of East Lake Dam
500,000
(xviii) Luzerne County
(A) West Side Landfill Authority postclosure, capping and revegetating
6,000,000
(xix) Montgomery County
(A) Abington and Upper Dublin Townships - Sandy Run Flood Protection Project
720,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $120,000)
(xx) Dixmont State Hospital Property
(A) Environmental cleanup
500,000
(4) Department of General Services
$126,126,000
(i) Dauphin County
(A) ((A) repealed July 11, 1996, P.L.595, No.101 and Oct. 10, 1997, P.L.392, No.47; Act 1996-101 overlooked by Act 1997-47)
(ii) Capitol Complex
(A) Renovation of Labor and Industry Building
3,100,000
(Base Project Allocation - $2,583,000)
(Design and Contingencies - $517,000)
(B) Renovation of Health and Welfare Building
1,853,000
(Base Project Allocation - $1,544,000)
(Design and Contingencies - $309,000)
(C) Construction of addition to and renovation of the State Record Center
2,500,000
(Base Project Allocation - $2,100,000)
(Design and Contingencies - $400,000)
(D) Construction of freight elevator in the north end of the State Capitol Building
1,000,000
(E) ((E) repealed July 11, 1996, P.L.595, No.101 and Oct. 10, 1997, P.L.392, No.47; Act 1996-101 overlooked by Act 1997-47)
(iii) Philadelphia State Office Building
(A) Additional funds for DGS 943-7 - fire and safety improvements
2,237,000
(Base Project Allocation - $1,864,000)
(Design and Contingencies - $373,000)
(iv) Pittsburgh State Office Building
(A) Renovation of Pittsburgh State Office Building
5,112,000
(Base Project Allocation - $4,260,000)
(Design and Contingencies - $852,000)
(v) Tioga County
(A) Construction of a welcome center at the Tioga - Hammond Dam area along US 15
3,400,000
(Base Project Allocation - $3,000,000)
(Design and Contingencies - $400,000)
(5) Historical and Museum Commission
$5,824,000
(i) Butler Industrial Museum
(A) Building and site improvement
500,000
(Base Project Allocation - $415,000)
(Design and Contingencies - $85,000)
(ii) DeBence Museum
(A) Building and site improvements
250,000
(iii) Muhlenberg House
450,000
(Base Project Allocation - $400,000)
(Design and Contingencies - $50,000)
(iv) The Highlands, Ft. Washington, Pa.
(A) Restoration and maintenance
100,000
(v) Old Economy Village
(A) Restoration and preservation of Great House
540,000
(Base Project Allocation - $450,000)
(Design and Contingencies - $90,000)
(vi) Scottish Rite Cathedral - City of New Castle
(A) Renovation and improvements. The design portion of this project shall include the cost of a study to determine the feasibility of restoration. The cost of the study shall not exceed $100,000.
500,000
(Base Project Allocation - $400,000)
(Design and Contingencies - $100,000)
(vii) Schuylkill County
(A) Anthracite Museum of Mining - construct a multiuse auditorium/community room
484,000
(Base Project Allocation - $421,000)
(Design and Contingencies - $63,000)
(viii) Venango County
(A) Improvements to roof and addition to Drake Well State Museum
3,000,000
(Base Project Allocation - $2,400,000)
(Design and Contingencies - $600,000)
(6) Department of Military Affairs
$8,369,000
(i) Armstrong County Armory
(A) New Armory, Ford City
960,000
(Base Project Allocation - $675,000)
(Design and Contingencies - $135,000)
(Land Allocation - $150,000)
(ii) Indiana County Armory
(A) New Armory
870,000
(Base Project Allocation - $725,000)
(Design and Contingencies - $145,000)
(iii) Erie Soldiers' and Sailors' Home
(A) Replacement of fire and smoke detection system
198,000
(Base Project Allocation - $165,000)
(Design and Contingencies - $33,000)
(iv) Hollidaysburg Veterans Home
(A) Smoke removal systems in MacArthur and Eisenhower Halls
220,000
(B) Steam Tunnel repair
350,000
(v) Cambria County Armory
(A) ((A) repealed Oct. 10, 1997, P.L.392, No.47)
(vi) Westmoreland County Armory
(A) New Armory, Mount Pleasant
1,671,000
(Base Project Allocation - $1,176,000)
(Design and Contingencies - $235,000)
(Land Allocation - $260,000)
(vii) Philipsburg Airport
(A) Flight facility and armory at Philipsburg Airport
600,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $100,000)
(viii) Mid-State Regional Airport
(A) Construction of Butler Building
500,000
(Base Project Allocation - $400,000)
(Design and Contingencies - $100,000)
(ix) Johnstown Army National Guard Armory
(A) Construction and renovation
1,500,000
(x) 28th Division Shrine
(A) For the purchase and installation of the plaques of the 28th Division on the WWII Memorial Wall at Boalsburg
120,000
(7) Department of Public Welfare
$12,863,000
(i) Loysville Youth Development Center
(A) Air condition Allegheny Building
228,000
(Base Project Allocation - $190,000)
(Design and Contingencies - $38,000)
(ii) Central Pennsylvania Youth Development Center
(A) Acquisition or construction of facility for use as a maximum security youth development center
3,200,000
(Base Project Allocation - $3,200,000)
The amount provided for this project is the maximum amount which may be used for the acquisition or construction of this facility.
(iii) Youth Forestry Camp Number 2
(A) Addition to Dormitory A
256,000
(Base Project Allocation - $213,000)
(Design and Contingencies - $43,000)
(iv) Youth Forestry Camp Number 3
(A) Construction of perimeter security fence around institution
350,000
(Base Project Allocation - $300,000)
(Design and Contingencies - $50,000)
(v) Allentown State Hospital
(A) Upgrade electrical distribution system
1,917,000
(Base Project Allocation - $1,598,000)
(Design and Contingencies - $319,000)
(vi) Clarks Summit State Hospital
(A) Replacement of water distribution system
1,800,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $300,000)
(vii) Mayview State Hospital
(A) Renovate baths in Dixon Building No. 27
282,000
(Base Project Allocation - $235,000)
(Design and Contingencies - $47,000)
(viii) Norristown State Hospital
(A) Renovate Laundry Building No. 35
1,200,000
(Base Project Allocation - $1,000,000)
(Design and Contingencies - $200,000)
(ix) Warren State Hospital
(A) Upgrade heating control systems
540,000
(Base Project Allocation - $450,000)
(Design and Contingencies - $90,000)
(x) Laurelton Center
(A) Replace air conditioning and windows
720,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $120,000)
(xi) Wernersville State Hospital
(A) Upgrade water supply/treatment systems
660,000
(Base Project Allocation - $550,000)
(Design and Contingencies - $110,000)
(xii) Ebensburg Center
(A) Upgrade water supply distribution system
660,000
(Base Project Allocation - $550,000)
(Design and Contingencies - $110,000)
(B) Reconstruct masonry walls and upgrade windows in Keystone House, Harmony House, Laurel House, Villa, JFK, Horizon and Sunset buildings
1,050,000
(Base Project Allocation - $875,000)
(Design and Contingencies - $175,000)
(8) Pennsylvania State Police
$1,766,000
(i) Bethlehem Troop Headquarters
(A) Additional funds for DGS 206-3 - renovations and addition to Bethlehem Troop Headquarters
1,766,000
(Base Project Allocation - $1,500,000)
(Design and Contingencies - $266,000)
(9) State System of Higher Education
$548,802,000
(i) Bloomsburg State University
(A) Addition to Hartline Science
7,904,000
(B) Renovation of Ben Franklin Hall
4,528,000
(C) Renovation of Navy Hall
5,650,000
(D) Renovation of Bakeless Center
5,106,000
(E) Construction of parking areas
1,456,000
(ii) California State University
(A) Renovation of Old Main and South Hall
7,654,000
(B) Renovation of Old Industrial Arts Building
3,461,000
(C) Renovation of Steel Auditorium
2,200,000
(D) Renovation of Vulcan Hall
1,202,000
(E) Renovation of Noss Hall
3,006,000
(iii) Cheyney University of Pennsylvania
(A) Renovation of Rachael Hall Educational Building
6,600,000
(B) Renovation of Coppin Hall
2,015,000
(C) Renovation of Waring Hall
5,905,000
(D) Renovation of Browne Hall
2,058,000
(E) Utility and infrastructure renovations
5,880,000
(F) Renovation of Carnegie Building
4,478,000
(G) Renovation of Vaux/Logan
6,385,000
(H) Renovation/razing of cottages
120,000
(iv) Clarion State University
(A) Renovate/upgrade communication system
3,600,000
(B) Renovation of Montgomery Hall - Phase II
1,200,000
(C) Renovation of Harvey Hall - Phase II
1,690,000
(D) Addition and renovation of Carlson Library
15,071,000
(E) Renovation of Pierce Science Center
6,757,000
(v) East Stroudsburg State University
(A) Campus pedestrian safety modifications
1,597,000
(B) Renovation of Koehler Field House
6,286,000
(C) Renovation of and addition to auditorium
2,604,000
(D) Construction of physics and computer science facility
15,111,000
(E) Renovation and expansion of storm water management system
1,860,000
(F) Addition/renovation of stadium complex
5,494,000
(G) Construction of instructional complex for physical education
5,578,000
(H) Construction of maintenance building
6,846,000
(I) Construction of parking areas
856,000
(J) Additional funds for Gessner Science DGS 405-49
530,000
(vi) Edinboro State University
(A) Renovation of McComb Field House bleachers
907,000
(B) Rehabilitation of campus drainage system
640,000
(C) Renovation of Memorial Auditorium
1,638,000
(D) Renovation of Loveland Hall - Phase II
2,128,000
(E) Construction of maintenance/storage/office facility
6,144,000
(F) Addition to McComb Field House
5,296,000
(G) Replacement or renovation of White Hall
881,000
(H) Construction of new classroom building
7,196,000
(I) Renovation and asbestos decontamination of Sox Harrison Stadium
780,000
(vii) Indiana State University
(A) Rehabilitation of Miller Stadium
6,798,000
(B) Renovation of Stabley Library
6,134,000
(C) Renovation of Eicher Hall
2,525,000
(D) Addition/renovation of Ackerman Hall
6,348,000
(E) Addition/renovation of Cogswell Hall
7,272,000
(F) Renovation of Keith Hall
9,773,000
(G) Renovation of John Sutton Hall
14,303,000
(H) Renovation of Leonard Hall
7,549,000
(I) Addition/renovation Fisher Auditorium
9,754,000
(J) Renovation of Wilson Hall
3,157,000
(K) Construction of behavioral science classroom building
16,748,000
(L) Renovation of steam distribution system
1,440,000
(M) Upgrade electrical distribution system
1,800,000
(N) Renovation to Boiler Plant
3,600,000
(viii) Kutztown State University
(A) Construction of College of Business Building
7,438,000
(B) Construction of Communications Design Building
5,903,000
(C) Addition to maintenance building and garage
2,992,000
(D) Addition and renovation of science building
10,403,000
(E) Construction of Kutztown University Bypass from US 222 to College Boulevard
2,243,000
(Base Project Allocation - $1,869,000)
(Design and Contingencies - $374,000)
(ix) Lock Haven State University
(A) Renovation of Rogers Gym
3,102,000
(B) Renovation of Zimmerli Gym
3,380,000
(C) Acquisition and renovation or construction of Courthouse Annex
4,400,000
(Base Project Allocation - $3,250,000)
(Land Allocation - $500,000)
(Design and Contingencies - $650,000)
(x) Mansfield State University
(A) Addition to Grant Science - Phase III
3,901,000
(B) Renovation/addition home economics center
5,630,000
(C) Renovation of South Hall
3,390,000
(xi) Millersville State University
(A) Addition to McComsey Hall
8,232,000
(B) Renovation of Bassler Hall
1,253,000
(C) Addition to Stayer Hall
4,700,000
(D) Construction of Theater Arts Education Building
12,926,000
(E) Addition of Palmer/Bishop
600,000
(F) Construction of Academic Support Center
3,000,000
(G) Construction of parking and roadways
2,258,000
(xii) Shippensburg State University
(A) Renovation of Horton Hall
9,185,000
(B) Renovation of Gilbert and Stewart Halls
4,468,000
(C) Construction of instructional arts facility
17,308,000
(D) Addition to Lehman Library
9,485,000
(E) Construction of central receiving and storage facility
1,292,000
(F) Construction of roadways, sidewalks and parking facilities
3,894,000
(G) Renovation of Franklin Science Center
11,018,000
(H) Addition and renovation of Memorial Auditorium
9,799,000
(I) Renovation of Shippen Hall
4,854,000
(J) Upgrade sanitary sewer system
383,000
(K) Upgrade Steam Plant Boiler No. 4
500,000
(L) Renovation of Rowland and Shearer
7,417,000
(xiii) Slippery Rock State University
(A) Renovation of Vincent Science Building
18,293,000
(B) Renovation of McKay Educational Building
8,644,000
(C) Renovation of Morrow Field House - Phase I
13,300,000
(D) Construction of roadways and parking
3,380,000
(E) Construction of health professionals building
8,190,000
(xiv) West Chester State University
(A) Renovation of E. O. Bull Center
6,580,000
(B) Construction of classroom facility
12,186,000
(C) Renovation of Old Library
3,198,000
(D) Addition and renovation to Mitchell Hall
8,701,000
(E) Construction of computing/instructional technology center
13,250,000
(F) Construction of all-purpose outdoor physical education and athletic fields
3,602,000
(xv) Systemwide project
(A) Asbestos abatement
10,625,000
(10) Department of Transportation
$10,042,000
(i) Luzerne County Maintenance Facility
(A) Replacement
4,034,000
(Base Project Allocation - $3,195,000)
(Land Allocation - $200,000)
(Design and Contingencies - $639,000)
(ii) Adams County Welcome Center
(A) Additional funds for DGS 657-6 - construction of new welcome center
574,000
(Base Project Allocation - $479,000)
(Design and Contingencies - $95,000)
(iii) Pike County
(A) Construction of new welcome center
4,160,000
(Base Project Allocation - $3,550,000)
(Design and Contingencies - $610,000)
(iv) York County Substation
(A) Demolition of York Substation
274,000
(Base Project Allocation - $228,000)
(Design and Contingencies - $46,000)
(v) Lebanon County
(A) Bridge repair and necessary roadway improvement to bridge at intersection of SR 897 and East Elm Street
1,000,000
(Base Project Allocation - $1,000,000)
Compiler's Note: The Department of Public Welfare, referred to in this section, was redesignated as the Department of Human Services by Act 132 of 2014.