Section 321. Cumberland County.
(a) I-81
(1) Exit 12, Interchange with PA 465, Interchange Improvements
1,520,000
(Base Construction Allocation - $1,200,000)
(Land Allocation - $20,000)
(Design and Contingencies - $300,000)
(2) Franklin County Line to Stoughstown, Pavement Rehabilitation and Safety Improvements
1,210,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $10,000)
(Design and Contingencies - $200,000)
(3) Cumberland West, Resurfacing Pavement, Rehabilitation and Safety Improvements
9,790,000
(Base Project Allocation - $9,480,000)
(Land Allocation - $10,000)
(Design and Contingencies - $300,000)
(4) Hampton East PM, PA 114 to George Wade Bridge, Pavement Rehabilitation and Safety Improvements
1,388,000
(Base Project Allocation - $1,358,000)
(Design and Contingencies - $30,000)
(5) US 11 to PA 114, Pavement Restoration
7,810,000
(Base Project Allocation - $7,540,000)
(Design and Contingencies - $270,000)
(6) Interchange with PA 944, Transportation Improvements around Interchange
500,000
(Base Project Allocation - $400,000)
(Land Allocation - $50,000)
(Design and Contingencies - $50,000)
(b) I-83
(1) Interchange with PA 581 and PA 114, Exit 18 to Susquehanna River, Interchange Design Alternative
90,000
(Design and Contingencies - $90,000)
(c) US 15
(1) PA 581 to Dillsburg, Pavement Restoration
8,100,000
(Base Project Allocation - $8,000,000)
(Design and Contingencies - $100,000)
(2) US 11, Range Road to Cumberland County Line, Pavement Restoration and Safety Improvements
1,310,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $10,000)
(Design and Contingencies - $300,000)
(d) PA 114
(1) I-81 to US 11, Silver Spring Township, Pavement Restoration and Safety Improvements
720,000
(Base Project Allocation - $460,000)
(Land Allocation - $10,000)
(Design and Contingencies - $250,000)
(e) SR 581
(1) Installation of Noise Barriers on SR 581 from I-83 Intersection to Sporting Hill
21,000,000
(Base Project Allocation - $18,000,000)
(Land Allocation - $1,500,000)
(Design and Contingencies - $1,500,000)
(f) SR 1015
(1) 21st Street to PA 944, Relocation, Widening and Reconstruction
391,000
(Base Project Allocation - $391,000)