Section 336. Lancaster County.
(a) PA 23
(1) US 30 to Berks County Line, Pavement Rehabilitation and Safety Improvements
2,200,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $200,000)
(2) Four-Lane Relocation Environmental Impact Study
1,000,000
(Design and Contingencies - $1,000,000)
(3) US 30 to Berks County Line, Four-Lane Relocation of PA 23
60,000,000
(4) Environmental Impact Study
1,000,000
(5) US 30 to Berks County Line, M.I.S., Roadway Rehabilitation and Safety Improvements
1,200,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $100,000)
(Design and Contingencies - $100,000)
(6) US 30 to Berks County Line, Corridor Improvements
1,200,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $100,000)
(Design and Contingencies - $100,000)
(b) PA 322
(1) Farmersville Road to PA 897, Pavement Rehabilitation, Widen Shoulder and Safety Improvements
1,320,000
(Base Project Allocation - $1,200,000)
(Design and Contingencies - $120,000)
(c) PA 372
(1) Oak Bottom Road to Germantown Avenue, Pavement Rehabilitation and Safety Improvements
2,200,000
(Base Project Allocation - $2,000,000)
(Design and Contingencies - $200,000)
(d) PA 896
(1) US 30 to Strasburg Borough, Pavement Rehabilitation, Widen Shoulder and Safety Improvements
1,980,000
(Base Project Allocation - $1,800,000)
(Design and Contingencies - $180,000)
(2) Strasburg Borough to PA 372, Valley Road, Pavement Rehabilitation and Safety Improvements
2,338,000
(Base Project Allocation - $2,126,000)
(Design and Contingencies - $212,000)
(3) Strasburg Township and Strasburg Borough, Two-Lane Relocation
2,500,000
(Base Project Allocation - $2,500,000)
(e) PA 897
(1) Amish Road to Adamstown Road, Pavement Rehabilitation and Safety Improvements
3,850,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $350,000)
(f) US 30
(1) PA 741 to PA 72, Widening West, Roadway Rehabilitation
7,600,000
(Base Project Allocation - $6,800,000)
(Land Allocation - $200,000)
(Design and Contingencies - $600,000)
(2) US 222 to PA 340, Widening East, Roadway Rehabilitation
9,540,000
(Base Project Allocation - $8,740,000)
(Land Allocation - $200,000)
(Design and Contingencies - $600,000)
(3) PA 896 to PA 897
3,000,000
(Design and Contingencies - $3,000,000)
(4) PA 896 to PA 41, Environmental Impact Study
1,000,000
(Design and Contingencies - $1,000,000)
(5) Widen to Five Lanes between PA 896 to PA 41
10,000,000
(6) Intersection Improvements on Parallel Roads to Alleviate Congestion Prior to and During Reconstruction
1,000,000
(7) Vicinity of PA 772 and PA 41, Reconstruction
1,500,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $150,000)
(Design and Contingencies - $150,000)
(g) SR 2015
(1) Strasburg Borough to PA 372, Pavement Rehabilitation and Safety Improvements
2,860,000
(Base Project Allocation - $2,600,000)
(Design and Contingencies - $260,000)
(h) SR 2040
(1) Paradise Lane to PA 741, Pavement Rehabilitation and Safety Improvements
671,000
(Base Project Allocation - $610,000)
(Design and Contingencies - $61,000)
(i) SR 3017
(1) PA 462 to Harrisburg Pike, Pavement Rehabilitation and Safety Improvements
7,700,000
(Base Project Allocation - $7,000,000)
(Design and Contingencies - $700,000)
(j) PA 41
(1) PA 926 to US 30, Major Investment Study
500,000
(Design and Contingencies - $500,000)
(k) PA 72/PA 501 Corridor
(1) Construction of Manheim Relief Route
3,400,000
(2) Construction of East Petersburg Relief Route
2,400,000
(3) Widen PA 72 from PA 283 to Miller Road
4,000,000
(l) Airport Road
(1) Relocate and Realign Airport Road in Manheim Township
300,000