Section 343. Mercer County.
(a) I-79
(1) Lawrence County Line to Crawford County Line, Pavement Rehabilitation and Safety Improvements
2,600,000
(Base Project Allocation - $2,327,000)
(Land Allocation - $13,000)
(Design and Contingencies - $260,000)
(2) Intersection with PA 208 and PA 258, Springfield Township, Highway and Interchange Improvements
2,700,000
(Base Project Allocation - $2,500,000)
(Land Allocation - $100,000)
(Design and Contingencies - $100,000)
(b) I-80
(1) PA 173 to Venango County Line, Safety Improvements and Pavement Rehabilitation, Length 4.0 Miles
12,600,000
(Base Project Allocation - $12,000,000)
(Design and Contingencies - $600,000)
(2) Ohio State Line to US 19, Pavement Rehabilitation and Safety Improvements
1,020,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $10,000)
(Design and Contingencies - $10,000)
(c) PA 208
(1) From PA 258 to Old Route 258, Including Bridge over I-79, Widen to 48 Feet
14,700,000
(Base Construction Allocation - $12,500,000)
(Land Allocation - $1,000,000)
(Design and Contingencies - $1,200,000)
(d) SR 60
(1) Bridge Rehabilitation and Interchange Improvement at SR 318
4,080,000
(Base Project Allocation - $3,800,000)
(Land Allocation - $80,000)
(Design and Contingencies - $200,000)
(2) T-369 to Broadway, Pavement Rehabilitation and Safety Improvements
620,000
(Base Project Allocation - $600,000)
(Design and Contingencies - $20,000)
(e) PA 58
(1) Near Jamestown, Underpass Removal and Pavement Rehabilitation
250,000
(Base Project Allocation - $200,000)
(Land Allocation - $20,000)
(Design and Contingencies - $20,000)
(f) PA 518
(1) Lamore Road over Pine Hollow Run, Two-Lane Relocation
760,000
(Base Project Allocation - $600,000)
(Land Allocation - $100,000)
(Design and Contingencies - $60,000)
(g) TR 18
(1) Remove Box Beam Barrier, Add Turning Lanes, Shoulder and Intersection Improvements
5,750,000
(Base Project Allocation - $4,000,000)
(Land Allocation - $1,250,000)
(Design and Contingencies - $500,000)
(2) Hermitage to Greenville, Pavement Rehabilitation and Safety Improvements
440,000
(Base Project Allocation - $400,000)
(Land Allocation - $20,000)
(Design and Contingencies - $20,000)
(h) PA 718
(1) Improvements to Route 718 in the Borough of Wheatland and Cities of Farrell and Sharon
10,000,000