Section 345. Monroe County.
(a) I-80
(1) Construction of Full Interchange at I-80, Exit 44 to Connect with US 611
13,000,000
(Base Construction Allocation - $10,000,000)
(Land Allocation - $2,000,000)
(Design and Contingencies - $1,000,000)
(2) Carbon County Line to US 209, Pavement Rehabilitation and Safety Improvements
2,190,000
(Base Project Allocation - $1,989,000)
(Land Allocation - $1,000)
(Design and Contingencies - $200,000)
(3) Interchange with I-380, Interchange Improvements
2,766,000
(Base Project Allocation - $2,666,000)
(Design and Contingencies - $100,000)
(4) I-80 at Tunkhannock, Pavement Restoration
2,440,000
(Base Project Allocation - $2,400,000)
(Design and Contingencies - $40,000)
(5) Construction of Diamond-Shaped Interchange at Exit 53 of I-80 in Delaware Water Gap to Provide Access to Visitors Center
14,000,000
(Base Project Allocation - $13,000,000)
(Design and Contingencies - $1,000,000)
(b) SR 115
(1) From I-80 at Exit 43, South Approximately 3.5 Miles to Long Pond Road, Stabilize and Widen Shoulders
11,000,000
(Base Project Allocation - $10,500,000)
(Design and Contingencies - $500,000)
(c) SR 209
(1) Construction of Four-Lane Divided Relocation of SR 209 at Intersection with SR 402 in Smithfield Township
49,500,000
(Base Project Allocation - $35,000,000)
(Land Allocation - $10,000,000)
(Design and Contingencies - $4,500,000)
(2) Transportation Study for Possible Marshalls Creek Bypass
300,000
(Design and Contingencies - $300,000)
(3) Construction of Intersection Improvements of Routes 209/447 Intersection just off Exit 52 of I-80 in Smithfield Township
3,800,000
(Base Project Allocation - $3,500,000)
(Design and Contingencies - $300,000)
(d) SR 611
(1) Widen to 64 Feet Between T-535 and T-537 in Pocono Township
2,600,000
(Base Project Allocation - $2,000,000)
(Land Allocation - $500,000)
(Design and Contingencies - $100,000)
(2) Restoration of SR 611 between Scotrun and Swiftwater, Pocono Township
2,010,000
(Base Construction Allocation - $2,000,000)
(Design and Contingencies - $10,000)
(3) Five-Point Intersection with SR 940 and SR 196, Intersection Improvements
540,000
(Base Project Allocation - $400,000)
(Land Allocation - $80,000)
(Design and Contingencies - $60,000)
(e) Pocono Scenic Vistas
(1) Construction of Pocono Scenic Vistas in the Long Pond Area
1,250,000
(Base Project Allocation - $100,000)
(Land Allocation - $1,050,000)
(Design and Contingencies - $100,000)