Westmoreland County

Act 78 of 1998, § 365, under HIGHWAY CAPITAL BUDGET PROJECT ITEMIZATION ACT OF 1996-1997.

Act 78 of 1998, § 365

Section 365. Westmoreland County.

(a) I-70

(1) Washington County Line to I-76, Pavement Rehabilitation and Safety Improvements

1,700,000

(Base Project Allocation - $1,521,000)

(Land Allocation - $9,000)

(Design and Contingencies - $170,000)

(2) North Belle Vernon to SR 201, Reconstruction and Safety Improvements

470,000

(Base Project Allocation - $450,000)

(Land Allocation - $10,000)

(Design and Contingencies - $10,000)

(b) SR 3111

(1) Center Avenue, Borough of New Stanton, Two-Lane Relocation

940,000

(Base Project Allocation - $700,000)

(Land Allocation - $40,000)

(Design and Contingencies - $200,000)

(c) SR 982

(1) Reconstruction of SR 982, Including Climbing Lanes from Laurelville, Mt. Pleasant Township, to Intersection with SR 31 in Fayette County

6,500,000

(Base Project Allocation - $5,000,000)

(Land Allocation - $500,000)

(Design and Contingencies - $1,000,000)

(d) SR 356

(1) Reconstruction of SR 356, Including Widening, Overlay and Safety Improvements

3,000,000

(Base Project Allocation - $2,500,000)

(Land Allocation - $100,000)

(Design and Contingencies - $400,000)

(e) US 30

(1) Georges' Station Road to Mt. View, Pavement Restoration and Safety Improvements

840,000

(Base Project Allocation - $800,000)

(Land Allocation - $20,000)

(Design and Contingencies - $20,000)

(2) Beatty to PA 981, Pavement Restoration

4,600,000

(Base Project Allocation - $4,500,000)

(Design and Contingencies - $100,000)

(3) PA 981 to Kingston, Pavement Restoration

3,200,000

(Base Project Allocation - $3,100,000)

(Design and Contingencies - $100,000)

(f) US 119

(1) Mt. Pleasant to South of Youngwood Interchange, Pavement Rehabilitation and Safety Improvements

4,040,000

(Base Project Allocation - $4,000,000)

(Land Allocation - $20,000)

(Design and Contingencies - $20,000)

(2) Mt. Pleasant and Scottdale Interchange, Interchange Improvements

1,400,000

(Base Project Allocation - $1,000,000)

(Land Allocation - $200,000)

(Design and Contingencies - $200,000)

(3) New Stanton Park-and-Ride, Parking Lot and Lighting

140,000

(Base Project Allocation - $80,000)

(Land Allocation - $40,000)

(Design and Contingencies - $20,000)

(g) PA 56

(1) Cambria County Line to Indiana County Line, Roadway Realignment and Reconstruction

7,400,000

(Base Project Allocation - $5,500,000)

(Land Allocation - $900,000)

(Design and Contingencies - $1,000,000)

(h) PA 906

(1) Belle Vernon to Rostraver, Pavement Restoration and Safety Improvements

440,000

(Base Project Allocation - $400,000)

(Land Allocation - $20,000)

(Design and Contingencies - $20,000)