Section 14. Butler County.
(a) Local Bridges
Local
State
(1) Butler Township, SR 7101 over Little Connoquenessing Creek, Bridge Replacement, Bridge Key 8153, Project ID 95865
Project Allocation
313,000
(Base Project Allocation - $313,000)
(2) Clearfield Township, SR 7208 over Tributary of Little Buffalo Run, Bridge Replacement, Bridge Key 8191, Project ID 77934
Project Allocation
313,000
(Base Project Allocation - $313,000)
(3) Clearfield Township, SR 7208 over Little Buffalo Run, Bridge Replacement, Bridge Key 8192, Project ID 77937
Project Allocation
750,000
(Base Project Allocation - $750,000)
(4) Clinton Township, SR 7209 over Goldscheitter Creek, Bridge Replacement, Bridge Key 8201, Project ID 95874
Project Allocation
313,000
(Base Project Allocation - $313,000)
(5) Clinton Township, SR 7209 over Davis Run, Bridge Replacement, Bridge Key 8206, Project ID 95876
Project Allocation
313,000
(Base Project Allocation - $313,000)
(6) Forward Township, SR 7215 over Connoquenessing Creek, Bridge Rehabilitation, Bridge Key 8228, Project ID 24420
Project Allocation
1,572,666
(Base Project Allocation - $1,562,666)
(Land Allocation - $2,000)
(Design & Contingencies - $8,000)
(7) Winfield Township, SR 7231 over Rough Run, Bridge Replacement, Bridge Key 8296, Project ID 77954
Project Allocation
313,000
(Base Project Allocation - $313,000)
(8) Worth Township, SR 7232 over Muddy Creek, Bridge Replacement, Bridge Key 8297, Project ID 24866
Project Allocation
2,310,000
(Base Project Allocation - $2,280,000)
(Land Allocation - $4,000)
(Design & Contingencies - $26,000)
(b) State Bridges
(1) SR 0008 over Muddy Creek, Clay Township, Bridge Replacement, Bridge Key 7787, Project ID 24722
Project Allocation
3,090,000
(Base Project Allocation - $3,000,000)
(Land Allocation - $20,000)
(Design & Contingencies - $70,000)
(2) SR 0008 over Bessemer & Lake Erie Railroad and Thorn Creek, Penn Township, Bridge Preservation, Bridge Key 7777, Project ID 117126
Project Allocation
300,000
(Base Project Allocation - $300,000)
(3) SR 0019 over Coal Run, Cranberry Township, Bridge Replacement, Bridge Key 7799, Project ID 99683
Project Allocation
2,450,000
(Base Project Allocation - $2,450,000)
(4) SR 0019 over CSX Railroad and Connoquenessing Creek, Zelienople Borough, Bridge Restoration, Bridge Key 7804, Project ID 98023
Project Allocation
1,881,000
(Base Project Allocation - $1,881,000)
(5) SR 0019 over SR 0422, Muddy Creek Township, Bridge Preservation, Bridge Key 46494, Project ID 117126
Project Allocation
300,000
(Base Project Allocation - $300,000)
(6) SR 0028 over SR 2017, Buffalo Township, Bridge Rehabilitation, Bridge Key 7808, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(7) SR 0058 over McMurray Run, Mercer Township, Bridge Replacement, Bridge Key 7824, Project ID 24679
Project Allocation
1,560,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $10,000)
(Design & Contingencies - $50,000)
(8) SR 0068 over Tributary of Connoquenessing Creek, Forward Township, Bridge Replacement, Bridge Key 7842, Project ID 90001
Project Allocation
1,825,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $50,000)
(Design & Contingencies - $275,000)
(9) SR 0068 over Sullivan Run, City of Butler, Bridge Replacement, Bridge Key 53498, Project ID 117126
Project Allocation
2,059,691
(Base Project Allocation - $1,732,391)
(Land Allocation - $20,300)
(Design & Contingencies - $307,000)
(10) SR 0079 over Tollgate School Road (TR 302), Jackson Township, Bridge Rehabilitation, Bridge Key 7863, Project ID 117126
Project Allocation
300,000
(Base Project Allocation - $300,000)
(11) SR 0079 over SR 0068, Buffalo & Pittsburgh Railroad and Connoquenessing Creek, Jackson Township, Bridge Replacement, Bridge Key 7866, Project ID 117126
Project Allocation
28,835,670
(Base Project Allocation - $24,253,470)
(Land Allocation - $284,200)
(Design & Contingencies - $4,298,000)
(12) SR 0079 over SR 0068, Buffalo & Pittsburgh Railroad and Connoquenessing Creek, Jackson Township, Bridge Replacement, Bridge Key 7867, Project ID 117126
Project Allocation
26,775,979
(Base Project Allocation - $22,521,079)
(Land Allocation - $263,900)
(Design & Contingencies - $3,991,000)
(13) SR 0079 over Tollgate School Road (TR 302), Jackson Township, Bridge Rehabilitation, Bridge Key 7861, Project ID 117126
Project Allocation
300,000
(Base Project Allocation - $300,000)
(14) SR 0228 over Kaufman Run, Adams Township, Bridge Replacement, Bridge Key 7903, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(15) SR 0228 over Tributary of Kaufman Run, Seven Fields Borough, Bridge Replacement, Bridge Key 7902, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(16) SR 0228 over Buffalo & Pittsburgh Railroad, Adams Township, Bridge Preservation, Bridge Key 48069, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(17) SR 0228 over I-79 and SR 9479, Cranberry Township, Bridge Rehabilitation, Bridge Key 41062, Project ID 117126
Project Allocation
4,119,381
(Base Project Allocation - $3,464,781)
(Land Allocation - $40,600)
(Design & Contingencies - $614,000)
(18) SR 0258 over Tributary of Wolf Creek, Slippery Rock Borough, Bridge Replacement, Bridge Key 7912, Project ID 117126
Project Allocation
300,000
(Base Project Allocation - $300,000)
(19) SR 0268 over North Branch of Bear Creek, Parker Township, Bridge Replacement, Bridge Key 7920, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(20) SR 0422 over Tributary of Muddy Creek, Muddy Creek Township, Bridge Replacement, Bridge Key 7939, Project ID 83611
Project Allocation
1,000,643
(Land Allocation - $25,000)
(Design & Contingencies - $975,643)
(21) SR 0422 over Connoquenessing Creek, Shearer Road and Railroad, Butler Township, Bridge Restoration, Bridge Key 7957, Project ID 98028
Project Allocation
1,850,000
(Base Project Allocation - $1,850,000)
(22) SR 0422 over Buffalo and Pittsburgh Railroad and Bonnie Brook, Summit Township, Bridge Restoration, Bridge Key 7960, Project ID 98023
Project Allocation
1,881,000
(Base Project Allocation - $1,881,000)
(23) SR 0422 over SR 0068, Summit Township, Bridge Rehabilitation, Bridge Key 7958, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(24) SR 0422 over SR 2004, Summit Township, Bridge Preservation, Bridge Key 7959, Project ID 117126
Project Allocation
5,149,227
(Base Project Allocation - $4,330,977)
(Land Allocation - $50,750)
(Design & Contingencies - $767,500)
(25) SR 0488 over I-79, Muddy Creek Township, Bridge Replacement, Bridge Key 7970, Project ID 98730
Project Allocation
1,761,500
(Base Project Allocation - $1,229,900)
(Land Allocation - $25,000)
(Design & Contingencies - $506,600)
(26) SR 0528 over Lake Arthur, Franklin Township, Bridge Rehabilitation, Bridge Key 7978, Project ID 24241
Project Allocation
19,533,000
(Base Project Allocation - $19,500,000)
(Land Allocation - $3,000)
(Design & Contingencies - $30,000)
(27) SR 0528 over Big Run, Brady Township, Bridge Replacement, Bridge Key 7979, Project ID 83323
Project Allocation
1,825,000
(Base Project Allocation - $1,825,000)
(28) SR 0528 over SR 0079 Southbound, Jackson Township, Bridge Replacement, Bridge Key 7971, Project ID 117126
Project Allocation
7,208,917
(Base Project Allocation - $6,063,367)
(Land Allocation - $71,050)
(Design & Contingencies - $1,074,500)
(29) SR 0528 over SR 0079 Northbound, Jackson Township, Bridge Replacement, Bridge Key 7972, Project ID 117126
Project Allocation
7,208,917
(Base Project Allocation - $6,063,367)
(Land Allocation - $71,050)
(Design & Contingencies - $1,074,500)
(30) SR 1004 over Tributary of Silver Creek, Parker Township, Bridge Replacement, Bridge Key 7981, Project ID 83324
Project Allocation
2,020,000
(Base Project Allocation - $2,020,000)
(31) SR 2004 over Bonnie Brook, East Butler Borough, Bridge Replacement, Bridge Key 8023, Project ID 24781
Project Allocation
3,212,034
(Base Project Allocation - $3,152,034)
(Land Allocation - $10,000)
(Design & Contingencies - $50,000)
(32) SR 2011 over Lardintown Run, Clinton Township, Bridge Replacement, Bridge Key 8037, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(33) SR 2018 over Little Buffalo Creek, Buffalo Township, Bridge Replacement, Bridge Key 8049, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(34) SR 3014 over Breakneck Creek, Callery Borough, Bridge Replacement, Bridge Key 8077, Project ID 89972
Project Allocation
738,980
(Base Project Allocation - $278,240)
(Land Allocation - $57,460)
(Design & Contingencies - $403,280)
(35) SR 3022 over Brush Creek, Cranberry Township, Bridge Replacement, Bridge Key 8094, Project ID 24790
Project Allocation
1,560,000
(Base Project Allocation - $1,500,000)
(Land Allocation - $10,000)
(Design & Contingencies - $50,000)
(36) SR 3025 over SR 0079, Jackson Township, Bridge Preservation, Bridge Key 46947, Project ID 117126
Project Allocation
1,029,845
(Base Project Allocation - $866,195)
(Land Allocation - $10,150)
(Design & Contingencies - $153,500)
(37) SR 3031 over SR 0422 Eastbound and Westbound, Butler Township, Bridge Replacement, Bridge Key 8109, Project ID 24793
Project Allocation
786,760
(Base Project Allocation - $448,360)
(Land Allocation - $256,000)
(Design & Contingencies - $82,400)
(38) SR 3042 over SR 0079 Southbound, Muddy Creek Township, Bridge Replacement, Bridge Key 7875, Project ID 117126
Project Allocation
5,149,227
(Base Project Allocation - $4,330,977)
(Land Allocation - $50,750)
(Design & Contingencies - $767,500)
(39) SR 3042 over SR 0079 Northbound, Muddy Creek Township, Bridge Replacement, Bridge Key 7874, Project ID 117126
Project Allocation
5,149,227
(Base Project Allocation - $4,330,977)
(Land Allocation - $50,750)
(Design & Contingencies - $767,500)
(40) SR 8005 over Glade Run, Jackson Township, Bridge Replacement, Bridge Key 8333, Project ID 92660
Project Allocation
1,599,546
(Base Project Allocation - $1,599,546)