Section 46. McKean County.
(a) Local Bridges
Local
State
(1) Foster Township, SR 7206 over Bolivar Run, Bridge Replacement, Bridge Key 40075, Project ID 117151
Project Allocation
980,000
(Base Project Allocation - $980,000)
(2) Foster Township, SR 7206 over Tunungwant Creek, Bridge Replacement, Bridge Key 43372, Project ID 117151
Project Allocation
1,610,000
(Base Project Allocation - $1,610,000)
(3) Keating Township, SR 7209 over Potato Creek, Bridge Replacement, Bridge Key 47295, Project ID 117151
Project Allocation
1,190,000
(Base Project Allocation - $1,190,000)
(4) Liberty Township, SR 7211 over Allegheny River, Bridge Replacement, Bridge Key 46456, Project ID 117151
Project Allocation
1,610,000
(Base Project Allocation - $1,610,000)
(5) Wetmore Township, SR 7215 over East Branch of Tionesta Creek, Bridge Replacement, Bridge Key 56866, Project ID 117151
Project Allocation
770,000
(Base Project Allocation - $770,000)
(6) Wetmore Township, T-300 (West Kane Road) over East Branch of Tionesta Creek, Bridge Box Culvert, Bridge Key 56866
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(7) Foster Township, T-369 (Tuna Cross Road) over Tunungwant Creek, Bridge Replacement, Bridge Key 43372
Project Allocation
2,000,000
(Base Project Allocation - $2,000,000)
(8) Smethport Borough, T-378 (Galico Crossing) over Potato Creek, Bridge Replacement, Bridge Key 47295
Project Allocation
1,500,000
(Base Project Allocation - $1,500,000)
(9) Port Allegany Borough, T-415 (Boyer Crossing) over Allegheny River, Bridge Replacement, Bridge Key 46456
Project Allocation
2,000,000
(Base Project Allocation - $2,000,000)
(10) Foster Township, T-531 (Bigley Avenue) over Bolivar Run, Bridge Replacement, Bridge Key 40075
Project Allocation
1,250,000
(Base Project Allocation - $1,250,000)
(11) Foster Township, T-576 (BJ Road) over Foster Brook, Bridge Box Culvert, Bridge Key 25565
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(b) State Bridges
(1) SR 0006 over Branch of Marvin Creek, Hamlin Township, Bridge Replacement, Bridge Key 25214, Project ID 85254
Project Allocation
300,000
(Base Project Allocation - $150,000)
(Land Allocation - $40,000)
(Design & Contingencies - $110,000)
(2) SR 0006 over Sartwell Creek, Liberty Township, Bridge Rehabilitation, Bridge Key 25237, Project ID 85256
Project Allocation
352,600
(Base Project Allocation - $221,800)
(Land Allocation - $20,000)
(Design & Contingencies - $110,800)
(3) SR 0006 over Allegheny River, Liberty Township, Bridge Restoration, Bridge Key 45165, Project ID 110672
Project Allocation
999,000
(Base Project Allocation - $945,000)
(Design & Contingencies - $54,000)
(4) SR 0046 over Branch of Potato Creek, Keating Township, Bridge Replacement, Bridge Key 25257, Project ID 93719
Project Allocation
1,197,121
(Base Project Allocation - $500,000)
(Land Allocation - $125,000)
(Design & Contingencies - $572,121)
(5) SR 0046 over Tunungwant Creek, City of Bradford, Bridge Rehabilitation, Bridge Key 25277, Project ID 116888
Project Allocation
1,206,120
(Base Project Allocation - $1,035,120)
(Design & Contingencies - $171,000)
(6) SR 0059 over Kinzua Creek, Keating Township, Bridge Replacement, Bridge Key 25279, Project ID 91544
Project Allocation
500,000
(Base Project Allocation - $500,000)
(7) SR 0066 over Tributary of West Run, Wetmore Township, Bridge Replacement, Bridge Key 25289, Project ID 116989
Project Allocation
600,000
(Base Project Allocation - $300,000)
(Land Allocation - $100,000)
(Design & Contingencies - $200,000)
(8) SR 0146 over Warner Brook, Hamlin Township, Bridge Replacement, Bridge Key 25292, Project ID 85214
Project Allocation
1,405,440
(Base Project Allocation - $750,000)
(Land Allocation - $100,000)
(Design & Contingencies - $555,440)
(9) SR 0155 over Branch of Portage Creek, Liberty Township, Bridge Replacement, Bridge Key 25298, Project ID 91549
Project Allocation
500,000
(Base Project Allocation - $500,000)
(10) SR 0155 over Annin Creek, Annin Township, Bridge Restoration, Bridge Key 25312, Project ID 68934
Project Allocation
586,000
(Base Project Allocation - $550,000)
(Land Allocation - $6,000)
(Design & Contingencies - $30,000)
(11) SR 0219 over Bolivar Run, City of Bradford, Bridge Replacement, Bridge Key 25348, Project ID 68944
Project Allocation
326,000
(Base Project Allocation - $290,000)
(Land Allocation - $6,000)
(Design & Contingencies - $30,000)
(12) SR 0219 over Foster Brook, Foster Township, Bridge Replacement, Bridge Key 25356, Project ID 88657
Project Allocation
750,000
(Base Project Allocation - $750,000)
(13) SR 0219 over Foster Brook, Foster Township, Bridge Replacement, Bridge Key 25357, Project ID 88658
Project Allocation
750,000
(Base Project Allocation - $750,000)
(14) SR 0246 over Kendall Creek, Foster Township, Bridge Replacement, Bridge Key 25362, Project ID 68946
Project Allocation
486,000
(Base Project Allocation - $450,000)
(Land Allocation - $6,000)
(Design & Contingencies - $30,000)
(15) SR 0246 over Baker Run, Otto Township, Bridge Replacement, Bridge Key 25367, Project ID 81410
Project Allocation
1,933,421
(Base Project Allocation - $1,250,000)
(Land Allocation - $108,879)
(Design & Contingencies - $574,542)
(16) SR 0246 over Kendall Creek, Foster Township, Bridge Preservation, Bridge Key 25362, Project ID 117037
Project Allocation
580,000
(Base Project Allocation - $500,000)
(Land Allocation - $20,000)
(Design & Contingencies - $60,000)
(17) SR 0321 over Tributary of Hubert Run, Kane Borough, Bridge Replacement, Bridge Key 41688, Project ID 109707
Project Allocation
700,000
(Base Project Allocation - $350,000)
(Land Allocation - $100,000)
(Design & Contingencies - $250,000)
(18) SR 0346 over Marilla Creek, Bradford Township, Bridge Replacement, Bridge Key 25409, Project ID 91547
Project Allocation
500,000
(Base Project Allocation - $500,000)
(19) SR 0346 over Meadow Branch, City of Bradford, Bridge Replacement, Bridge Key 25411, Project ID 109705
Project Allocation
700,000
(Base Project Allocation - $350,000)
(Land Allocation - $100,000)
(Design & Contingencies - $250,000)
(20) SR 0346 over Gates Hollow Run, Bradford Township, Bridge Replacement, Bridge Key 25412, Project ID 85232
Project Allocation
1,462,421
(Base Project Allocation - $750,000)
(Land Allocation - $115,000)
(Design & Contingencies - $597,421)
(21) SR 0346 over Foster Brook, Foster Township, Bridge Replacement, Bridge Key 25421, Project ID 85261
Project Allocation
596,480
(Base Project Allocation - $350,000)
(Land Allocation - $62,194)
(Design & Contingencies - $184,286)
(22) SR 0346 over TR 398 and Western New York and Pennsylvania Railroad, Eldred Borough, Bridge Restoration, Bridge Key 25435, Project ID 110671
Project Allocation
2,719,300
(Base Project Allocation - $2,485,000)
(Land Allocation - $92,300)
(Design & Contingencies - $142,000)
(23) SR 0346 over Willow Creek, Corydon Township, Bridge Replacement, Bridge Key 25405, Project ID 85260
Project Allocation
650,400
(Base Project Allocation - $573,000)
(Land Allocation - $20,000)
(Design & Contingencies - $57,400)
(24) SR 0346 over Cobbs Hollow Run, Corydon Township, Bridge Replacement, Bridge Key 25406, Project ID 116860
Project Allocation
660,000
(Base Project Allocation - $500,000)
(Land Allocation - $100,000)
(Design & Contingencies - $60,000)
(25) SR 0446 over Moody Hollow Run, Keating Township, Bridge Replacement, Bridge Key 25439, Project ID 68951
Project Allocation
536,000
(Base Project Allocation - $500,000)
(Land Allocation - $6,000)
(Design & Contingencies - $30,000)
(26) SR 0446 over Branch of Allegheny River, Eldred Township, Bridge Replacement, Bridge Key 25445, Project ID 85264
Project Allocation
640,000
(Base Project Allocation - $120,000)
(Land Allocation - $20,000)
(Design & Contingencies - $500,000)
(27) SR 0446 over Canfield Creek, Eldred Borough, Bridge Replacement, Bridge Key 25447, Project ID 85236
Project Allocation
640,000
(Base Project Allocation - $120,000)
(Land Allocation - $20,000)
(Design & Contingencies - $500,000)
(28) SR 0446 over Carpenter Creek, Eldred Township, Bridge Replacement, Bridge Key 25446, Project ID 116852
Project Allocation
660,000
(Base Project Allocation - $500,000)
(Land Allocation - $100,000)
(Design & Contingencies - $60,000)
(29) SR 0646 over Pennbrook Run, Foster Township, Bridge Replacement, Bridge Key 25460, Project ID 114317
Project Allocation
395,250
(Base Project Allocation - $342,550)
(Land Allocation - $18,700)
(Design & Contingencies - $34,000)
(30) SR 0770 over Sheppard Run, Bradford Township, Bridge Replacement, Bridge Key 25461, Project ID 69481
Project Allocation
500,000
(Base Project Allocation - $500,000)
(31) SR 1002 over Tributary of Potato Creek, Eldred Township, Bridge Replacement, Bridge Key 25470, Project ID 113148
Project Allocation
1,100,000
(Base Project Allocation - $750,000)
(Design & Contingencies - $350,000)
(32) SR 1009 over Tributary of Bell Run, Ceres Township, Bridge Replacement, Bridge Key 25482, Project ID 68959
Project Allocation
336,000
(Base Project Allocation - $300,000)
(Land Allocation - $6,000)
(Design & Contingencies - $30,000)
(33) SR 1011 over Fowler Run, Eldred Township, Bridge Replacement, Bridge Key 25483, Project ID 85269
Project Allocation
360,000
(Base Project Allocation - $200,000)
(Land Allocation - $20,000)
(Design & Contingencies - $140,000)
(34) SR 1011 over Mix Creek, Eldred Township, Bridge Replacement, Bridge Key 25488, Project ID 85253
Project Allocation
1,518,300
(Base Project Allocation - $1,100,000)
(Land Allocation - $53,045)
(Design & Contingencies - $365,255)
(35) SR 1017 over Knapp Creek, Otto Township, Bridge Preservation, Bridge Key 25492, Project ID 117037
Project Allocation
580,000
(Base Project Allocation - $500,000)
(Land Allocation - $20,000)
(Design & Contingencies - $60,000)
(36) SR 1023 over Land, Eldred Borough, Bridge Restoration, Bridge Key 25494, Project ID 110671
Project Allocation
1,110,700
(Base Project Allocation - $1,015,000)
(Land Allocation - $37,700)
(Design & Contingencies - $58,000)
(37) SR 2001 over Smith Run, Sergeant Township, Bridge Replacement, Bridge Key 25497, Project ID 85241
Project Allocation
625,000
(Base Project Allocation - $350,000)
(Land Allocation - $100,000)
(Design & Contingencies - $175,000)
(38) SR 4013 over Bolivar Run, City of Bradford, Bridge Replacement, Bridge Key 25538, Project ID 69304
Project Allocation
614,908
(Base Project Allocation - $400,000)
(Land Allocation - $100,000)
(Design & Contingencies - $114,908)
(39) SR 7206 over Foster Brook, Foster Township, Bridge Replacement, Bridge Key 25565, Project ID 117113
Project Allocation
877,530
(Base Project Allocation - $677,530)
(Land Allocation - $50,000)
(Design & Contingencies - $150,000)