Section 66. Warren County.
(a) Local Bridges (Reserved)
Local
State
(b) State Bridges
(1) Scott Run Road (TR 468) over Scott Run, Conewango Township, Bridge Replacement, Project ID 109399
Project Allocation
300,000
(Base Project Allocation - $300,000)
(2) SR 0027 over Telic Run, Brokenstraw Township, Bridge Replacement, Bridge Key 34000, Project ID 114404
Project Allocation
830,000
(Base Project Allocation - $750,000)
(Design & Contingencies - $80,000)
(3) SR 0062 over Allegheny Railroad, Brokenstraw Township, Bridge Rehabilitation, Bridge Key 34032, Project ID 106585
Project Allocation
435,000
(Base Project Allocation - $160,000)
(Land Allocation - $25,000)
(Design & Contingencies - $250,000)
(4) SR 0346 over Tributary of Allegheny Reservoir, Elk Township, Bridge Replacement, Bridge Key 34058, Project ID 93622
Project Allocation
300,000
(Base Project Allocation - $250,000)
(Design & Contingencies - $50,000)
(5) SR 0426 over Branch of Brokenstraw Creek, Spring Creek Township, Bridge Replacement, Bridge Key 34059, Project ID 74610
Project Allocation
515,000
(Base Project Allocation - $400,000)
(Land Allocation - $40,000)
(Design & Contingencies - $75,000)
(6) SR 1005 over Tributary of Kiantone Creek, Farmington Township, Bridge Rehabilitation, Bridge Key 34103, Project ID 113315
Project Allocation
300,000
(Base Project Allocation - $300,000)
(7) SR 1012 over Conewango Creek, Pine Grove Township, Bridge Rehabilitation, Bridge Key 34116, Project ID 2582
Project Allocation
760,000
(Base Project Allocation - $750,000)
(Design & Contingencies - $10,000)
(8) SR 3011 over Tidioute Creek, Deerfield Township, Bridge Replacement, Bridge Key 34173, Project ID 93623
Project Allocation
350,000
(Base Project Allocation - $300,000)
(Design & Contingencies - $50,000)
(9) SR 4003 over Brokenstraw Creek, Columbus Township, Bridge Rehabilitation, Bridge Key 34198, Project ID 84957
Project Allocation
300,000
(Base Project Allocation - $300,000)