Section 345. Monroe County.
Projects are as follows:
(1) SR 0033, Safety Improvements, PA 33 from SR 0115 to SR 2002, Hamilton and Ross Townships, Project ID 96414
Project Allocation
7,424,505
(Base Project Allocation - $6,234,345)
(Land Allocation - $27,295)
(Design & Contingencies - $1,162,865)
(2) SR 0033, Highway Restoration, SR 0033 Southbound from Northampton County Line to Saylorsburg Exit, Hamilton and Ross Townships, Project ID 113863
Project Allocation
11,035,000
(Base Project Allocation - $11,000,000)
(Land Allocation - $20,000)
(Design & Contingencies - $15,000)
(3) SR 0033, Highway Restoration, PA 33 from US 209 to I-80, Hamilton and Stroud Townships, Project ID 96448
Project Allocation
3,450,000
(Base Project Allocation - $3,000,000)
(Design & Contingencies - $450,000)
(4) SR 0033, Safety Improvements, PA 33 from US 209 to SR 0611, Hamilton and Stroud Townships, Project ID 110456
Project Allocation
5,907,280
(Base Project Allocation - $5,907,280)
(5) SR 0033, Highway Resurfacing, SR 0033 from Northampton County Line Northbound to Saylorsburg Exit, Hamilton Township, Project ID 113864
Project Allocation
300,000
(Base Project Allocation - $300,000)
(6) SR 0033, Safety Improvements, SR 0033 at Saylorsburg Ramps, Hamilton Township, Project ID 97262
Project Allocation
3,500,000
(Base Project Allocation - $3,500,000)
(7) SR 0033, Safety Improvements, SR 0033 at SR 0209 Sciota Ramps, Hamilton Township, Project ID 97264
Project Allocation
3,500,000
(Base Project Allocation - $3,500,000)
(8) SR 0033, Safety Improvements, PA 33 from SR 2002 to SR 2008, Hamilton Township, Project ID 110457
Project Allocation
6,746,474
(Base Project Allocation - $6,746,474)
(9) SR 0080, Highway Reconstruction, I-80 at SR 2017 Interchange, East Stroudsburg and Stroudsburg Boroughs, Project ID 57921
Project Allocation
23,214,529
(Base Project Allocation - $6,222,727)
(Land Allocation - $7,793,322)
(Design & Contingencies - $9,198,480)
(10) SR 0080, Highway Resurfacing, I-80 from SR 0115 (Blakeslee) to I-380 Exits 284 to 293 (Eastbound), Including SR 8004 (Ramp to I-380 Northbound), Jackson, Tobyhanna and Tunkhannock Townships, Project ID 85908
Project Allocation
8,284,435
(Base Project Allocation - $8,284,435)
(11) SR 0080, Safety Improvements, I-80, Segments 2728 to 2824 in Carbon County and Segments 2826 to 3104 in Monroe County, Pocono, Coolbaugh, Kidder, Hamilton, Jackson, Smithfield, Stroud, Tobyhanna and Tunkhannock Townships and Delaware Water Gap, East Stroudsburg, East Side and Stroudsburg Boroughs, Project ID 104433
Project Allocation
2,898,616
(Base Project Allocation - $2,543,616)
(Design & Contingencies - $355,000)
(12) SR 0080, Highway Reconstruction, I-80 from Exit 308 East to Toll Bridge, Smithfield Township and Delaware Water Gap and East Stroudsburg Boroughs, Project ID 97231
Project Allocation
13,690,400
(Base Project Allocation - $10,000,000)
(Land Allocation - $940,400)
(Design & Contingencies - $2,750,000)
(13) SR 0080, Safety Improvements, Various Locations, Tobyhanna Township, Project ID 76443
Project Allocation
505,000
(Base Project Allocation - $388,000)
(Design & Contingencies - $117,000)
(14) SR 0115, Highway Resurfacing, SR 0115 from SR 0209 to Maltese Road, Chestnuthill Township, Project ID 106761
Project Allocation
300,000
(Base Project Allocation - $300,000)
(15) SR 0115, Safety Improvements, SR 0115 in Vicinity of Astolat Road to Sugar Hollow Road, Chestnuthill Township, Project ID 102167
Project Allocation
3,901,208
(Base Project Allocation - $2,200,000)
(Land Allocation - $554,273)
(Design & Contingencies - $1,146,935)
(16) SR 0115, Highway Restoration, PA 115 from SR 4001 (Kukenbaker Road) to Bridge over Tobyhanna Creek, Tobyhanna and Tunkhannock Townships, Project ID 101644
Project Allocation
3,300,000
(Base Project Allocation - $3,300,000)
(17) SR 0115, Highway Restoration, PA 115 from Bridge over Tobyhanna Creek to Luzerne County Line, Tobyhanna Township, Project ID 101675
Project Allocation
1,420,000
(Base Project Allocation - $1,400,000)
(Design & Contingencies - $20,000)
(18) SR 0115, Interchange Improvements, SR 0115 at I-80 Interchange, Tobyhanna Township, Project ID 102578
Project Allocation
1,510,000
(Base Project Allocation - $1,505,000)
(Land Allocation - $5,000)
(19) SR 0115, Roadway Widening, SR 0115 from SR 0903 to Hullman Drive, Tunkhannock Township, Project ID 11645
Project Allocation
10,056,936
(Base Project Allocation - $7,687,580)
(Land Allocation - $755,499)
(Design & Contingencies - $1,613,857)
(20) SR 0191, Highway Restoration, PA 191 from PA 390 to Pike County Line, Barrett and Coolbaugh Townships, Project ID 101670
Project Allocation
3,000,000
(Base Project Allocation - $3,000,000)
(21) SR 0191, Highway Restoration, PA 191 from Northampton County Line to Fifth Street, Stroud Township and Stroudsburg Borough, Project ID 101671
Project Allocation
1,800,000
(Base Project Allocation - $1,800,000)
(22) SR 0191, Highway Restoration, PA 191 from Fifth Street to PA 447, Stroud Township and Stroudsburg Borough, Project ID 101677
Project Allocation
2,300,000
(Base Project Allocation - $2,300,000)
(23) SR 0191, Safety Improvements, Various Locations, Various Municipalities, Project ID 90318
Project Allocation
600,000
(Base Project Allocation - $600,000)
(24) SR 0196, Safety Improvements, SR 0196, Segments 0080 to 0150, Coolbaugh Township, Project ID 116800
Project Allocation
1,255,600
(Base Project Allocation - $635,000)
(Land Allocation - $415,600)
(Design & Contingencies - $205,000)
(25) SR 0196, Safety Improvements, SR 0196 from Intersection with PA 940 to Approximately Intersection with Old Post Road, Coolbaugh Township and Mount Pocono Borough, Project ID 105966
Project Allocation
2,000,000
(Base Project Allocation - $2,000,000)
(26) SR 0209, Highway Restoration, US 209 from SR 3005 (Gilbert Road) to Sciota Hill, Chestnuthill and Hamilton Townships, Project ID 101647
Project Allocation
2,500,000
(Base Project Allocation - $2,500,000)
(27) SR 0209, Highway Restoration, US 209 Business (SR 2012) from Bridge over PA 33 to Stroudsburg High School, Chestnuthill and Hamilton Townships, Project ID 101652
Project Allocation
1,390,000
(Base Project Allocation - $1,390,000)
(28) SR 0209, Highway Resurfacing, SR 0209 from Frable Road to Lesh Road, Chestnuthill and Hamilton Townships, Project ID 95517
Project Allocation
1,170,000
(Base Project Allocation - $500,000)
(Land Allocation - $450,000)
(Design & Contingencies - $220,000)
(29) SR 0209, Safety Improvements, SR 0209 from Gilbert Road to Leslie Drive, Chestnuthill and Polk Townships, Project ID 95518
Project Allocation
11,100,000
(Base Project Allocation - $4,500,000)
(Land Allocation - $5,800,000)
(Design & Contingencies - $800,000)
(30) SR 0209, Roadway Widening, SR 0209 from Brodheadsville to PA 115, Chestnuthill Township, Project ID 88935
Project Allocation
2,315,000
(Base Project Allocation - $2,315,000)
(31) SR 0209, Highway Restoration, SR 0209 from SR 0033 to SR 0080, Hamilton and Stroud Townships, Project ID 107653
Project Allocation
300,000
(Base Project Allocation - $300,000)
(32) SR 0209, Highway Resurfacing, SR 0209 (Hamilton West) from PA 33 to I-80, Hamilton and Stroud Townships, Project ID 96442
Project Allocation
4,300,000
(Base Project Allocation - $3,500,000)
(Land Allocation - $200,000)
(Design & Contingencies - $600,000)
(33) SR 0209, Safety Improvements, SR 0209 from SR 2005 (Schafer School House Road) to Beaver Valley Road, Hamilton and Stroud Townships, Project ID 104432
Project Allocation
7,183,300
(Base Project Allocation - $5,380,000)
(Land Allocation - $160,000)
(Design & Contingencies - $1,643,300)
(34) SR 0209, Highway Resurfacing, SR 0209 (Hamilton West) from East of Lesh Road to PA 33, Hamilton Township, Project ID 95574
Project Allocation
3,670,000
(Base Project Allocation - $3,600,000)
(Land Allocation - $40,000)
(Design & Contingencies - $30,000)
(35) SR 0209, Highway Resurfacing, SR 0209 from Oak Grove Drive to Municipal Drive, Middle Smithfield Township, Project ID 113865
Project Allocation
300,000
(Base Project Allocation - $300,000)
(36) SR 0209, Safety Improvements, SR 0209 from Mount Nebo to Holy Cross Road, Middle Smithfield Township, Project ID 113878
Project Allocation
300,000
(Base Project Allocation - $300,000)
(37) SR 0209, Safety Improvements, SR 0209 from Approximately 100 Feet South of T-542 (Holy Cross Road) to Approximately 90 feet North of SR 2023 (Hollow Road), Middle Smithfield Township, Project ID 95398
Project Allocation
3,980,718
(Base Project Allocation - $1,254,000)
(Land Allocation - $1,150,000)
(Design & Contingencies - $1,576,718)
(38) SR 0209, Highway Resurfacing, US 209 from Municipal Drive to Pike County Line, Middle Smithfield Township, Project ID 101680
Project Allocation
1,220,000
(Base Project Allocation - $1,210,000)
(Design & Contingencies - $10,000)
(39) SR 0209, Safety Improvements, SR 0209 from Municipal Road to Portuguese Lane, Middle Smithfield Township, Project ID 113879
Project Allocation
300,000
(Base Project Allocation - $300,000)
(40) SR 0209, Highway Restoration, US 209 from I-80 to SR 2012, Smithfield Township, Project ID 101649
Project Allocation
1,620,000
(Base Project Allocation - $1,600,000)
(Design & Contingencies - $20,000)
(41) SR 0314, Highway Restoration, PA 314 (Manor Drive) from SR 4009 to PA 611, Pocono and Tobyhanna Townships, Project ID 101648
Project Allocation
980,000
(Base Project Allocation - $980,000)
(42) SR 0380, Intelligent Transportation Systems, I-380 Southbound at Exit 8, Coolbaugh Township, Project ID 97261
Project Allocation
3,000,000
(Base Project Allocation - $3,000,000)
(43) SR 0380, Safety Improvements, I-380 Off Ramp to Tobyhanna Army Depot, Coolbaugh Township, Project ID 105961
Project Allocation
600,000
(Base Project Allocation - $475,000)
(Design & Contingencies - $125,000)
(44) SR 0402, Highway Restoration, PA 402 from US 209 to Pike County Line, Middle Smithfield and Smithfield Townships, Project ID 101668
Project Allocation
3,105,000
(Base Project Allocation - $3,100,000)
(Design & Contingencies - $5,000)
(45) SR 0402, Highway Restoration, Intersection of SR 0402 and Oak Grove Drive, Middle Smithfield Township, Project ID 92001
Project Allocation
1,135,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $55,000)
(Design & Contingencies - $80,000)
(46) SR 0423, Highway Restoration, PA 423 from PA 611 to Wayne County Line, Coolbaugh Township, Project ID 101676
Project Allocation
2,400,000
(Base Project Allocation - $2,400,000)
(47) SR 0447, Highway Restoration, PA 447 (Creek Road) from Bridge over Stony Run to Upper Seese Hill Road, Barrett and Price Townships, Project ID 101662
Project Allocation
310,000
(Base Project Allocation - $310,000)
(48) SR 0447, Highway Restoration, PA 447 (Creek Road) from Upper Seese Hill Road to Pike County Line, Barrett Township, Project ID 101667
Project Allocation
1,295,000
(Base Project Allocation - $110,000)
(Design & Contingencies - $1,185,000)
(49) SR 0447, Highway Restoration, PA 447 (Creek Road) from PA 191 to Bridge over Stony Run, Price and Stroud Townships, Project ID 101660
Project Allocation
330,000
(Base Project Allocation - $330,000)
(50) SR 0447, Highway Restoration, PA 447 from East Brown Street to Wendy's, Smithfield Township and East Stroudsburg Borough, Project ID 101659
Project Allocation
1,700,000
(Base Project Allocation - $1,700,000)
(51) SR 0534, Highway Restoration, PA 534 from SR 0209 to Carbon County Line, Polk Township, Project ID 101650
Project Allocation
2,250,000
(Base Project Allocation - $2,250,000)
(52) SR 0611, Retaining Wall Rehabilitation, PA 611, Segments 0010 to 0060 on Delaware River, Delaware Water Gap Borough, Project ID 96481
Project Allocation
13,000,000
(Base Project Allocation - $10,000,000)
(Land Allocation - $1,000,000)
(Design & Contingencies - $2,000,000)
(53) SR 0715, Safety Improvements, SR 0175, SR 0611 and SR 4004 from 1-80 Exit 298 to I-80 Exit 299, Pocono Township, Project ID 74979
Project Allocation
19,818,500
(Base Project Allocation - $13,800,000)
(Land Allocation - $2,832,500)
(Design & Contingencies - $3,186,000)
(54) SR 0611, Highway Restoration, PA 611 from End of Saint Luke's Hospital to Bridge over Scott Run, Pocono, Hamilton and Stroud Townships, Project ID 101663
Project Allocation
2,300,000
(Base Project Allocation - $2,300,000)
(55) SR 0611, Highway Restoration, PA 611 from Bridge over I-80 to Saint Luke's Hospital at Schafers Schoolhouse Road, Stroud Township and Stroudsburg Borough, Project ID 101645
Project Allocation
1,920,000
(Base Project Allocation - $1,900,000)
(Design & Contingencies - $20,000)
(56) SR 0715, Highway Resurfacing, PA 715 from US 209 to SR 4010 (Mountain Road), Chestnuthill and Jackson Townships, Project ID 101658
Project Allocation
2,120,000
(Base Project Allocation - $2,100,000)
(Design & Contingencies - $20,000)
(57) SR 0715, Highway Restoration, PA 715 from SR 4010 (Mountain Road) to PA 611, Pocono and Jackson Townships, Project ID 101673
Project Allocation
1,620,000
(Base Project Allocation - $1,600,000)
(Design & Contingencies - $20,000)
(58) SR 0715, Intersection Improvements, Intersection of SR 0715 and SR 0611, Pocono Township, Project ID 79473
Project Allocation
19,123,831
(Base Project Allocation - $14,500,000)
(Land Allocation - $2,370,000)
(Design & Contingencies - $2,253,831)
(59) SR 0903, Highway Resurfacing, SR 0903 from Carbon County Line to SR 0115, Tunkhannock Township, Project ID 102438
Project Allocation
540,000
(Base Project Allocation - $500,000)
(Design & Contingencies - $40,000)
(60) SR 0940, Highway Resurfacing, PA 940 from SR 0611 to PA 191, Paradise Township and Mount Pocono Borough, Project ID 101665
Project Allocation
1,639,028
(Base Project Allocation - $1,634,028)
(Design & Contingencies - $5,000)
(61) SR 0940, Highway Restoration, PA 940 from SR 4005 to PA 423, Tobyhanna Township, Project ID 101646
Project Allocation
1,800,000
(Base Project Allocation - $1,800,000)
(62) SR 0940, Highway Restoration, PA 940 from Carbon County Line to SR 4005 (Locust Ridge Road), Tobyhanna Township, Project ID 101678
Project Allocation
1,600,000
(Base Project Allocation - $1,600,000)
(63) SR 1005, Highway Restoration, SR 1005 (Schoolhouse Road) from PA 191 to Manzanedo Road, Middle Smithfield, Price and Stroud Townships, Project ID 101664
Project Allocation
1,360,000
(Base Project Allocation - $1,360,000)
(64) SR 1007, Highway Restoration, SR 1007 (Marshalls Creek Road) from US 209 to Pike County Line, Middle Smithfield, Smithfield and Stroud Townships, Project ID 101681
Project Allocation
2,630,000
(Base Project Allocation - $2,630,000)
(65) SR 1008, Highway Restoration, SR 1008 (Sands Springs Road) from PA 191 to PA 447, Barrett Township, Project ID 101661
Project Allocation
709,000
(Base Project Allocation - $709,000)
(66) SR 2004, Highway Restoration, SR 2004 (Cherry Valley Road) from Bossardsville Road to SR 2012 (Main Street), Hamilton and Stroud Townships and Stroudsburg Borough, Project ID 101672
Project Allocation
2,080,000
(Base Project Allocation - $2,080,000)
(67) SR 2012, Highway Restoration, SR 2012 from Eagle Valley Corner to Marshalls Creek, Smithfield Township, Project ID 101654
Project Allocation
1,200,000
(Base Project Allocation - $1,200,000)
(68) SR 2012, Safety Improvements, SR 2012 from Intersection with Mount Tom Road (Valhalla Drive) to Intersection with Airport Road, Smithfield Township, Project ID 95516
Project Allocation
5,250,000
(Base Project Allocation - $2,500,000)
(Land Allocation - $2,250,000)
(Design & Contingencies - $500,000)
(69) SR 2012, Highway Restoration, SR 2012 from SR 2014 (Washington Street) to Eagle Valley Corner, Smithfield Township and East Stroudsburg Borough, Project ID 101657
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(70) SR 2030, Highway Reconstruction, SR 2030 from SR 0611 to SR 0080, Delaware Water Gap Borough, Project ID 113866
Project Allocation
300,000
(Base Project Allocation - $300,000)
(71) SR 2030, Highway Reconstruction, SR 2030 from SR 0611 to SR 0080, Smithfield Township and Delaware Water Gap Borough, Project ID 113867
Project Allocation
300,000
(Base Project Allocation - $300,000)
(72) SR 3004, Highway Restoration, SR 3004 (Kunkletown Road) from Carbon County Line to SR 2012 (Hamilton South Road), Eldred, Hamilton and Ross Townships, Project ID 101666
Project Allocation
4,160,000
(Base Project Allocation - $4,160,000)
(73) SR 3017, Highway Restoration, SR 3017 (Hamilton South Street) from US 209 to Northampton County Line, Chestnuthill, Hamilton and Ross Townships, Project ID 101674
Project Allocation
2,500,000
(Base Project Allocation - $2,500,000)
(74) SR 3017, Intersection Improvements, Intersection of SR 3017 and SR 2004 (Cherry Valley Road) and Intersection of SR 3017 and SR 3004 (Kunkletown Road), Hamilton and Ross Townships, Project ID 105967
Project Allocation
1,000,000
(Base Project Allocation - $1,000,000)
(75) SR 4002, Highway Restoration, SR 4002 (Long Pond Road) from PA 115 to PA 940, Tobyhanna and Tunkhannock Townships, Project ID 101679
Project Allocation
1,860,000
(Base Project Allocation - $1,860,000)
(76) SR 4013, Highway Restoration, SR 4013 (Gouldsboro Road) from SR 8025 at I-380 Interchange to Wayne County Line, Coolbaugh Township, Project ID 101651
Project Allocation
1,600,000
(Base Project Allocation - $1,600,000)
(77) SR 8004, Safety Improvements, I-81, Mile Markers 108 and 274-277 and I-80/I-380 Interchange, Tunkhannock, Kidder and Frailey Townships, Project ID 116727
Project Allocation
300,000
(Base Project Allocation - $300,000)
(78) Various Routes, Slide Remediation, Various State Routes, Various Municipalities
Project Allocation
1,500,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $250,000)
(Design & Contingencies - $250,000)
(79) Various Routes, All Weather Pavement Markings, Various State Routes, Various Municipalities, Project ID 110035
Project Allocation
300,000
(Base Project Allocation - $300,000)