Section 6. Itemization of redevelopment assistance projects.
Additional capital projects in the category of redevelopment assistance projects for capital grants by the Department of Community and Economic Development, its successors or assigns, authorized under the provisions of the act of May 20, 1949 (P.L.1633, No.493), known as the Housing and Redevelopment Assistance Law, and redevelopment assistance capital projects and to be financed by the incurring of debt are hereby itemized, together with their estimated financial costs, as follows:
Project
Total
Project
Allocation
(1) Adams County
(i) County projects
(A) Construction of the Gettysburg Area School District stadium
500,000
(B) Harrisburg Area Community College, Gettysburg Campus, facility expansion/renovation to increase the availability of academic square footage
3,000,000
(i.1) Carroll Valley Borough
(A) Construction of municipal building and police station
1,300,000
(ii) Cumberland Township
(A) Consolidation and rehabilitation of YWCA facilities, including construction
500,000
(iii) Gettysburg Borough
(A) Construction of the Borough Public Swimming Pool
500,000
(B) Gettysburg College, construction/expansion of existing day-care center to expand capacity for college and community use
1,500,000
(C) Development of the Pathways Innovation Center, including acquisition, demolition, engineering and infrastructure improvements
5,000,000
(iv) Huntington Township
(A) Infrastructure, development, site development, design and construction of buildings related to the construction of a new equestrian facility
20,000,000
(2) Allegheny County
(i) City of Pittsburgh
(A) Construction, infrastructure and related costs for the restoration of the historic New Grenada Theater
1,000,000
(B) Construction, infrastructure and related costs to expand the National Aviary
10,000,000
(C) Construction, infrastructure and related costs for the Pittsburgh Glass Center expansion project
2,000,000
(D) Construction and related costs for the Eighth Street Project in Pittsburgh's Cultural District
30,000,000
(E) Construction and related costs for the renovation and expansion of the Jewish Community Center of Greater Pittsburgh facilities
1,500,000
(F) Acquisition, construction, infrastructure improvements and other related costs for an economic and community development project
5,000,000
(G) Construction and other related costs to expand the UPMC Transplant Center
20,000,000
(H) Construction, infrastructure and other related costs for the expansion of the Pittsburgh Zoo
10,000,000
(I) Acquisition, construction, infrastructure and other related costs for Federal North Federal Hill
3,000,000
(J) Construction, infrastructure and other related costs for City Theatre
2,000,000
(K) Construction, infrastructure and other related costs for an early childhood center at the Western Pennsylvania School for Blind Children
2,100,000
(L) Construction, infrastructure and other related costs for the expansion of Duquesne University
10,000,000
(M) University of Pittsburgh Medical Center, acquisition of land, demolition and construction of a multifaceted biomedical research facility to conduct basic research programs, basic cancer research programs and translational and clinical research
20,000,000
(N) Expansion of the Children's Institute, including acquisition, construction, abatement of hazardous materials and related infrastructure
6,000,000
(O) Construction of a translational research facility
10,000,000
(P) Renovation of brewing and bottling plant, including construction of new building
5,000,000
(Q) Construction of Shaler Area Emergency Services Building
500,000
(R) Expansion and renovation of Children's Institute facility to increase its total bed capacity from 39 to 80 and add five new classrooms and a day hospital program
6,000,000
(S) Construction of building for additional cancer research at University of Pittsburgh Cancer Institute
20,000,000
(S.1) Construction of new facilities for the clinical and research programs at Thomas E. Starzl Transplant Institute, University of Pittsburgh Medical Center
20,000,000
(T) Renovation of laboratories at McGowan Institute for Regenerative Medicine, University of Pittsburgh Medical Center
5,000,000
(U) Infrastructure improvements and construction to include a public entrance from the Central Business District along Braddock Avenue, Braddock Campus, University of Pittsburgh Medical Center
3,000,000
(V) Infrastructure improvements and construction of lab, office and support facilities, Magee-Womens Hospital Research Center, University of Pittsburgh Medical Center
12,500,000
(W) Infrastructure improvements and renovations at the Braddock end of the site for development for clean, industrial, flex and warehousing space at Carrie Furnace Hot Metal Bridge
2,000,000
(X) Infrastructure improvements of Phase II section, Nine Mile Run
5,000,000
(Y) Acquisition, infrastructure improvements and construction, Nanotechnology Building, Carnegie-Mellon University
10,000,000
(Z) Infrastructure improvements, Carnegie Museum, Oakland
1,000,000
(AA) Expansion to include construction, Phipps Conservancy and Botanical Gardens
5,125,000
(BB) Infrastructure improvements and construction of a state-of-the-art exhibition and performing arts center, African-American Cultural Center
10,000,000
(CC) Infrastructure improvements and construction, Armstrong Cork Building Project
500,000
(DD) Infrastructure improvements for mixed-use development, including parking, Fifth and Forbes Corridor Redevelopment
1,000,000
(EE) Infrastructure improvements and construction of two new parking garages, Pittsburgh Technology Center Mixed-Use Development
12,000,000
(FF) Infrastructure improvements, renovations and construction, Duquesne University
10,000,000
(GG) Acquisition, infrastructure improvements and construction of a mixed-use development, including an incubator office building, retail development, residential development with a community center and open space linking to the city trail system, Mt. Ararat Community Renaissance Project
5,000,000
(HH) A mixed-use development, commercial and residential site, site and infrastructure improvements to support existing and new businesses in the business district on Penn and Center Avenues
6,000,000
(II) Construction, infrastructure and other related costs, including parking facilities, as part of the Armstrong Lofts redevelopment project
7,000,000
(JJ) Acquisition, construction, infrastructure and other related costs for the renovation of a historic cultural community center
5,000,000
(KK) Construction and infrastructure improvements of an Entertainment Technology Center, Carnegie Mellon University
250,000
(LL) Construction, renovations and infrastructure improvements, Mt. Washington/Grandview Avenue renovation project
400,000
(MM) Infrastructure improvements and construction, Southwestern Pennsylvania Economic Conversion Center for Green Products and Applied Research
4,000,000
(NN) Acquisition, infrastructure improvements and construction for community development project, Pittsburgh Community Reinvestment Group
7,000,000
(OO) Senator John Heinz Pittsburgh Regional History Center, exhibit construction
1,000,000
(PP) Soldiers and Sailors Museum, capital improvements and renovation of facility, including auditorium improvements, roof replacement, elevator and exterior and electrical upgrades
5,250,000
(QQ) University of Pittsburgh Medical Center, Kelly Building renovation project, McKeesport, to accommodate expansion of the Nursing School, oncology services and physician offices
1,000,000
(RR) City of Pittsburgh Development Project, acquisition, site preparation and infrastructure
250,000
(SS) Manchester Thomas and Betts Redevelopment, infrastructure improvements and construction for the redevelopment of a brownfield
1,500,000
(TT) Gage Building Adaptive Reuse, infrastructure improvements and construction
2,000,000
(UU) Pittsburgh Mercy Health System, construction and renovation of existing structures for an integrated interventional surgical suite for the treatment of stroke patients at Mercy Hospital
2,000,000
(VV) Pittsburgh Mercy Health System, construction and renovation of existing structures to expand ICU capacity at Mercy Hospital
7,000,000
(ii) County projects
(A) Improvements to SPC Regional Enterprise Tower, including construction and infrastructure
3,750,000
(B) Expansion of the St. Clair Hospital emergency department, including construction of a building that will house additional health care services in Mt. Lebanon
10,000,000
(C) Expansion and renovation of the Alle-Kiski Medical Center's Emergency Department
5,000,000
(D) Renovations at the Woods Run, Hill District and East Liberty facilities, Carnegie Library, Neighborhood Library Revitalization Program
7,500,000
(E) Renovation and rehabilitation, including infrastructure improvements of the County Health Building
4,000,000
(F) Acquisition, infrastructure improvements and construction of the County Forensic Laboratory
5,000,000
(G) Acquisition, environmental cleanup and construction, Steel Valley Trail Development
2,000,000
(H) Infrastructure improvements and construction, Point State Park Riverfront Connections
4,650,000
(I) Infrastructure improvements, site preparation and construction for comfort facilities, County Park restorations
1,400,000
(J) Acquisition, infrastructure improvements and renovations at site for brownfield and community redevelopment project
20,000,000
(K) Redevelopment, infrastructure improvements and construction to Edgewater Steel property
1,500,000
(L) Construction and renovation for Hartwood Acres Amphitheatre
300,000
(M) Construction and renovation to Hartwood Acres Mansion
2,500,000
(N) Infrastructure improvements and renovations to an existing manufacturing facility, Blawnox Redevelopment
6,500,000
(O) Residential and commercial development of the former Forest Hills Engineering Center, including site remediation and development, infrastructure improvements and construction
1,000,000
(P) MAGLEV, Advanced Manufacturing and Precision Fabrication of Large Steel Structures and Curved Beam Technology Program, continued and expanded development of efforts in McKeesport to fabricate, test, integrate and certify high-speed guideway beams for commercial availability
14,000,000
(Q) MAGLEV, construction of rail production facility
3,000,000
(R) Construction of Harrison Township Community Center
3,000,000
(S) Construction of Pleasant Ridge facility
400,000
(T) Construction of Tarentum Senior Life Center and Wellness Center
1,350,000
(U) Construction of Frazer Hall
2,500,000
(V) Burns Heights revitalization, including infrastructure development and demolition
1,000,000
(W) Hawkins Village infrastructure development, including street resurfacing and curb replacement
500,000
(X) North and South Parks, site preparation and construction for irrigation upgrades for golf courses
1,000,000
(Y) North Park lake, refurbishment of trail
1,200,000
(Z) Allegheny County Community College, acquisition, renovations and construction of a workforce training center facility which will serve as a state-of-the-art training facility focused on technology training and continuing professional education
3,000,000
(AA) Allegheny County Park System expansion, including infrastructure improvements and construction projects
5,000,000
(BB) Allegheny River Towns Enterprise Zone project, acquisition, infrastructure improvements, remediation and construction for redevelopment projects
2,000,000
(CC) Community College of Allegheny County, Siemens Building, Airport West Corridor, renovation and rehabilitation of old Siemens Building for classroom and workforce purposes
8,000,000
(DD) Senior housing project and/or infrastructure in support of senior housing project
4,000,000
(EE) Construction of a World War II Veterans Memorial
1,500,000
(FF) Allegheny County Airport Revitalization Project
2,000,000
(GG) Acquisition, construction, infrastructure and other related costs for Southside Works Garages
5,000,000
(HH) Construction, infrastructure and other related costs to expand and renovate the Lauri Ann West Memorial Library
4,000,000
(II) Construction, infrastructure and other related costs for the Harrison Township Center
1,500,000
(JJ) Construction, infrastructure and other related costs for the Tarentum Life Center
1,050,000
(iii) Bethel Park
(A) Acquisition and construction of a YMCA branch facility in Bethel Park, including related infrastructure
1,000,000
(B) Renovation of Logan School, including construction, abatement of hazardous materials and infrastructure, for redevelopment as a community college facility
3,500,000
(C) Development and construction of an expanded central fire station, which would require renovating and/or replacing the existing building
500,000
(iii.1) Bradford Woods Borough
(A) Woodlands Foundation, Inc., construction/renovation of program facility building
1,000,000
(iv) Carnegie Borough
(A) Acquisition, construction and other related costs for the redevelopment of the Carnegie downtown business district
1,000,000
(iv.1) Collier Township
(A) Construction, infrastructure and other related costs as part of the Prestley Street and Lane Road economic development project
2,000,000
(B) Botanic Garden at Settlers Cabin Park, site preparation and construction of visitor center complex and garden
5,000,000
(iv.2) Dormont Borough
(A) Rehabilitation of Dormont Pool and Recreation Facility
2,600,000
(iv.3) Findlay Township
(A) Dicks Sporting Goods, expansion of headquarters facility
5,000,000
(B) North Field development
8,000,000
(iv.4) Jefferson Hills Township
(A) Jefferson Technology Center, redevelop area for small testing-based business park
3,000,000
(iv.5) City of McKeesport
(A) Auberle, construction/development of a facility to house at-risk children
500,000
(iv.6) Borough of Castle Shannon
(A) Infrastructure improvements, construction and renovation for the development of retail space and parking garages
4,000,000
(iv.7) Forest Hills
(A) Acquisition, infrastructure improvements, construction and renovations, Forest Hills Business District
250,000
(B) Land acquisition, site development and building construction and renovations, Forest Hills multipurpose facility
1,500,000
(iv.8) Jefferson Hills Borough
(A) Construction, infrastructure and other related costs for Jefferson Regional Medical Center improvements
10,000,000
(iv.9) Marshall Township
(A) Tech 21 Marshall Township Trail Network, construction of three miles of new trail, including a lighting system
500,000
(iv.10) Borough of McKees Rocks
(A) Acquisition and infrastructure improvements for manufacturing site, P&LE McKees Rocks
5,000,000
(v) Millvale Borough
(A) Construction, site improvement, site redevelopment and other related costs for the Hillside parking and development project
500,000
(B) Acquisition, construction and other related costs to redevelop North Avenue and Grant Avenue
500,000
(C) Construction, abatement and other related costs for the redevelopment of 301 North Avenue
500,000
(D) Millvale Community Center, infrastructure improvements, renovations and construction
1,000,000
(vi) Monroeville Borough
(A) Construction and related costs for a recreation and cultural community center
5,000,000
(B) Construction and renovation for expanded inpatient and outpatient clinical programs for Western Pennsylvania Hospital-Forbes Regional Campus
2,000,000
(C) Monroeville Community Center Aquatic Center, construction
2,000,000
(D) Boyce Park, site preparation and construction of new ski lifts and cabling
1,500,000
(vi.1) Moon Township
(A) Clinton Industrial Park, Phase II, construction of five pad-ready industrial sites with infrastructure
2,000,000
(B) The Film Factory, construction of two sound stages and state-of-the-art special effects and digital editing equipment and digital picture exchange camera equipment
13,900,000
(vi.2) Mt. Lebanon Borough
(A) Expand emergency department, expansion of outpatient and endoscopy procedures at St. Clair Hospital
10,000,000
(B) Construction of the Center for Compassionate Care
400,000
(C) McNeilly Road Recreation Center, construction of an athletic facility
300,000
(vi.3) Neville Township
(A) Redevelopment of brownfield site, including acquisition, demolition and remediation for light industrial and commercial expansion, Neville Crossing project
3,000,000
(vi.4) McKeesport
(A) Regional hydroponic and agricultural greenhouse, construction
3,000,000
(B) Riverfront development project, acquisition, infrastructure improvements and construction for recreation, commercial and residential uses
3,750,000
(C) Impact McKeesport Downtown Revitalization project, acquisition, rehabilitation, renovation, demolition and construction of the downtown, including former industrial sites and the commercial business district
6,250,000
(vi.5) Munhall Borough
(A) Infrastructure improvements and construction for Battle of Homestead historic site
5,000,000
(B) West field renovation
1,000,000
(vi.6) New Kensington
(A) River Line development, relocation and reconstruction of existing businesses and infrastructure improvements
10,000,000
(vi.7) North Versailles
(A) Construction of a new truck bay for the North Versailles Volunteer Fire Department
1,000,000
(vii) O'Hara Township
(A) Construction and renovation of Lauri Ann West Memorial Library
1,000,000
(vii.1) Penn Hills
(A) Penn Hills cement plant, acquisition, infrastructure improvements and rehabilitation of a former concrete plant
5,000,000
(viii) Plum Borough
(A) Construction and related costs for the Plum Senior Community Center
1,000,000
(ix) Reserve Township
(A) Acquisition, construction and other related costs for a municipal building
500,000
(ix.1) Richland Township
(A) Construction of a special needs playground at Pine Richland Youth Center
500,000
(x) Ross Township
(A) Construction and other related costs to expand the Ross Township emergency management building
500,000
(B) Site development and construction of an emergency management facility to include emergency-related equipment storage
750,000
(xi) Scott Township
(A) Acquisition, construction and other related costs for improvements to the Brookview Avenue neighborhood
1,000,000
(xii) Sewickley Borough
(A) Expansion and renovation of Sewickley Valley Hospital emergency room, including construction and related infrastructure
4,000,000
(B) Family Guidance, expansion of camp for at-risk youth to increase capacity of children served
250,000
(C) Sewickley Valley Hospital, renovation and expansion of the emergency department
4,000,000
(xiii) Shaler Township
(A) Acquisition, construction, infrastructure and other related costs for the Shaler Area EMS headquarters
500,000
(xiv) Sharpsburg Borough
(A) Construction and other related costs to renovate the Linden Gym to include a public library
500,000
(xiv.1) Swissvale
(A) Renovations to Carrie Furnaces former steel mill, for national historic site
15,000,000
(xv) Upper St. Clair Township
(A) Redevelopment and construction for the development of the Boyce Mayview Park, including infrastructure
5,000,000
(B) Expansion of the Upper St. Clair Township Volunteer Fire Department, including acquisition, construction and related infrastructure
1,500,000
(xvi) Urban Redevelopment Authority of Pittsburgh
(A) Acquisition, construction, infrastructure, abatement and other related costs for neighborhood development in the City of Pittsburgh
10,000,000
(B) Construction, infrastructure and other related costs for a public market place
5,000,000
(C) Rehabilitation and replacement of the Allegheny riverwall and construction of public infrastructure and amenities along the Allegheny River
2,000,000
(D) Streetscape improvements, industrial/commercial site development and other capital revitalization activities to promote economic development in the Strip District
6,000,000
(E) South Hills High School and other closed school buildings, acquisition, construction, abatement of hazardous materials, redevelopment and related infrastructure
5,000,000
(F) Construction, infrastructure, environmental remediation and redevelopment costs associated with mixed-use and commercial development in the Fifth, Forbes and Wood Street corridors, Fifth Avenue District
60,000,000
(G) Redevelopment and related infrastructure improvements to produce terminal
5,000,000
(H) New construction and infrastructure improvements, South Shore Riverfront Park
3,500,000
(I) Acquisition, site and infrastructure improvements, environmental remediation and construction, South Hills High School
5,000,000
(J) Construction, renovations and infrastructure improvements, Beechview business district redevelopment
250,000
(K) Construction, infrastructure improvements and renovations, West End-Elliott business district redevelopment
250,000
(L) Nine Mile Run Phase II and Phase III, site preparation, infrastructure and development of housing units in the Summerset housing development, City of Pittsburgh
20,000,000
(M) South Side Works infrastructure and parking, construction, infrastructure, environmental remediation and redevelopment
10,000,000
(N) Former Nabisco Plant rehabilitation project, including acquisition, infrastructure and construction
5,000,000
(O) Pittsburgh Abandoned Property Management Project, including acquisition, infrastructure improvements and construction
25,000,000
(P) Bryant Street, Highland Park Business District rehabilitation, acquisition, infrastructure improvements and construction
1,000,000
(Q) Southwestern Pennsylvania Center for Economic Conversion Center for High Performance, acquisition, infrastructure improvements and construction
4,000,000
(xvii) Hampton Township
(A) Redevelopment and restoration of a historic facility
500,000
(xviii) Verona Borough
(A) Steel City Rowing Boathouse project, development of riverfront trails and acquisition and construction for regional riverfront rowing facility
500,000
(xix) Wilmerding Borough
(A) Acquisition and development of Wilmerding Castle to provide for educational and tourism attractions and commercial tenants
1,500,000
(3) Armstrong County
(i) County projects
(A) Renovations to the former county jail for conversion to a document storage center
1,000,000
(B) Construction and equipment for new facility for 911 center relocation
1,500,000
(C) Site preparations to create ready sites for an industrial park facility
1,500,000
(D) Renovate former IUP Kittanning campus
2,000,000
(E) Kittanning Borough Downtown Redevelopment, redevelopment of downtown area, including construction and related infrastructure improvements
3,000,000
(F) Redevelopment and rehabilitation of Armsdale office complex
1,500,000
(i.1) Apollo Borough
(A) Apollo brownfield project, infrastructure improvements and renovations
1,250,000
(ii) Freeport Borough
(A) Redevelopment of the downtown area, including environmental remediation, construction and related infrastructure
2,500,000
(iii) Kiskiminetas Township
(A) Construction of township building, including acquisition and environmental remediation of land
1,000,000
(iv) Manor Township
(A) Acquisition of land and construction of township building, including related infrastructure
500,000
(v) Ford City
(A) Renovation of the downtown area of Ford City, including construction and related infrastructure
550,000
(4) Beaver County
(i) County projects
(A) Acquisition, construction, infrastructure and other related costs for the Beaver County Conference Center
10,000,000
(B) Construction and related costs for the renovation and expansion of The Medical Center - Emergency Room
3,000,000
(C) Acquisition, construction, infrastructure and other related costs for the Beaver development project
5,000,000
(D) Acquisition, construction and infrastructure improvements and other related costs for an economic and community development project
5,000,000
(E) Expansion of the Beaver County YMCA
2,000,000
(F) Construction, infrastructure and other related costs to rehabilitate and restore the recreation and cultural center in Center Township
7,000,000
(ii) City of Aliquippa
(A) Acquisition, construction, infrastructure and other related costs for the Aliquippa development project
5,000,000
(B) Renovations to Aliquippa Community Hospital
600,000
(iii) Ambridge Borough
(A) Acquisition, construction, infrastructure and other related costs for the Ambridge development project
5,000,000
(iv) Beaver Borough
(A) Construction and related costs for a county administration building
3,000,000
(v) City of Beaver Falls
(A) Acquisition, construction, infrastructure and other related costs for the Beaver Falls development project
5,000,000
(vi) Bridgewater Borough
(A) Acquisition, construction, infrastructure and other related costs for the Bridgewater development project
5,000,000
(vi.1) Center Township
(A) Infrastructure and renovations for the Beaver Valley Intermediate Unit No.27
1,400,000
(vii) Chippewa Township
(A) Acquisition, construction, infrastructure and other related costs for the Chippewa Township development project
5,000,000
(viii) Darlington Township
(A) Acquisition, construction, infrastructure and other related costs for the Darlington Township development project
5,000,000
(ix) East Rochester Borough
(A) Acquisition, construction, infrastructure and other related costs for the East Rochester development project
5,000,000
(x) Economy Borough
(A) Acquisition, construction, infrastructure and other related costs for the Economy development projecy
5,000,000
(xi) Freedom Borough
(A) Acquisition, construction, infrastructure and other related costs for the Freedom development project
5,000,000
(xii) Hopewell Township
(A) Acquisition, construction, infrastructure and other related costs for the Hopewell Township redevelopment project
5,000,000
(xiii) Industry Borough
(A) Acquisition, construction, infrastructure and other related costs for the Industry redevelopment project
5,000,000
(xiv) Midland Borough
(A) Acquisition, construction, infrastructure and other related costs for the Midland development project
5,000,000
(B) Site acquisition, site improvement and site cleanup of Midland industrial sites. This project shall be construed as a supplement to the project authorized in section 6(4)(xi)(A) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Itemization Act of 2003-2004.
5,000,000
(xv) Monaca Borough
(A) Acquisition, construction, infrastructure and other related costs for the Monaca development project
5,000,000
(xvi) New Brighton Borough
(A) Acquisition, construction, infrastructure and related costs for a materials technology center
1,000,000
(B) Acquisition, construction, infrastructure and other related costs for the New Brighton development project
5,000,000
(xvii) New Sewickley Township
(A) Construction and infrastructure costs related to the New Sewickley Township municipal building expansion project
3,500,000
(xviii) Ohioville Borough
(A) Acquisition, construction, infrastructure and other related costs for the Ohioville development project
5,000,000
(xix) Rochester Borough
(A) Acquisition, construction, infrastructure and other related costs for the Rochester development project
10,000,000
(xx) Rochester Township
(A) Acquisition, construction, infrastructure and other related costs for the Rochester Township development project
5,000,000
(xxi) Shippingport Borough
(A) Acquisition, construction, infrastructure and other related costs for the Shippingport development project
5,000,000
(xxii) South Beaver Township
(A) Acquisition, construction, infrastructure and other related costs for the South Beaver Township development project
5,000,000
(xxiii) Vanport Township
(A) Acquisition, construction, infrastructure and other related costs for the Vanport Township development project
5,000,000
(5) Bedford County
(i) County projects
(A) Bedford Area School District, renovation of the high school auditorium, including construction, and construction of restroom facilities at the track/soccer complex
1,500,000
(B) Construction of Bedford County Business Center II, a second multitenant building
1,500,000
(C) Additional funds for redevelopment, rehabilitation and renovation of Bedford Springs Hotel and Resort, Phase II. This project shall be construed to be a supplement to the project itemized in section 6(5)(i)(A) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
5,000,000
(ii) Bedford County Development Association
(A) Development of the Everett Business Park Biotechnology Center
5,000,000
(B) Construction of a multitenant building in Bedford Business Park
1,500,000
(C) Onsite and offsite infrastructure for Phase II of Business Park II
5,000,000
(iii) Bedford Borough
(A) Development of the National Museum of the American Coverlet
500,000
(6) Berks County
(i) County projects
(A) Acquisition, infrastructure improvements and construction of RiverPlace, RiverPlace Development Corporation
6,270,000
(B) Site acquisition and preparation and construction of new baseball stadium, Reading/Berks County Baseball Stadium
42,000,000
(C) Development of biotech facility at the airport
3,000,000
(D) Acquisition, environmental remediation, rehabilitation, construction, renovation, site improvements and infrastructure as necessary for the redevelopment of various brownfield development sites that are deemed a priority by the county's brownfield development program
2,000,000
(E) Land acquisition and development of sites designated by the county in the Vision 2020 County Comprehensive Plan as appropriate for industrial park development
10,000,000
(ii) Bern Township
(A) Mid-Atlantic Air Museum expansion, including construction
600,000
(B) Construction and infrastructure improvements for a nutrition, wellness and bioresearch industrial park on the grounds of Reading Regional Airport
3,500,000
(C) Berks County Industrial Development Authority, acquisition of land, engineering and cost of developing infrastructure for industrial park to serve industry clusters identified in the Action Plan for Investing in a New Pennsylvania, the ICGR report and the Leak-Goforth study such as those engaged in agri-bio, medical equipment and devices, agro-food processing and shared service on nonaviation land at the Reading Regional Airport along Route 183 called the Reading-Berks Research and Technology Center
5,000,000
(ii.1) Bethel Township
(A) Site preparation, infrastructure improvements and construction to develop site for business development, Bethel Business/Industrial Park
5,000,000
(ii.2) Birdsboro Borough
(A) Land acquisition, environmental remediation, flood control improvements, site development and infrastructure improvements to convert the former Armorcast brownfield site into a mixed-use development of residential, retail and office uses
6,000,000
(ii.3) Cumru Township
(A) American Museum of Veterinary Medicine, acquisition, infrastructure and construction
5,000,000
(ii.4) Exeter Township
(A) Infrastructure development, including traffic and transportation improvements to support the redevelopment of a blighted property into the Exeter Retail Center
5,000,000
(ii.5) Maxatawny Township
(A) Acquisition, site preparation and construction at 222 North Industrial Park
5,000,000
(B) Acquisition and development of multiple acre tract known as the Kutztown Airport site, Kutztown Airport Redevelopment project
7,500,000
(C) Berks County Industrial Development Authority, acquisition of land, engineering and cost of developing infrastructure for business, office and industrial park along Route 222 called the 222 North Industrial Park
5,000,000
(iii) New Morgan Borough
(A) Development of a Smart Growth Community, including construction and abatement of hazardous materials for commercial, industrial and recreational uses
25,000,000
(iii.1) Perry Township
(A) Acquisition, infrastructure development and construction of project along Route 61 to create an industrial park to serve industries engaged in food processing, Food Industry Park
5,000,000
(B) Berks County Industrial Development Authority, acquisition of land, engineering and cost of developing infrastructure for industrial park to serve industries engaged in food processing activities along Route 61, called the Berks County Food Park
5,000,000
(iii.2) City of Reading
(A) Expansion, renovation and construction to create a learning center, creative arts center, teen center and additional office space to Salvation Army Reading Corps Headquarters
500,000
(B) Renovation and expansion of cafeteria and banquet facilities and construction of a multipurpose room to student center, Alvernia College
4,000,000
(C) Construction of a recreational field house and athletic field for college and community uses, Alvernia College
7,500,000
(D) Renovation and construction of building infrastructure, Reading/Berks YMCA building
1,200,000
(E) Acquisition, demolition and site preparation for abandoned buildings to prepare for development
2,000,000
(F) Construction of a multiscreen movie theater
4,000,000
(G) Construction of retail shops and, at GoggleWorks Parking Garage, construction
1,200,000
(H) Acquisition of land, demolition of buildings and construction of GoggleWorks apartments and parking development
6,000,000
(I) GoggleWorks Building 2, construction and expansion to facilitate a children's museum and magnet school for the arts
2,000,000
(J) Apartment and shops development at 3rd quadrant adjacent to the GoggleWorks
3,000,000
(K) Construction of hotel banquet, convention center and parking garage as part of Convention Hotel
15,000,000
(L) Philosopher's Landing amphitheatre
4,000,000
(M) Construction and renovation of former American bank building
2,700,000
(N) Acquisition, demolition, construction and revitalization of Reading's central business district
10,000,000
(O) Acquisition and renovation of buildings
1,600,000
(P) GoggleWorks Neighborhood Lighting Project
1,000,000
(Q) Acquisition and construction of parking project and renovation to Franklin Street Station
4,000,000
(R) Acquisition, demolition and construction of townhouse project
2,000,000
(S) Acquisition, demolition, construction and site development for south Eight Street Factory
1,000,000
(T) Acquisition and renovation of former shoe factory
1,000,000
(U) Acquisition, infrastructure improvements, construction and renovations, Commonwealth Sports Hall of Fame
12,500,000
(V) Development of hotel and parking garage
10,000,000
(iv) Tulpehocken Township
(A) Rehabilitation and construction of the Tulpehocken Elementary School Building
1,000,000
(iv.1) Wyomissing Borough
(A) Conversion of the former Textile Machineworks site into retail, hotel and office complex, including construction
2,000,000
(B) Berks County Industrial Development Authority, conversion of a brownfield site that was the former Textile Machineworks factory into a retail, hotel and office and housing complex along Park Road called Wyomissing Square
3,000,000
(C) Wyomissing Square Project, project development, including environmental cleanup, demolition and site work
3,000,000
(v) Hamburg Borough
(A) Construction of the Reading Company Heritage Museum, including environmental remediation
1,200,000
(B) Downtown Streetscape improvements
500,000
(vi) Berks County Industrial Development Authority
(A) Development of Reading research and development park
20,000,000
(7) Blair County
(i) County projects
(A) Construction of trolley line from Altoona to Bellwood
1,800,000
(B) Expansion of Lower Trail west of Williamsburg to Hollidaysburg Borough, including construction
1,600,000
(C) Redevelopment of Veterans Field, including construction
2,100,000
(D) Redevelopment of facilities damaged by flooding, including infrastructure
1,000,000
(E) Construction of a regional manure digester
10,000,000
(F) ABCD Corporation, construction of a multifunction building in southern Blair County
15,000,000
(G) Land acquisition, site preparation, infrastructure improvements and construction for a recycling plant for manufactured steel
15,000,000
(H) Improvement of the Blair County Ball Park
2,000,000
(I) Renovation and associated construction for the Roaring Spring Nason Hospital
5,000,000
(J) Altoona Regional Health System, facility improvements, including demolition, construction and land/facility acquisition
10,000,000
(ii) City of Altoona
(A) Redevelopment and construction of the Round House and yard
3,800,000
(B) ABCD Corporation, construction of multitenant Class 1 office space
5,000,000
(C) Rehabilitation, reconstruction, improvement and establishment of a mixed-use business facility in the City of Altoona
12,000,000
(iii) North Woodbury Township
(A) Construction of a manure abatement facility
10,000,000
(iv) Roaring Spring Borough
(A) ABCD Corporation, development and construction of a secure papermaking facility
30,000,000
(B) Renovation of Nason Hospital, including necessary costs
8,000,000
(8) Bradford County
(i) County projects (Reserved)
(ii) Athens Borough
(A) Main elementary building adaptive reuse project, acquisition, construction, related infrastructure and other related costs
1,500,000
(iii) North Towanda Township
(A) Expansion of the Zodiaq Complex, including construction
8,000,000
(iv) Towanda Borough
(A) 400 block of Main Street Acquisition, fire damage, restoration redevelopment, acquisition, construction, related infrastructure requirements and other related costs
1,000,000
(9) Bucks County
(i) County projects
(A) Expansion of the Mercer Museum
5,000,000
(B) Construction of a performing arts center at a county-owned parking facility
2,000,000
(C) Construction, renovation and expansion of a 50-bed inpatient unit
7,500,000
(D) Construction, renovation and expansion of a Breast Center at St. Mary Medical Center
2,650,000
(E) Construction, renovation and expansion of the Intensive Care Unit at St. Mary Medical Center
3,900,000
(F) Construction, renovation and expansion of a Heart Center at St. Mary Medical Center
15,000,000
(G) Acquisition of property in conjunction with the new courthouse, including site improvements and construction
500,000
(H) Restoration of the King Library
500,000
(I) Construction of a new facility in Silverdale for Pennridge Community Senior Center
1,000,000
(J) Construction of a prison annex to house State prisoners
8,000,000
(K) Construction of a regional public safety training center
15,000,000
(L) Delaware Valley College, construction of a three-phase sow production facility
5,000,000
(M) Construction, infrastructure and other related costs for the renovation and expansion of Snipes Farms facilities as part of a farm education program
4,550,000
(N) Construction, infrastructure and other related costs for a fire training facility
2,500,000
(O) Acquisition, construction, infrastructure and other related costs for the construction of a new YMCA building
4,000,000
(P) Delaware Valley College, construction of a milk processing plant
5,000,000
(Q) Redevelopment of a Department of Transportation facility to be used for conservation purposes, including acquisition if necessary
3,000,000
(i.1) Bucks County Redevelopment Authority
(A) (Reserved)
(B) Construction of parking garage to be used for visitor parking for the Mercer Museum, James A. Michener Art Museum and the Bucks County Free Library
3,000,000
(C) Port of Bucks County infrastructure improvements, including rebuilding port area work surfaces, dock repair, lighting improvements and installation of a dock fendering system
3,700,000
(D) Construction of import/export ocean-going barge facility, including infrastructure improvements and related construction at the Port of Bucks County, Falls Township
5,500,000
(E) Renovation and expansion of the James A. Michener Art Museum
6,000,000
(F) Implementation of the Bucks County Waterfront Revitalization Plan in Bensalem, Bristol Borough, Bristol Township, Tullytown Borough, Falls Township and Morrisville Borough
20,000,000
(i.2) Bensalem Township
(A) Beautification of Route 13/Bristol Pike to include curbs, sidewalks, lighting, trees and drainage
5,000,000
(i.3) Bristol Borough
(A) Construction of Mill Street parking area for the Delaware Canal Visitors Center
500,000
(i.4) Bristol Township
(A) Newportville Fire Company, construct a new community pavilion and expand current firehouse
100,000
(B) Edgely Industrial Park, fully develop industrial park, including work on lighting, water and sewer network, drainage and roadway improvements
1,000,000
(C) Expansion of the Lower Bucks Hospital
5,000,000
(ii) Hilltown Township
(A) Development of a township park, including redevelopment and related infrastructure
610,000
(iii) Hulmeville Borough
(A) Redevelopment of a Hulmeville historical building, including construction
500,000
(iv) Lower Southampton Township
(A) Construction and/or redevelopment of a building for an indoor recreation and community center. This authorization includes costs for acquisition of land and/or buildings if necessary.
2,000,000
(v) Middletown Township
(A) Acquisition of land and construction of a community center
5,000,000
(B) Construction of the Northern Emergency Services Station to provide emergency services and public works
1,500,000
(C) Construction of a public works facility to include administrative offices, bays for trucks, equipment repair and a truck washing facility
1,500,000
(D) St. Mary Medical Center, construction of a new heart catheterization area, expansion of cancer center and infrastructure improvements
10,000,000
(v.1) Morrisville Borough
(A) Construction of a new engine house for the Morrisville Fire Company
500,000
(vi) Northampton Township
(A) Construction of a new township building
1,000,000
(B) Churchville Nature Center, construction of auditorium, new welcome center and additional instructional space
1,000,000
(vi.1) Quakertown Borough
(A) Streetscape improvements, lighting and crosswalks, Broad Street from Main Street to Hellertown Avenue
1,000,000
(vi.2) Solebury Township
(A) Restoration of the Ingham Springs Dam
1,400,000
(vii) Upper Makefield Township
(A) Renovation of fire company building, including construction
1,000,000
(viii) Warminster Township
(A) Construction of a new firehouse
1,000,000
(ix) Warwick Township
(A) Construction of a new firehouse
1,000,000
(x) Doylestown Borough
(A) Acquisition of property in conjunction with the new courthouse, including site improvements and construction
500,000
(B) Acquisition of the Doylestown Armory
500,000
(xi) Bensalem Township
(A) Construction of soccer and recreational amenities
850,000
(B) Acquisition of additional acreage to add to the Central Park campus
600,000
(C) Construction of an Emergency Services Training Center
1,250,000
(xii) Lower Southampton Township
(A) Expansion of the St. Mary's Hospital, including construction
5,000,000
(xiii) West Rockhill Township
(A) Penn Foundation, Inc., expansion of existing facility and rehabilitation for community services
4,300,000
(xiv) Falls Township
(A) Rehabilitation and related improvements of port area at the former USS Fairless Works site
1,000,000
(10) Butler County
(i) County projects
(A) Acquisition, construction and related costs for Phase II of the Slippery Rock Revitalization Program
1,400,000
(B) Initial infrastructure construction and site development for the Slippery Rock Business Park
1,250,000
(C) Construction of an ice rink, sports complex and exhibition hall
3,000,000
(D) Construction of student services building at Butler County Community College
3,000,000
(E) Construction of the National Character Education Foundation National Headquarters, including necessary costs
12,000,000
(ii) Cranberry Township
(A) Graham Park, development of community park and athletic fields
6,500,000
(B) Cranberry Town Cent
6,000,000
(iii) City of Butler
(A) Center city revitalization project
6,000,000
(iv) Forward Township
(A) Forward Township Business Park, brownfield redevelopment, demolition and construction of new infrastructure
1,500,000
(v) Zelienople Borough
(A) Construction of a family hospitality center and renovation and expansion of existing facilities at Glade Run Lutheran Services main campus
2,500,000
(11) Cambria County
(i) County projects
(A) Construction, infrastructure and other related costs for improvements to the Stoneycreek River Basin
2,000,000
(B) Acquisition, construction, infrastructure and other related costs for a community events and convocation center
10,000,000
(C) Acquisition, construction, infrastructure and other related costs for a new main campus building at the Penn Highlands Community College
9,000,000
(D) Acquisition and construction of a regional technology complex/mixed-use facility with office space and business and educational development activities
500,000
(E) Methane Gas Recovery Project, construction of methane gas recovery and distribution systems
1,000,000
(F) Construction and renovations for a Technology and Workforce Development Center
4,000,000
(ii) City of Johnstown
(A) Acquisition, construction, infrastructure and other related costs for the City Operations Center
5,000,000
(B) Construction, infrastructure and other related costs for a regional technology park
5,000,000
(C) Acquisition, construction, infrastructure and other related costs for a festival park
3,000,000
(D) Acquisition, construction, infrastructure and other related costs for the Art Works project
2,000,000
(E) Acquisition, construction, infrastructure and other related costs for redevelopment of facilities along the Stoneycreek Branch
3,000,000
(F) Cambria Iron Works, construction and rehabilitation of industrial site
600,000
(ii.1) Borough of Northern Cambria
(A) Bigler Square recreation project, demolition, property acquisition and construction
3,000,000
(ii.2) Cresson Township
(A) Mount Aloysius College, construction of a multipurpose facility, community events and convocation center
5,000,000
(ii.3) Ebensburg Borough
(A) Ebensburg Downtown revitalization for acquisition and infrastructure development
1,500,000
(ii.4) Jackson Township
(A) Jackson Township Industrial Park, construction, infrastructure and other related costs
500,000
(ii.5) Loretto Borough
(A) Saint Francis University, demolition and construction of a rural health and wellness science complex
15,000,000
(iii) Richland Township
(A) Acquisition, construction, infrastructure and other related costs for a new main campus building at Penn Highlands Community College
9,000,000
(12) Cameron County
(i) County projects (Reserved)
(ii) Driftwood Borough
(A) Industrial site development
2,000,000
(13) Carbon County
(i) County projects
(A) Construction, infrastructure and other related costs for the renovation of a county office building
1,000,000
(ii) Jim Thorpe
(A) Construction, infrastructure and other related costs for a new borough building
500,000
(iii) Nesquehoning Borough
(A) Construction, infrastructure and other related costs for the Broad Mountain Resort
7,500,000
(iv) Palmerton Borough
(A) Construction, infrastructure, abatement and other related costs for the redevelopment of the former Horsehead Laboratory building
1,500,000
(v) Summit Hill Borough
(A) Construction and other related costs for a new municipal office and fire company building
1,250,000
(vi) Weatherly Borough
(A) Construction, infrastructure, abatement and other related costs to expand the Weatherly Casting and Machine manufacturing facility
500,000
(14) Centre County
(i) County projects
(A) Redevelopment of the downtown area in Philipsburg Borough, including construction
3,000,000
(B) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(ii) Bellefonte Borough
(A) Redevelopment of the downtown area in Bellefonte Borough, including construction and related infrastructure
3,000,000
(iii) Benner Township
(A) Construction, infrastructure and other related costs for Rockview Office Park
6,000,000
(iii.1) Center County Industrial Development Authority
(A) Infrastructure development to support the expansion of Innovation Park
1,300,000
(iv) Centre Hall Borough
(A) Construction of a multipurpose complex to facilitate activities such as Grange Fairs
1,500,000
(B) Construction, infrastructure and other related costs for equestrian center and related facilities
3,200,000
(iv.1) Ferguson Township
(A) Development of the Collaboration of Arts, Social Services and Education Vision (CASE) Center to be located in the State College area, including construction, site improvements, infrastructure and land or facility acquisition
4,900,000
(v) Phillipsburg Borough
(A) Construction and other related costs for the improvement and renovation of intensive care, emergency room and oncology facilities
500,000
(B) Rowland Theatre Project, rehabilitation of historical theatre building
375,000
(v.1) Spring Township
(A) Construction, infrastructure and other related costs for an emergency responder training facility
6,500,000
(vi) State College Borough
(A) Redevelopment of the downtown area in State College Borough, including construction
6,000,000
(vii) Rush Township
(A) Expansion of the Philipsburg Hospital for adult assisted living, including construction, renovation and abatement of hazardous materials
2,550,000
(15) Chester County
(i) County projects
(A) Paoli Hospital, Southwest pavilion expansion project
30,000,000
(B) Coatesville Health and Wellness Center, redevelopment of a city block in the downtown commercial district, including the construction of a mixed-use building and associated demolition
11,000,000
(C) Revitalization of the Worthington Steel brownfield site located at Route 202 south and Route 29, including infrastructure and site improvements. This project shall be construed to be a supplement to the project itemized in section 6(15)(i)(F) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
15,000,000
(D) Redevelopment of the Rebecca Lukens House, including necessary costs
1,000,000
(ii) Charlestown Township
(A) Construction of an emergency operations center, including necessary costs
500,000
(ii.1) Downingtown Borough
(A) Redevelopment of Downingtown Train Station
3,500,000
(B) Construction of a new parking structure in Central Business District
4,000,000
(C) Kardon Park redevelopment
5,000,000
(ii.2) East Whiteland Township
(A) Design and construction and renovation of buildings, including site development and infrastructure improvements at Immaculata University
5,500,000
(ii.3) Kennett Square Borough
(A) Acquisition of a building to consolidate social services, adult education and primary health care
2,000,000
(iii) Parkesburg Borough
(A) Parkesburg Police and Borough Hall acquisition, construction and redevelopment
2,700,000
(iv) Schuylkill Township
(A) Renovation of the Schuylkill School building
500,000
(v) West Chester Borough
(A) West Chester Area Senior Center, design, construction and renovation of buildings, including site development and infrastructure developments
1,250,000
(16) Clarion County
(i) County projects
(A) Clarion County Commerce Center (KOZ), water and sewer infrastructure development
500,000
(B) Acquisition and rehabilitation of railroad to serve industrial sites
20,000,000
(ii) Clarion County Economic Development Corporation
(A) Development of the Knox Industrial Park, including construction and related infrastructure
1,000,000
(B) Construction of the Beaver Creek Dam and related infrastructure
4,000,000
(C) Construction of a new YMCA building
4,000,000
(D) Extension of the Paint Township waterline, including construction and related infrastructure
1,000,000
(17) Clearfield County
(i) County projects
(A) Acquisition, construction and other related costs for Allegheny Custom Forming Systems
3,000,000
(B) Construction and other related costs for the Biomass Conversion Center of Excellence
2,000,000
(C) Construction and other related costs for a new cancer center
3,000,000
(D) Construction, infrastructure and other related costs for the improvement of the Clearfield business area
500,000
(E) Development of a Clearfield County Technology Park
1,000,000
(F) Acquisition, demolition and remediation in the Howe's Leather Brownfield Redevelopment Project
1,000,000
(G) Redevelopment of Howe's Leather Brownfield Project
1,500,000
(H) Develop Sandy Township/DEVELOPAC Industrial Park
2,000,000
(I) Expansion of Clearfield County Professional Office Park
2,000,000
(J) Construction of a conference center
15,000,000
(K) Construction and renovations for expansion of the Clearfield Hospital Urgent Care Center, Decatur Township
500,000
(i.1) Clearfield Borough
(A) Renovate existing YMCA
3,500,000
(B) Renovations of Obstetrics Unit, Clearfield Hospital
2,000,000
(ii) Curwensville Borough
(A) Construction, infrastructure and other related costs for the Sunnyside Ethanol Manufacturing Plant
3,000,000
(B) Construction, infrastructure and other related costs to improve the Curwensville Business Area
500,000
(ii.1) City of DuBois
(A) Development of a regional health information system, including technology upgrades to enable local hospitals and health care providers to track patients in an efficient manner
10,000,000
(iii) Houtzdale Borough
(A) Construction, infrastructure and other related costs for the improvement of the Houtzdale business district
500,000
(iv) Karthaus Township
(A) Construction, infrastructure and other related costs for the River Hill Power Waste Coal Fired Power Plant
15,000,000
(v) Lawrence Township
(A) Acquisition, construction and other related costs for the expansion of the Quality Veneer Corporation
500,000
(B) Construction, infrastructure and other related costs for the development of the Wolf Run Industrial Park
2,000,000
(C) Acquisition, construction and other related costs to develop the former FCI Electronics complex
500,000
(18) Clinton County
(i) County projects
(A) Construction, infrastructure and other related costs to upgrade county facilities
2,339,000
(B) Construction, infrastructure and other related costs to develop a multiuse facility, including a Wrestling Hall of Fame Center
2,200,000
(ii) Bald Eagle Township
(A) Community stadium, infrastructure improvements and construction
1,250,000
(iii) Lock Haven
(A) Clinton County Intergenerational Community Center project, acquisition and construction
2,250,000
(19) Columbia County
(i) County projects
(A) Acquisition, infrastructure development and site preparation for an industrial park. This project shall be construed to be a supplement to the project authorized in section 6(19)(ii)(A) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
3,000,000
(B) Columbia County Agricultural, Horticultural and Mechanical Association, renovation and rehabilitation of stage, track and grandstand
1,000,000
(ii) Berwick Borough
(A) Renovation and rehabilitation of the Berwick YMCA
1,320,000
(20) Crawford County
(i) County projects
(A) Keystone Regional Industrial Park, infrastructure improvements to the industrial park
5,000,000
(B) Development and renovations to Conneaut Lake Park
10,000,000
(C) Crawford County Industrial Park, infrastructure improvements, renovations to existing structures and new construction
3,000,000
(D) Construction and related costs of the Northwestern Pennsylvania Railroad and Tooling Heritage Center
2,000,000
(ii) City of Meadville
(A) Additional funds for the renovation and rehabilitation of buildings located at the former Talon Plant No. 7 for mixed-use development, including demolition
2,000,000
(21) Cumberland County
(i) County projects
(A) Construction of forensic and laboratory facilities
1,750,000
(B) Construction, site improvement, infrastructure improvements and other related costs for a records storage facility
5,000,000
(C) Construction, site improvement, infrastructure improvements and other related costs for rebuilding pedestrian access between Harrisburg City Island and Cumberland County to advance economic development projects
6,300,000
(22) Dauphin County
(i) County projects
(A) Expansion and/or construction of medical facilities, Hershey Medical Center
14,500,000
(B) Expansion, renovation and construction of the Northern Dauphin County YMCA
1,100,000
(C) Development and construction of a new prison facility
50,000,000
(D) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(E) Construction, infrastructure and other related costs to develop a public safety training complex
1,000,000
(F) Construction, infrastructure and other related costs to renovate the Evans Physical Education Center at the Harrisburg Area Community College
5,000,000
(G) Construction, infrastructure and other related costs to expand the McCormick Library at the Harrisburg Area Community College
5,000,000
(H) Acquisition, construction, infrastructure and other related costs for an administrative and technical services building at the Harrisburg Area Community College
5,000,000
(I) Construction, infrastructure and other related costs to expand the Community Center for Technology Arts Building at the Harrisburg Area Community College
5,000,000
(ii) City of Harrisburg
(A) Construction, infrastructure and other related costs for the development of a minority business development center
5,500,000
(B) Construction and development of the South Third Street area, including parking, retail, commercial and industrial activities
13,000,000
(C) Replacement of the deteriorating Dock Street Dam to improve public safety and the passage of migratory fish, to preserve and enhance recreation and waterfront development and to protect existing environmental values. This project shall be construed as a supplement to the authorization in section 6(22)(ii)(M) of the act of October 30, 2002 (P.L.891, No.131), known as the Capital Budget Project Itemization Act of 2001-2002.
15,000,000
(D) Expansion and improvement of Commerce Bank Park, formerly known as Riverside Stadium, and Skyline Sports Complex. This project shall be construed as a supplement to the authorization in section 6(22)(ii)(A) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
4,500,000
(E) Construction, infrastructure and other related costs for the Harrisburg Technology Project
7,900,000
(F) Construction, infrastructure and other related costs to accommodate a major restaurant complex on Harrisburg City Island
950,000
(G) Construction, infrastructure and other related costs for the Paxton Commons warehouse project
4,000,000
(H) Construction, infrastructure and other related costs for an arts cooperative complex with workspaces, classrooms, offices, exhibit space and related facilities
3,000,000
(I) Construction, infrastructure and related costs for the Second Street Corridor Improvement Project
4,750,000
(J) Construction, infrastructure and other related costs for the Mulberry Street Boulevard Project
3,000,000
(K) Construction, infrastructure and other related costs for the Native American - Susquehanna River Exhibit Center
1,500,000
(L) Construction of multilevel parking structures to advance economic development projects
30,000,000
(M) Construction, infrastructure and other related costs for the downtown streetscapes project
17,900,000
(N) Construction, infrastructure, abatement and other related costs to redevelop blighted property
3,000,000
(O) Construction, infrastructure and other related costs to convert an existing warehouse complex into productive commercial reuse
5,000,000
(P) Construction, renovation and infrastructure improvement, Hershey-Harrisburg Capital Region Visitor Information Center
2,000,000
(Q) Sewer line replacement project
780,000
(R) Redevelopment of the Warrington Press Building to create new retail, office and residential opportunities
4,500,000
(S) Upgrade and expansion of advanced wastewater treatment plant and conveyance system
10,000,000
(T) Citywide demolition and hazards removal project
3,000,000
(U) 17th Street Corridor revitalization for commercial and industrial reuse
3,500,000
(iii) Conewago Township
(A) Construction of the Conewago Township Municipal Building
2,000,000
(iv) Derry Township
(A) Construction of a competitive pool and related facility
8,000,000
(iv.1) Greater Middletown Economic Development Corporation
(A) Restoration and renovation of a building containing a historic theater, three storefronts and additional space, including construction and other necessary costs
1,000,000
(iv.2) Halifax Township
(A) Construction and development of an industrial facility
5,000,000
(v) Lower Paxton Township
(A) Construction of the Dauphin County Heroes Grove
2,500,000
(B) Construction, infrastructure and other related costs for an economic development project, including a hotel and retail space
4,000,000
(vi) Lower Swatara Township
(A) Construction and redevelopment of the Meade Heights property, including related infrastructure
5,000,000
(B) Construction of a recreation facility
2,000,000
(C) Meade Heights Redevelopment, site preparation and development
5,000,000
(vi.1) South Hanover Township
(A) Construction of a new township building, including land acquisition
1,500,000
(vii) Steelton Borough
(A) Downtown revitalization project
5,000,000
(viii) Susquehanna Township
(A) Expansion and construction of the Widener University Campus, to improve academic classroom space, increase library space and increase academic support services
25,000,000
(ix) Swatara Township
(A) Construction of a retail complex and related infrastructure
6,000,000
(x) West Hanover Township
(A) Construction of a new township building, including land acquisition
1,500,000
(23) Delaware County
(i) County projects
(A) Construction and development of a new conference/community center at Neumann College
3,000,000
(B) Renovation of Woodcrest Mansion at Cabrini College
5,000,000
(C) Expansion of the Darlington Fine Arts Center, including construction and related infrastructure
500,000
(ii) Aston Township
(A) Construction of a conference and community center at Neumann College
3,000,000
(iii) City of Chester
(A) Construction, rehabilitation and renovation of a multitenant commercial complex
1,450,000
(B) Construction of a School of Nursing building at the Widener University main campus
3,000,000
(iii.1) Chester Redevelopment Authority
(A) Expansion of downtown parking structure
4,000,000
(B) Waterfront infrastructure, public marina and bulkhead upgrades and improvements
5,000,000
(iv) Concord Township
(A) Expansion of the Rachel Kohl Community Library
500,000
(B) Construction of a new field house for the Brandywine Youth Club
600,000
(iv.1) Darby Borough
(A) Acquisition, renovations and new construction of administration offices, recreation building and police department
250,000
(iv.2) Folcroft Borough
(A) Construction of a government and community center
3,000,000
(B) Delmar Drive, street scape enhancements
1,200,000
(C) Rasmussen Square improvements
750,000
(iv.3) Middletown Township
(A) Redevelopment of the Franklin Mint site, including site development, infrastructure improvements and construction of a loop road
10,000,000
(iv.4) Radnor Township
(A) Construction of the Center for Science, Education and Technology, Cabrini College
5,000,000
(v) Ridley Township
(A) Capital improvements to township facilities related to technology upgrades
500,000
(vi) Upland Borough
(A) Crozier Keystone Medical Center, expansion of the Nathan Speare Burn Treatment Center. This project shall be construed as a supplement to the project itemized in section 6(23)(xi)(A) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
3,000,000
(24) Elk County
(i) County projects
(A) Construction and infrastructure improvements related to the Elk Regional Medical Center expansion
4,000,000
(B) Construction, infrastructure improvements and abatement of hazardous materials related to the Fox Township Industrial Park expansion
1,000,000
(ii) Fox Township
(A) Construction and infrastructure improvements related to the Fox Township Community Park
500,000
(iii) City of St. Marys
(A) Construction of mixed-use facility, including parking garage in downtown St. Marys
1,100,000
(B) Construct an addition to Elk Regional Health Center
2,000,000
(C) Downtown redevelopment and streetscape improvement
4,000,000
(D) Construction, infrastructure and other related costs for the Kaulmont Park Community Center
1,000,000
(iv) Johnsonburg Borough
(A) Development of intermodal passenger terminals and an intelligent transportation system
2,000,000
(25) Erie County
(i) County projects
(A) Erie Art Museum, completion of Phase II of museum complex, including land acquisition
6,000,000
(B) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(ii) City of Erie
(A) Renovation and construction of the Jerry Uht Baseball Park
2,000,000
(B) Razing and construction of gymnasium and locker facilities at Strong Vincent High School
2,000,000
(C) Construction of multipurpose, multifaceted northwest Pennsylvania safety and communication facility
4,000,000
(D) Construction, infrastructure and other related costs for the development of the Warner Theater
15,000,000
(iii) City of Corry
(A) Acquisition, construction and redevelopment of an industrial facility and surrounding property, including abatement of hazardous materials
2,000,000
(B) Corry Downtown industrial reuse project
2,000,000
(iv) Erie-Western Pennsylvania Port Authority
(A) Acquisition of new 210-foot high-speed ferry for service between the Port of Erie and Port Dover, Ontario, Canada
5,000,000
(26) Fayette County
(i) County projects
(A) Small Town Revitalization project, including the acquisition, renovation and construction of new and existing buildings and structures in smaller communities
4,000,000
(B) Recreational Park project, including acquisition, renovation and construction of new and existing park facilities
4,000,000
(C) Fayette Bike Trail project, including site acquisition and construction of a hike and bike trail
1,000,000
(D) Fayette County Industrial Park project, including site acquisition and construction of new and existing industrial parks
4,000,000
(E) Fay-Penn Industrial Building project, including the acquisition, renovation and construction of new and existing industrial buildings
4,000,000
(F) Science and Engineering School, demolition, property acquisition, infrastructure improvements, construction and renovation
4,000,000
(G) Fallingwater, facilty and site upgrades
2,000,000
(H) Center for Creative Play, acquisition, construction, infrastructure and other related costs
2,500,000
(ii) City of Uniontown
(A) Parking garage expansion, including site acquisition and construction
4,000,000
(B) Uniontown revitalization project, including site acquisition, demolition, rehabilitation, construction and renovation of new and existing buildings
5,000,000
(C) Acquisition, construction and renovation of new and existing recreation park facilities
1,000,000
(D) Construction and renovation of the Fayette County Courthouse
4,000,000
(E) Uniontown Hospital, site acquisition, construction, renovation and expansion of new and existing buildings
4,800,000
(F) Construction, infrastructure and other related costs for improvements to county fairgrounds and related facilities
1,500,000
(iii) Borough of Brownsville
(A) Brownsville revitalization project, including acquisition, demolition, renovation and construction of new and existing downtown buildings
5,000,000
(B) Construction, infrastructure and other related costs for a Velodrome, including administrative and training facilities
15,000,000
(iv) City of Connellsville
(A) Connellsville revitalization project, including acquisition, demolition, renovation and construction of new and existing buildings in the city
5,000,000
(B) Acquisition, infrastructure improvements and renovations of historic buildings within the downtown business district
1,000,000
(v) Dunbar Township
(A) Acquisition, construction, infrastructure and other related costs for the Fayette County Fairgrounds and farm agency offices
750,000
(vi) North Union Township
(A) University Technology Park expansion project, including site acquisition and construction
3,000,000
(27) Forest County
(i) County projects
(A) Wireless Internet infrastructure development
1,000,000
(28) Franklin County
(i) County projects
(A) Construction of a museum honoring Pennsylvania's forest fire heritage, including acquisition and related infrastructure
5,000,000
(B) Construction of science center at Wilson College
5,000,000
(C) Construction of an Agricultural Services Support Center
1,500,000
(ii) Antrim Township
(A) Construction of a municipal government facility which will encompass township services
3,000,000
(B) Construction of infrastructure related to South Antrim Business Center, including a roadway and water and sewer infrastructure
2,600,000
(iii) Chambersburg Borough
(A) Renovation and construction of the Chambersburg Hospital Bed Tower. This authorization includes necessary costs related to acquisition and infrastructure.
32,000,000
(iv) Waynesboro Borough
(A) Construction of a freestanding outpatient services center for laboratory, radiography, preadmission testing, mammography and administrative services. This authorization includes necessary costs related to acquisition and infrastructure.
12,350,000
(29) Fulton County
(i) County projects (Reserved)
(ii) Fulton Industrial Development Association
(A) Construction of a multitenant complex to house commercial and nonprofit entities
1,000,000
(B) Development of the Fulton County Business Park
1,000,000
(C) Construction of infrastructure to expand Fulton County Business Park
2,000,000
(30) Greene County
(i) County projects
(A) Acquisition, construction and infrastructure improvements and other related costs for an economic and community development project
5,000,000
(B) Infrastructure improvements, construction and renovations to enhance the location as a tourist destination and blacksmith artisan facility, W.A. Young Machine Shop and Foundry
1,000,000
(C) EverGreen Technology Park, Inc., acquisition, infrastructure improvements and construction of a depolymerization facility
6,000,000
(D) Acquisition, infrastructure improvements, construction and renovations, Center for Creative Play
2,500,000
(ii) Franklin Township
(A) Construction and other related costs for the expansion of the Greene County Prison
1,600,000
(B) Acquisition, construction, infrastructure, abatement and other related costs for the Curry Technology Center
1,400,000
(iii) Washington Township
(A) Acquisition, construction, infrastructure and other related costs to develop a coal miner training school
4,300,000
(31) Huntingdon County
(i) County projects
(A) Expansion and construction of the Beeghly Library at Juniata College
10,000,000
(B) Construction and expansion of the Raystown Field Station to provide a learning environment for students and teachers
4,200,000
(C) Expansion of the Juniata College Center for Entrepreneurial Leadership, including construction
2,500,000
(D) Construction of a parking facility on Allegheny Street
2,100,000
(E) Infrastructure improvements to Riverview Business Center
600,000
(ii) Birmingham Borough
(A) The Grier School, construction of a new indoor riding arena
500,000
(32) Indiana County
(i) County projects
(A) Development of a business and industrial park, including acquisition, construction, improvements to an access road and related infrastructure
3,000,000
(B) Expansion of business districts and industrial parks within Indiana County for the development of fiberoptic communication and digital telecommunications capability, including engineering and construction
7,000,000
(C) Acquisition of blighted land in Indiana County, including demolition, environmental remediation and construction of public infrastructure
8,500,000
(D) Construction of a multipurpose business facility located in a Keystone Opportunity Expansion Zone in Indiana County Commerce Park, including site preparation and related infrastructure
4,000,000
(E) Construction of a multitenant facility located in a Keystone Opportunity Improvement Zone in Burrell Township, including acquisition, site preparation, infrastructure improvements and costs related to architecture and engineering
3,000,000
(F) Construction of a multitenant commercial facility located in a Keystone Opportunity Expansion Zone in Center Township, including acquisition, site preparation and related infrastructure
3,000,000
(G) Construction of a multitenant commercial facility located in a Keystone Opportunity Expansion Zone in Center Township, including acquisition, site preparation and infrastructure
5,000,000
(H) Acquisition and redevelopment of a facility near Clymer Borough, including site preparation, infrastructure improvements, construction and costs related to architecture and engineering
3,000,000
(I) Renovations to the Indiana County Fire Academy
500,000
(J) Construction and equipment for health facility for Indiana Regional Medical Center, Institute for Healthy Living
2,252,000
(ii) Indiana County Airport Authority
(A) Runway extension and rehabilitation
2,500,000
(iii) Indiana County Development Corporation
(A) Architectural design and engineering, site preparation, infrastructure improvements and construction of a multipurpose business facility
4,000,000
(B) Acquisition, engineering site preparation for construction of a multitenant facility
4,000,000
(C) Land acquisition and site remediation
5,000,000
(D) Industrial park construction, including acquisition, design and infrastructure improvements
5,000,000
(E) Multitenant facility construction, land acquisition and design
8,000,000
(F) Acquisition and redevelopment of a blighted site for construction of a convention center complex
10,000,000
(33) Jefferson County
(i) County projects
(A) Construction of a conference center
15,000,000
(ii) Borough of Brookville
(A) Industrial site development
2,000,000
(iii) Borough of Punxsutawney
(A) Industrial site development
2,000,000
(B) Punxsutawney Area Hospital, acquisition and installation of picture archiving capabilities in the Diagnostic Imaging Department
1,000,000
(C) Rehabilitation and renovation of the Eberhard Building in downtown Punxsutawney
2,000,000
(iv) Snyder Township
(A) Industrial site development
2,000,000
(v) Union Township
(A) Construction of a commerce park
4,000,000
(34) Juniata County (Reserved)
(35) Lackawanna County
(i) County projects
(A) Lackawanna River Heritage Trail redevelopment, acquisition, design and construct trail facilities
4,000,000
(B) Construction for the expansion of the Robert J. Mellow Center for Athletics and Wellness at Marywood College
1,500,000
(ii) City of Carbondale
(A) Acquisition, construction, infrastructure and other related costs to revitalize the Greater Carbondale YMCA
2,000,000
(B) Construction of Carbondale Parking Garage
3,000,000
(C) The Center for Children's Behavioral Health, Pediatric Medical Services and Autism Services
400,000
(ii.1) Borough of Jessup
(A) Infrastructure and expansion of Valley View Business Park
4,500,000
(iii) City of Scranton
(A) South Scranton revitalization project
500,000
(B) Acquisition, construction and infrastructure improvements and other related costs for an economic and community development project
5,000,000
(C) Lackawanna College and University of Scranton Cooperative Campus project, including demolition, site improvements, renovations and construction
8,500,000
(D) Renovations of the Pennsylvania Gas and Water Building to include development of a Heritage Exhibit Center, Lackawanna Visitors and Convention Bureau and visitors parking area, including acquisition, demolition and construction
3,000,000
(E) University of Scranton, design and construction of a new academic building
15,000,000
(F) Friendship House, construction
1,000,000
(G) Site acquisition, design and construction of new buildings and redesign, rehabilitation and infrastructure improvement to existing buildings for the Scranton Medical School
35,000,000
(H) Demolition, infrastructure and site improvements and construction of parking facility at former Martz bus station
600,000
(I) Saint Peters Square Parking Facility, construction and infrastructure improvements associated with the Saint Peters Square development project
5,000,000
(J) Connell Building redevelopment and other downtown economic and community development initiatives, construction of parking facility to support the redevelopment initiatives of downtown Scranton
4,000,000
(K) Nay Aug Park Wildlife Center expansion, construction and infrastructure improvements
10,000,000
(L) Mixed-use development in downtown Scranton to include the redevelopment of the former Central New Jersey Railroad Station building
10,000,000
(M) Construction, infrastructure and related costs to develop a children's science museum in Nay Aug Park
10,000,000
(N) Lackawanna College for renovations of the Scranton School District administration building on North Washington Street for use as administrative offices, classrooms, technical space area and job training areas for the college
2,500,000
(iv) LaPlume Township
(A) Keystone College, construction of campus wellness and fitness center
4,000,000
(36) Lancaster County
(i) County projects
(A) Demolition, environmental remediation and infrastructure development for Northwest Gateway Development Project
10,000,000
(B) Expansion of the Schreiber Pediatric Rehab Center of Lancaster County, including construction
1,250,000
(C) Expansion of the Philhaven facilities for autism
5,000,000
(D) Construction, infrastructure and other related costs for the Campus of History project
9,000,000
(E) Junior Achievement of Central PA Center, Exchange City and Finance Park, for land acquisition, site preparation, infrastructure improvements and construction of a multipurpose educational facility
3,500,000
(ii) City of Lancaster
(A) Acquisition, construction and infrastructure improvements and other related costs for an economic and community development project
5,000,000
(B) Construction, infrastructure and other related costs for the Nuestra Clinica expansion project
500,000
(C) Construction, infrastructure and other related costs for the renovation of the Crispus Attucks Community Center
1,500,000
(D) Construction, infrastructure and other related costs for the redevelopment of the East King Street corridor, including parking needs
2,500,000
(E) Construction, infrastructure and other related costs for the expansion and improvement of the Brightside Opportunity Center
500,000
(F) Construction, infrastructure and other related costs for the restoration and preservation of the historic Watt & Shand building facade
3,000,000
(G) Construction, infrastructure and other related costs for the Demuth Museum Expansion Project
2,000,000
(H) Construction, infrastructure and other related costs for a Latino cultural center
500,000
(I) Construction, infrastructure and other related costs for improvements to a college of technology in Lancaster City
5,000,000
(J) Construction, infrastructure and other related costs to expand, improve and update the Lancaster Public Library
2,500,000
(K) Rehabilitation and renovation of the Lancaster County Museum of Arts
4,000,000
(L) Construction, infrastructure and other related costs for a family and student center
500,000
(iii) Conoy Township
(A) Acquisition, redevelopment and construction of the Haldeman Mansion and outbuildings, including infrastructure for public use
3,300,000
(iii.1) East Cocalico Township
(A) Site acquisition, renovation, rehabilitation and construction related to the development of the Cocalico Community Center
4,000,000
(iv) Elizabethtown Borough
(A) Renovation of the GEARS Community Center, including construction
725,000
(B) Design and construction and renovation of buildings at Elizabethtown College, including site development and infrastructure improvements
2,250,000
(v) Ephrata Borough
(A) Expansion of the Ephrata Community Hospital Cancer Center, including construction
500,000
(v.1) Lancaster County Airport Authority
(A) Infrastructure and site development for Airport Business Park
2,000,000
(vi) Manheim Township
(A) For construction of the Overlook Library and Community Center
3,000,000
(vii) Millersville Borough
(A) Acquisition and redevelopment of the former Borough Water Pumping Station as an emergency services facility
500,000
(B) Acquisition and construction of a new municipal building facility
1,800,000
(viii) New Holland Borough
(A) Design and construction of the New Holland Recreation Center
2,000,000
(ix) Borough of Columbia
(A) Redevelopment of riverfront
1,000,000
(37) Lawrence County
(i) County projects
(A) Construction and related costs for the Ellwood City Hospital expansion
10,000,000
(B) Acquisition, site development and infrastructure improvements related to the railroad corridor development
20,000,000
(C) Acquisition, site development, infrastructure and construction costs for a mixed-use facility
3,000,000
(D) Jameson Health System, renovation and expansion of emergency services department and surgical suites
13,500,000
(E) Ellwood City Hospital, North Addition Tower expansion project, property acquisition, renovations and construction
1,500,000
(ii) New Castle Borough
(A) Acquisition, site development, infrastructure and construction to redevelop Southside New Castle
2,000,000
(iii) New Wilmington Borough
(A) Renovation of library
2,500,000
(iv) Taylor Township
(A) Construction and other related costs for the West Pittsburg Train Station
1,000,000
(v) Volant Borough
(A) Building acquisition, renovations and streetscape improvements, including parking facilities
1,500,000
(38) Lebanon County
(i) County projects
(A) Blueprint Community Northwest Redevelopment Project
6,500,000
(ii) Annville Township
(A) Annville/Lebanon Valley College, East Main Street streetscape project, including property acquisition, renovation, demolition and construction
3,000,000
(iii) City of Lebanon
(A) Northwest revitalization strategy, including demolition of blighted properties for commercial and residential reuse
4,000,000
(iv) South Londonderry Township
(A) Access improvements to complete Campbelltown Connector, including infrastructure improvements for Springbrook Farms
500,000
(39) Lehigh County
(i) County projects
(A) Redevelopment of J. Birney Crum Stadium
1,000,000
(B) Expansion of Burn Center at Lehigh Valley Hospital
1,000,000
(C) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(D) Schnecksville Community Fair, construction of a convention/exhibition center
1,500,000
(E) Expansion of manufacturing facility, including construction of new buildings/facilities, site acquisition and remediation and infrastructure improvement
4,000,000
(F) Construction of the Discovery Center
1,000,000
(G) For Sacred Heart Hospital, renovation of operating rooms, including necessary costs
1,170,000
(ii) City of Allentown
(A) Expansion of the Allentown campus of St. Luke's Hospital, including cardiac services and emergency room
5,000,000
(B) Construction of a new hospice house for St. Luke's Hospital and Health Network/Visiting Nurse Association of St. Luke's
500,000
(C) Redevelopment and renovation of Good Shepherd Hospital, including acquisition and construction
21,000,000
(D) Allentown Art Museum, for expansion and modernization of the museum facility, including demolition, construction and related infrastructure
2,000,000
(E) Renovation of Sacred Heart Hospital, including construction
500,000
(F) Renovation and systems upgrade of the Allentown YMCA/YWCA
2,000,000
(G) Lehigh Valley Hospital, construction of two arthroscopy/minimally invasive operating rooms
500,000
(H) Sacred Heart Hospital, renovations to laboratory and physical therapy department
800,000
(I) Allentown Patriot Youth Association, stadium renovations
1,000,000
(J) East Side Youth Center, construction of new building
1,000,000
(K) Westminster Village, interior and exterior renovations
1,100,000
(L) Neuweiler property, acquisition, remediation, demolition, infrastructure redevelopment as a mixed-use property
1,500,000
(M) Montex property, acquisition, remediation, site improvements, infrastructure improvements and redevelopment as a mixed-use property
1,500,000
(N) Muhlenberg College, new construction of science facilities to expand academic opportunities and employment readiness for careers in the sciences and research industries
2,000,000
(O) Brownfields at Basin Street and Union Street, remediation, demolition, infrastructure development, redevelopment of old brownfield site as a mixed-use property
2,000,000
(P) Valley Youth House - Camp Fowler, purchase, renovation and development of a 41-acre camp to improve life and educational outcomes for abused, neglected and troubled children
5,000,000
(Q) Downtown Arts District, safety code compliances
5,000,000
(R) Allentown State Hospital, off-site acquisition, remediation, demolition and infrastructure development for redevelopment of more than 80 acres of Allentown State Hospital property for mixed commercial and residential use
5,000,000
(S) Exide property, remediation, site improvements, infrastructure upgrades
5,000,000
(T) Lehigh Landing, acquisition, demolition, remediation, acquisition and infrastructure development of Lehigh Landing property and adjacent industrial, commercial and residential property as mixed-use properties
5,000,000
(U) Redevelopment of Queen City Airport, including acquisition, demolition, remediation and infrastructure development of 200 acres for mixed industrial and commercial use
10,000,000
(V) Good Shepherd Rehabilitation Hospital, renewal of South Allentown Campus to redevelop and improve the facilities and infrastructure at the south Allentown location
26,000,000
(W) Lehigh Valley Dairy, acquisition, remediation, demolition and infrastructure development for redevelopment of several old industrial properties on MacArthur Road (7th Street) in Whitehall Township and the City of Allentown for redevelopment as mixed-use properties
2,000,000
(X) Demolition of existing housing, site preparation and construction of new mixed and affordable income housing located at Hanover Acres, Riverview Terrace in the vicinity of East Linden and Hanover Streets
1,500,000
(Y) Construction and rehabilitation associated with the development of a business incubator and business development center
4,000,000
(ii.1) City of Bethlehem
(A) VIA of the Lehigh Valley, development of Economic Opportunity Network and complex for people with disabilities in the Greater Lehigh Valley
5,000,000
(B) Acquisition, remediation, demolition, safety code compliance and infrastructure development to Martin Towers property
5,000,000
(ii.2) Catasauqua Borough
(A) Acquisition, demolition, remediation and infrastructure development as a mixed use of former Fuller Co. property
5,000,000
(iii) Center Valley
(A) For construction of the Gambet Center at DeSales University
4,000,000
(iv) Emmaus Borough
(A) Construction of a new police facility for the Emmaus Police Department
500,000
(B) Acquisition and renovation of blighted property for use as a community center
750,000
(v) Salisbury Township
(A) Lehigh Valley Hospital and Health Network, expansion of burn center, including construction
1,000,000
(vi) Slatington Borough
(A) Renovation of the municipal and fire buildings, including construction
500,000
(B) Acquisition of land to develop a recreational area
500,000
(C) Acquisition, remediation, demolition and infrastructure development for redevelopment of the Stanwood Mills property
500,000
(vii) Washington Township
(A) Construction of an addition to the municipal building
500,000
(viii) Slatington Borough and Washington Township
(A) Construction of the Slate Heritage Trail in Washington Township and Slatington Borough
1,000,000
(40) Luzerne County
(i) County projects
(A) Construction, infrastructure and related costs for improving the Whitney Point Industrial Park
2,000,000
(B) Acquisition, construction and infrastructure improvements and other related costs for an economic and community development project
5,000,000
(C) Construction and related costs associated for the Junior Achievement business and enterprise center
1,600,000
(D) Construction and related costs for the redevelopment of downtown Edwardsville Borough
1,000,000
(E) Wilkes University, renovations to the Darte Center for the theatre, including handicap accessibility improvements
1,250,000
(F) Wilkes University, upgrade of athletic complex/stadium
2,500,000
(G) Infrastructure improvements and site preparation for Rails with Trails North project from Pittston City to Luzerne and Lackawanna County line
1,200,000
(H) Infrastructure improvements and site preparation for Rails with Trails South project
1,200,000
(I) Acquisition, construction, infrastructure and other related costs for The Lands at Hillside Farms facilities
2,500,000
(J) Construction, Infrastructure and other related costs for the Wilkes-Barre River Commons Project
2,500,000
(K) Construction, infrastructure and other related costs to redevelop and expand an existing commercial area as part of an economic development project in Kingston and Edwardsville Boroughs
500,000
(L) Infrastructure development of former Dyno Nobel lands and surrounding lands, approximately 1,100 acres, located in Jenkins and Pittston Townships
20,000,000
(ii) Ashley Borough
(A) Restoration of Huber Breaker
5,000,000
(iii) City of Nanticoke
(A) Construction, infrastructure, site improvement and other costs related to the development of the Lower Broadway Recreation Complex
1,000,000
(B) Downtown revitalization project
4,000,000
(iv) City of Wilkes-Barre
(A) Selective demolition, renovation, construction, environmental remediation and infrastructure improvements of blighted industrial site into mixed-use facility, Murray Complex, Pennsylvania Avenue
10,000,000
(B) South Main Street mixed-use project
5,000,000
(C) Construction and infrastructure improvements to downtown parking deck
4,000,000
(D) Revitalization, reconstruction and construction of the river commons, riverfront and access to the Susquehanna River
15,000,000
(E) Rehabilitation and infrastructure improvement of the historic Sterling Annex Building, Museum of the Susquehanna
4,000,000
(F) Rehabilitation, expansion, infrastructure improvement and environmental remediation of historic Shriner's Hall
20,000,000
(G) Rehabilitation, infrastructure improvements and environmental remediation of historic railroad station property, Market Street Square
5,000,000
(H) Acquisition, demolition, renovation, environmental remediation, infrastructure development and construction of blighted and abandoned industrial site along Courtwright Street
5,000,000
(I) Construction, infrastructure development and environmental remediation of medical arts/office building, Coal Street Park
7,000,000
(J) Construction and infrastructure improvement of downtown convention headquarters hotel
15,000,000
(K) Renovation, construction and infrastructure improvements of regional Kirby Park along the Susquehanna River
750,000
(L) Construction and infrastructure development, regional sports and nutrition complex
8,000,000
(M) Acquisition, renovation, construction, environmental remediation and infrastructure improvements, including construction of a regional arts center and public green space, 100 Block South Main Street redevelopment project
13,000,000
(N) Acquisition, renovation, rehabilitation, construction, environmental remediation and infrastructure improvements, including construction of existing and vacant properties, first block South Main Street, Phase II
10,000,000
(O) Renovation, construction and infrastructure improvements of Public Square
1,600,000
(P) Clear Brook Inc., construction of new dormitory/kitchen/detoxification building
1,000,000
(Q) Redevelop blighted city park into recreational facility
6,500,000
(v) Dallas Borough
(A) Construction of a technology center
2,500,000
(B) College Misericordia, Assistive Technology Research Institute infrastructure improvements
2,500,000
(vi) City of Pittston
(A) Acquisition, demolition, relocation assistance, public improvements and new parking facilities to Pittston downtown area
9,000,000
(B) WVIA, public television and radio, equipment upgrade
500,000
(C) Property acquisition, infrastructure improvements, construction and renovations, Greater Pittston YMCA
750,000
(vii) Luzerne County redevelopment authority
(A) Infrastructure improvements and design to Avoca Borough Industrial Development
1,500,000
(B) Demolition, infrastructure improvements and rehabilitation to Avoca Borough Blight Removal
1,150,000
(C) Acquisition and rehabilitation of existing building for Swoyersville Police Department
1,100,000
(D) Infrastructure improvements for commercial, industrial or housing area in Swoyersville
1,250,000
(E) Demolition and property acquisition for economic revitalization business expansion project in Plymouth
1,500,000
(F) Infrastructure improvements to Ashley yard industrial expansion
1,500,000
(G) Site preparation and infrastructure improvements to the Sather Building within the Grimes Industrial Park
1,100,000
(H) Construction, infrastructure and other related costs to redevelop a former strip mine
500,000
(41) Lycoming County
(i) County projects
(A) Construction of roads internal to the Muncy Industrial Park Phase III
1,000,000
(B) Construction of water and sewer infrastructure internal to the Muncy Industrial Park Phase II
1,500,000
(C) Construction of new roads internal to the Muncy Industrial Park Phase II
1,000,000
(D) Upgrade to the Jersey Shore Borough's community sewer system, including construction and related infrastructure
2,500,000
(E) Construction of a Nippenose Township community sewer system
1,500,000
(F) Design and construction of water and sewer infrastructure for Muncy Industrial Park Phase III
2,000,000
(G) Construction of a sports complex
4,000,000
(H) Duboistown, community sewer system upgrades
1,000,000
(I) South Williamsport sewer system, community sewer upgrades
1,500,000
(J) Construction of the riverwalk pedestrian bridge
2,500,000
(K) Construction of the white water recreation course
1,000,000
(L) Wellfield improvement project, construction of a water transmission line
4,000,000
(M) Lycoming Creek water line, construction and infrastructure
7,500,000
(N) South Williamsport water tank, construction and infrastructure
1,000,000
(O) Grimesville Road water line, construction of a community water system
500,000
(P) Infrastructure and facilities improvements to the White Deer Recreational Complex
1,000,000
(Q) Improvements to the flood warning system, phase 2, including necessary costs
500,000
(R) Construction of the Church Street Transportation Center
2,000,000
(S) Construction of the Trade and Transit Center
2,000,000
(ii) Brady Township
(A) Design and construction of the Timber Run Industrial Park infrastructure
2,000,000
(iii) Jersey Shore Borough
(A) Construction of an addition to the Jersey Shore Hospital
2,000,000
(iv) Lycoming County Water and Sewer Authority
(A) Construction of a new water system for Fairfield Tules Run Development area
3,000,000
(B) Construction of water and sewer infrastructure internal to the Muncy Industrial Park Phase III
1,000,000
(C) Construction of a new water system for Muncy Industrial Parks
2,000,000
(D) Construction of a new water system for growth corridor surrounding Fairfield business and industrial areas
3,000,000
(E) Construction of a new water system for a Keystone Opportunity Zone and commercial growth areas surrounding Lycoming Mall Interchange
2,000,000
(F) Lycoming County Water and Sewer Authority, construction of a new community sewer system
2,000,000
(v) City of Williamsport
(A) Expansion of the Williamsport Hospital and Medical Center Campus into a regional complex and expansion of the Muncy Valley Hospital and the Divine Providence Hospital, as well as other health care facilities, including acquisition, construction, redevelopment and related infrastructure
20,000,000
(B) Expansion of the James V. Brown Library
1,000,000
(C) Acquisition of a large service facility to serve MH/MR clients
2,000,000
(D) Construction of the Center for Business and Workforce Development at the Pennsylvania College of Technology
1,000,000
(E) Construction of a multipurpose arena and entertainment complex
500,000
(F) Expand trade and transit center
2,500,000
(G) Reconstruction of Reach Road in conjunction with an industrial park
2,400,000
(42) McKean County
(i) County projects
(A) Construction of a biomass steam plant, including acquisition and other necessary costs
10,000,000
(ii) City of Bradford
(A) Impact Bradford II, acquisition, construction, redevelopment and related infrastructure
7,500,000
(43) Mercer County
(i) County projects
(A) Renovation and rehabilitation of buildings in the Reynolds Industrial Park
500,000
(B) Reynolds East Business Park, Phase II infrastructure improvements
750,000
(C) Reynolds East Business Park, construction of multitenant building
2,000,000
(D) Construction of a 200,000-square-foot facility, including land acquisition and site preparation in conjunction with the development of a business park to be located within Mercer County
4,000,000
(E) Development of an industrial park to be located in Mercer County
8,000,000
(ii) Greenville Borough
(A) Renovations to the Passavant Center at Thiel College
2,500,000
(B) Improvements to Academic Center at Thiel College
2,500,000
(C) Development of multiuse site in the borough
2,500,000
(D) Renovations of existing structures on Main Street
2,500,000
(iii) City of Hermitage
(A) Development of a technology, innovation and development center
4,500,000
(iv) City of Sharon
(A) Renovation of the historic Columbia Theater for the Vocal Group Hall of Fame and Museum
5,000,000
(B) Redevelopment of the former Westinghouse Buildings, North Side
20,000,000
(v) Farrell Area School District
(A) Improvements to recreational facilities
1,000,000
(44) Mifflin County
(i) County projects (Reserved)
(ii) Granville Township
(A) Industrial Park Road upgrades
500,000
(B) Development of large-scale park
750,000
(iii) Mifflin County Industrial Development Corporation
(A) Reconstruct and expand the highway access road and improve storm water management to serve the new Mifflin County Industrial Park East
1,000,000
(45) Monroe County
(i) County projects
(A) Infrastructure improvements for commercial and industrial site in Stroud, Coolbaugh, Tobyhanna and Smithfield Townships
8,000,000
(B) Infrastructure improvements for the Pocono Mountains Corporate Center, Coolbaugh Township
3,000,000
(C) Construction of a parking facility
7,000,000
(D) Upgrade of stadium athletic facility for Pleasant Valley High School
1,000,000
(ii) Coolbaugh Township
(A) Pennsylvania Inland Port and Express Business Park, infrastructure and transportation facility improvements
30,000,000
(ii.1) Pleasant Valley School District
(A) Construction, renovation and rehabilitation associated with the Pleasant Valley Stadium Project
2,000,000
(ii.2) Pocono Township
(A) Land acquisition and construction of new campus for Northampton County Area Community College
15,550,000
(iii) Smithfield Township
(A) Acquisition, construction, infrastructure and related costs for the Penn Regional Business Center
18,296,000
(iv) East Stroudsburg
(A) East Stroudsburg University Research and Technology Park Phase I Computer Security Research Center expansion, including construction and infrastructure improvements
5,000,000
(46) Montgomery County
(i) County projects
(A) Construction and related costs for the Upper Merion Middle School community recreation facilities
3,600,000
(B) Expansion and construction of buildings at Montgomery County Farm Park
1,000,000
(C) Construction and other related costs to expand emergency facilities at the Holy Redeemer Health System
3,500,000
(D) Construction of a new facility for the provision of programs for persons with developmental disabilities for ARC of Montgomery County
1,500,000
(E) Renovate an existing campus structure to create a public space to be used to house events for campus and community events at Rosemont College
5,000,000
(F) Bryn Mawr Hospital, expansion of emergency department
10,000,000
(G) Lankenau Hospital, Mother/Baby Center neonatal ICU expansion
3,000,000
(H) Renovation of Goodhart Hall, including construction and infrastructure improvements at Bryn Mawr College
6,000,000
(I) Acquisition, design and construction of new medical center and offices
10,000,000
(J) Construction of police firearms and homeland security training center
2,500,000
(K) Acquisition, construction and infrastructure and other related costs, including streetscape redevelopment for the Abington Gateway Corridor
10,000,000
(L) Arcadia University, development and construction of a campus commons building to house a performing arts theater, student center and parking
20,000,000
(M) Montgomery County Department of Parks and Heritage Services, Cresheim Trail project, including Fairmount Park in Philadelphia
2,500,000
(N) Construction, infrastructure and other related costs for expansion of the Carson Simpson Farm Camp
1,000,000
(O) Construction of an exposition center
19,000,000
(P) Acquisition, design and construction costs for an airport
25,000,000
(ii) Abington Township
(A) Construction and other related costs to upgrade the Manor Junior College dental center
500,000
(B) Construction, infrastructure and other related costs for the renovation and expansion of the Abington YMCA, including pool improvements
1,000,000
(ii.1) Ambler Borough
(A) Construction of a new YMCA facility
5,000,000
(B) Restoration of a landmark historic theater in Ambler for the purpose of preserving this historic building and expanding cultural offerings in the area
500,000
(iii) Cheltenham Township
(A) Acquisition, construction and other related costs to expand the Mobility Rehabilitation Research Center
2,000,000
(B) Restoration, construction and infrastructure improvements of African-American Soldiers Civil War Museum
500,000
(iv) Green Lane Borough
(A) Acquisition and construction of a building for borough services
500,000
(v) Franconia Township
(A) Acquisition of land and construction of a new secondary school
9,500,000
(vi) Hatboro Borough
(A) Enterprise Fire Company of Hatboro, renovation of existing firehouse or construction of new firehouse
1,700,000
(B) Hatboro YMCA, construction of a new youth gymnastics center, exercise studio, wellness center and a multipurpose space for youth and adult classes
2,000,000
(vi.1) Jenkintown Borough
(A) Acquisition and restoration of a landmark historic theater for preservation and expansion
500,000
(B) Construction of new firehouse
500,000
(C) Jenkintown Highway Theater construction and renovations for preservation and expansion
1,000,000
(vi.2) Lansdale Borough
(A) Redevelop former Masonic Hall site for use as a performing arts center
2,200,000
(B) Construction of a parking garage in downtown business district
3,000,000
(vii) Lower Gwynedd Township
(A) Construction of a new facility on the campus of Gwynedd-Mercy College to enhance learning and community service
11,000,000
(vii.1) Lower Merion Township
(A) Improvements and renovations to the Sears Barn building and the center facility in the Riverbend Environmental Education Center
500,000
(B) Construction, infrastructure improvements, renovations and restoration of the central commercial and cultural building in the Bryn Mawr Film Institute
2,500,000
(C) Renovations to parking lot for ADA compliance, natatorium, wellness center and gymnasium, Main Line YMCA
2,000,000
(vii.2) Lower Salford Township
(A) Construction of new facility and infrastructure improvements for economic development at Fretz and Wambold
10,000,000
(vii.3) Marlborough Township
(A) Streetscape improvements on Route 63 in the Village of Sumneytown
2,000,000
(viii) Montgomery County Industrial Development Corporation
(A) Redevelopment of the Keasbey and Mattison Boiler House as a commercial building
5,500,000
(ix) Pennsburg Borough
(A) Expansion of the St. Luke's Hospital and Health Network, including outpatient facilities, operating room, dialysis facilities and emergency vehicle storage
5,000,000
(ix.1) Pottstown Borough
(A) Construction of performing arts center
1,000,000
(B) Purchase of existing facility for conversion into a borough garage
1,500,000
(C) Construction of downtown parking garage
2,000,000
(D) Pottstown Redevelopment Authority, Washington Neighborhood Initiative revitalization project
20,000,000
(x) Springfield Township
(A) Keystone House Project Phase II and Phase III. This project shall be construed as a supplement to the project authorized in section 6(46)(iv)(B) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
1,000,000
(x.1) Upper Dublin Township
(A) Construction of group of homes on the campus of St. Mary's Villa for Children and Families
1,000,000
(B) Acquisition, construction, infrastructure and other related costs for the Upper Dublin Junior Athletic Association Football Field Project
500,000
(x.2) Upper Hanover Township
(A) Infrastructure improvements to support economic expansion on Gravel Pike, including facility expansion
10,000,000
(xi) Upper Merion Township
(A) Construction, infrastructure and other related costs for the Village of Valley Forge
50,000,000
(xii) Upper Moreland Township
(A) Redevelopment of the Willow Grove area, including acquisition, construction and related infrastructure
5,000,000
(xiii) Whitemarsh and Whitpain Townships
(A) Acquisition, construction, infrastructure improvements and other related costs for an economic and community development project
1,000,000
(xiv) Whitpain Township
(A) Acquisition, construction and redevelopment of abandoned commercial property, Butler Pike and Skippack Pike
500,000
(47) Montour County
(i) County projects
(A) Geisinger Health Systems, construction of the Center for Health Research and Rural Advocacy
10,000,000
(48) Northampton County
(i) County projects
(A) Acquisition, construction, infrastructure and related costs for the Northampton County Baseball Stadium
500,000
(B) Construction of the Slate Belt Council of Governments Police Complex
1,710,000
(C) Construction of the Colonial Regional police complex
3,000,000
(D) Construction of Art Park on former Bethlehem Steel Property
25,000,000
(E) Acquisition and construction of Lehigh Valley Business Arts and Education Center
7,500,000
(F) Acquisition, infrastructure and construction of the Lehigh Valley Arena
30,000,000
(G) Construction of Environmental Science and Technology Building at Lehigh University
10,000,000
(H) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(ii) City of Bethlehem
(A) Construction, infrastructure and abatement of hazardous materials and related costs for Eastern Wood Products
5,000,000
(B) Acquisition, construction, infrastructure and other related costs for a wood products fabrication/warehouse/storage facility located on a brownfield site
5,000,000
(C) Construction, infrastructure and other related costs for a science and technology building at Lehigh University
10,000,000
(D) St. Luke's Hospital and Health Network, hospice
400,000
(E) Construction of Arts Park on former Bethlehem Steel property. This project shall be construed to be a supplement to the project itemized in section 6(48)(ii)(N) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
5,000,000
(F) Construction and development of a South Side parking garage in the City of Bethlehem
5,000,000
(G) Northampton Community College, development and improvements to Fowler Center located at the Southside Campus
10,000,000
(H) Acquisition of research facility and construction and other related costs for expansion, conservation and renovation of various historic properties of the Historic Bethlehem Partnership
4,000,000
(I) Redevelop and revitalize existing office space into mixed-use development
5,000,000
(iii) City of Easton
(A) Rehabilitation and expansion of the former Social Security building for job training and community purposes for Project of Easton
500,000
(B) Renovate and revitalize former Pomeroy's Department Store Building for commercial development
5,000,000
(iii.1) Bangor Borough
(A) Acquisition and renovation of existing facility and property to relocate borough offices, police and garage to the downtown
1,500,000
(iv) Bethlehem Township
(A) Construction of a health village related to St. Luke's Hospital to include community and specialty hospitals, medical office buildings, other health care facilities and educational facilities and related infrastructure
22,000,000
(B) St. Luke's Riverfront Health Campus, construction of a building to house medical offices, emergency center, radiology labs, cancer center and other health care units
15,000,000
(C) Construction and site preparation of the Summit Lehigh Valley Project
15,000,000
(D) Northampton County Area Community College, expansion, including acquisition, construction and related infrastructure
1,075,000
(v) West Easton Borough
(A) Renovation and revitalization of former silk mill for community development
9,000,000
(vi) Wilson Borough
(A) Reconstruction and remediation of former Dixie Cup factory for community development
2,500,000
(49) Northumberland County
(i) County projects
(A) Shamokin Area Community Hospital, expansion and renovation of radiological department
1,750,000
(B) Construction and rehabilitation for a veterans' vocational and rehabilitation center for homeless veterans
1,000,000
(ii) Lewis Township
(A) Construction of a new municipal building
500,000
(iii) Lower Mahanoy Township
(A) Expansion of municipal building, including construction
500,000
(iv) Point Township
(A) Expansion of municipal building, including construction
500,000
(v) Upper Mahanoy Township
(A) Expansion of municipal building, including construction
500,000
(vi) City of Sunbury
(A) Redevelopment of the riverfront, including construction and other related costs
10,000,000
(vii) Shamokin Borough
(A) Construction and acquisition of Shamokin/Coal Township Community Center
2,000,000
(50) Perry County
(i) Perry County Industrial Development Corporation
(A) Redevelopment of the former Newport Hotel for a mixed-use facility for commercial and residential purposes, including necessary land acquisition, demolition and the construction of parking facilities
1,000,000
(51) Philadelphia County
(i) City of Philadelphia
(A) Acquisition, construction, infrastructure and related costs for expanding the Maria de los Santos Health Center
1,000,000
(B) Construction, infrastructure and other related costs for the redevelopment of the Youth Entrepreneurship Mall and shopping center
1,000,000
(C) Acquisition, construction, infrastructure improvements and other related costs for an economic and community development project
5,000,000
(D) Redevelopment of the Uptown Theater
2,750,000
(E) Redevelopment of the Waterview Recreation Center and surrounding recreation area
2,000,000
(F) Construction and related costs for the renovation of the Fishtown Recreation Complex, including the Miles Lederer Pool
1,500,000
(G) Construction and related costs for the renovation of Methodist Family Services facilities
2,000,000
(H) Construction and related costs for the South Street improvement project
1,500,000
(I) Acquisition, construction, infrastructure and related costs to develop the Paradise Island Child Center
1,500,000
(J) Construction, infrastructure and related costs for the Cyber Village development project
2,000,000
(K) Construction, infrastructure and other related costs for the Friends Co-op redevelopment project
500,000
(L) Construction and related costs for the redevelopment of ASPIRA
2,500,000
(M) Acquisition, construction and other related costs to expand the Germantown Community Health Services
1,300,000
(N) Construction, infrastructure and related costs to develop the Hunting Park recreation complex
1,000,000
(O) Acquisition, construction and other related costs to expand the Albert Einstein Medical Center
5,000,000
(P) Acquisition, construction, infrastructure and other related costs to expand the Masonic Hall on North Broad Street, including a community center and banquet hall
2,000,000
(Q) Construction of an ambulatory care center at Tenth and Sansom Streets
10,000,000
(R) Construction of a medical education building and parking facility on the north side of Locust Street between Tenth and Eleventh Streets
30,000,000
(S) Acquisition, construction, infrastructure and other related costs to renovate Interim House
2,000,000
(T) Construction, infrastructure and other related costs to redevelop Lower Venice Island
3,500,000
(U) Acquisition, construction, infrastructure and other related costs for a community recreation center at Tenth and Pike Streets
5,500,000
(V) The Torresdale Avenue Revitalization Project
1,000,000
(W) Construction of the First Responders and Allied Health Professional Learning and Training Center
1,300,000
(X) Construction of the Academic and Medical Teaching Center, Albert Einstein Medical Center
5,000,000
(Y) Rehabilitation of the environmental education center, including revitalization, flood control, construction of walking path, bridges and entertainment venues and other improvements to the Pleasant Hill Park
1,000,000
(Z) Construction, infrastructure and other related costs for Robin Hood Dell East
500,000
(AA) Acquisition, construction, infrastructure and other related costs for the Lancaster Avenue Corridor Revitalization Project
2,500,000
(BB) Construction of the Sbarro Health Organization International Research Residence
1,500,000
(CC) Acquisition, construction, infrastructure and other related costs for a preliminary land development and revitalization plan
500,000
(DD) Construction, infrastructure and other related costs to modernize a publicly owned natural gas utilities system in cities of the first class
200,000,000
(EE) Expansion of the Holy Family University School of Business, including construction
5,000,000
(FF) Expansion and construction of the Cardiac Center, the NICU and construction of the new radiology/imaging center and new fetal/special delivery unit at the Children's Hospital of Philadelphia
10,000,000
(GG) Construction and redevelopment of the Eden Hall Chapel in order to establish a school and/or other programs for autistic and special needs children
2,000,000
(HH) Expansion of the Science Center, 3701 Market Street, including construction
2,200,000
(II) Expansion of the Morris Arboretum at the University of Pennsylvania
12,000,000
(JJ) Renovation of the Mann Center for the Performing Arts
2,500,000
(KK) Construction of a community center on the Abraham Lincoln High School campus
1,200,000
(LL) Redevelopment of the Devon Theatre of Performing Arts, including related infrastructure
700,000
(MM) Construction of the Nazareth Academy High School Performing Arts Center
4,000,000
(NN) Construction of facilities at Philadelphia University. This authorization includes necessary funds for expansion and other related costs.
5,000,000
(OO) Construction of Sacred Heart Hospital facilities. This authorization includes necessary funds for expansion and other related costs.
2,500,000
(PP) University of Pennsylvania, renovation of the School of Nursing building
8,000,000
(QQ) University of Pennsylvania, construction of a center for nanotechnology research and development
30,000,000
(RR) University of Pennsylvania, construction of the Biobehavioral Research Center at the School of Nursing
1,000,000
(SS) Renovation of Harrison Auditorium at the University of Pennsylvania Museum of Archeology and Anthropology
2,000,000
(TT) National Constitutional Center, building renovations, repairs, construction and reconstruction of gallery spaces and other improvements, appurtenances and habiliments
4,100,000
(UU) Pennsylvania Ballet, construction of a rehearsal facility with administrative offices and other spaces. This project shall be construed to be a supplement to the project itemized in section 6(51)(i)(O) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
2,500,000
(VV) Infrastructure improvements and renovations to Jewish Community Center
500,000
(WW) Renovations and construction to Lassin Early Learning Center
500,000
(XX) Budd Commerce Center, infrastructure improvements and remediation
1,000,000
(YY) Acquisition and renovations to Sedgwick Theater
2,500,000
(ZZ) Acquisition and renovations of YWCA of Germantown property for neighborhood revitalization
1,000,000
(AAA) Infrastructure improvements and renovations to the Germantown Gateway Center
1,000,000
(BBB) Site preparations, infrastructure improvements and renovations to Pleasant Playground in Mt. Airy
1,000,000
(CCC) Construction and renovations to the Academy of Music
275,000
(DDD) Renovation of Mural Arts Program building
1,000,000
(EEE) Construction of a nondenominational school in APM Ludlow for Hope Partnership for Education
1,500,000
(FFF) Demolition, infrastructure improvements and restoration of retail area for Lawndale Revitalization Project in Olney
5,000,000
(GGG) Infrastructure improvements and renovations for Main Street Revitalization project
1,000,000
(HHH) Infrastructure improvements and construction of Phase I expansion project for Berean Institute
2,000,000
(III) Renovations to retail area on the Avenue of the Arts North
1,000,000
(JJJ) Construction of the Youth Mini Mall
1,000,000
(KKK) Infrastructure improvements and construction of retail center
3,000,000
(LLL) The Slaveship Project, land acquisition and construction of a memorial
250,000
(MMM) Mill Creek Community Transformation Project, renovations and construction
6,000,000
(NNN) The Center for Human Advancement, renovations and construction
5,000,000
(OOO) African Cultural Alliance of North America, acquisition and construction
250,000
(PPP) Saint Joseph's University, construction, renovations and infrastructure improvements
17,115,000
(QQQ) Expansion of the Lutheran Theological Seminary, including construction
9,000,000
(RRR) Philadelphia Housing Authority, infrastructure development associated with the Liddonfield Homes Development Project in the northeast section of Philadelphia. This project shall be construed to be a supplement to the project itemized in section 6(51)(ii)(PPPP) of the act of June 22, 2004 (P.L.257, No.40), known as the Capital Budget Project Itemization Act of 2003-2004.
5,600,000
(SSS) Gaudenzia House, renovation of new facilities, including necessary costs
3,000,000
(TTT) The Salvation Army, construction of the Ray and Joan Kroc Corps Community Center
8,000,000
(UUU) Construction, infrastructure and other related costs to renovate and expand the Magee Rehabilitation Hospital
2,000,000
(VVV) Construction, infrastructure and other related costs to renovate the Germantown YMCA
5,000,000
(WWW) Construction, infrastructure and other related costs to revitalize FDR Park
3,000,000
(XXX) Construction, infrastructure and other related costs for the revitalization of Smith Memorial Playground facilities
2,500,000
(YYY) Acquisition, construction, infrastructure and other related costs for the East Parkside Community Revitalization Project
15,000,000
(ZZZ) Construction, infrastructure and other related costs for a biological response center
5,000,000
(AAAA) Acquisition, demolition, construction, infrastructure and other related costs for the development of a job training facility on the first block of Wolf Street
2,500,000
(BBBB) Acquisition, demolition, construction, infrastructure and other related costs for the development of a job training facility on the 2300 block of South Swanson Street
2,500,000
(CCCC) Acquisition, demolition, construction, infrastructure and other related costs for the development of an educational facility on the first block of Wolf Street
2,500,000
(DDDD) Acquisition, demolition, construction, infrastructure and other related costs for the development of an educational facility on the 2300 block of South Swanson Street
2,500,000
(EEEE) Construction, infrastructure and other related costs to rehabilitate and expand the Eye Institute of the Pennsylvania College of Optometry
6,000,000
(FFFF) Construction of athletic supersite in Southwest Philadelphia to serve public school students and the community at large
750,000
(GGGG) Southwest Belmont Building Rehabilitation Project, infrastructure improvements and renovations
250,000
(HHHH) Legendary Blue Horizon, construction and renovations
4,000,000
(IIII) South Philadelphia Revitalization Corporation, construction of housing units in the vicinity of Snyder and Jackson Streets and Fourth and Sixth Streets. This authorization includes funds for acquisition, demolition, infrastructure and other related costs.
2,000,000
(JJJJ) Summerton Youth Organization, redevelopment of facilities, including necessary costs
500,000
(KKKK) Rehabilitation and construction of the former Conrail Girard Point Yard
1,400,000
(LLLL) Philadelphia Hispanic Chamber of Commerce, construction and renovation of headquarters
4,000,000
(MMMM) Brandywine Workshop Plaza project, including construction
250,000
(NNNN) MANNA, renovations to commercial kitchen and administrative offices
1,000,000
(OOOO) American Woman's Heritage Society for renovation and restoration of the Belmont Mansion in Fairmount Parl
1,000,000
(PPPP) Acquisition, construction, renovation site development and infrastructure improvements for Impact Services facilities
2,250,000
(QQQQ) Rehabilitation of Prince Hall Grand Lodge, including construction and infrastructure improvements
4,000,000
(RRRR) Construction of new buildings, renovation of existing buildings and infrastructure and related costs for the redevelopment of property at the intersection of Roosevelt Boulevard and Bustleton Avenue
3,000,000
(SSSS) Construction and renovation of Sayre Health Clinic
250,000
(TTTT) Chestnut Hill College, land acquisition, site preparation and construction of a new student and community-use facility
4,000,000
(UUUU) The Salvation Army of Greater Philadelphia, construction and acquisition of property to build the Ray and Joan Kroc Corps community center complex
8,000,000
(VVVV) Community Council for Mental Health and Mental Retardation, construction and renovations
5,000,000
(ii) County projects
(A) Construction of new facilities and renovation of existing buildings at the Northern Home for Children and Family Services, including demolition and construction
5,000,000
(B) Expansion of the Evangelical Manor Campus, including construction
7,750,000
(C) Expansion and construction of a facility to house elephants at the Philadelphia Zoo
11,000,000
(D) Construction of the Chinatown Community Center
5,000,000
(E) Construction and other related costs to expand Berean Institute
8,000,000
(F) Construction, infrastructure and other related costs for Memorial Hall
7,500,000
(G) Acquisition, construction, infrastructure and other related costs for the Lancaster Avenue Corridor Revitalization Project Phase 4
2,500,000
(H) Drexel University, construction of a biomedical research tower
15,000,000
(I) Construction of emergency department, including the expansion of existing medical and surgical outpatient facilities to Saint Christopher's Children's Hospital
6,000,000
(J) Construction of a medical education building and parking facility for Thomas Jefferson University
30,000,000
(K) Construction of ambulatory care center for Thomas Jefferson University
10,000,000
(L) Construction of an addition to the Christian Street YMCA
1,500,000
(M) Construction of an addition to the Roxborough YMCA
1,000,000
(N) Construction of an addition to the Columbia North YMCA
1,000,000
(O) Construction, infrastructure and other related costs for a performing arts center
12,500,000
(P) Construction, infrastructure and other related costs for neighborhood improvements located between Fifth and Eleventh Streets and Roosevelt Boulevard and Rockland Street
1,500,000
(Q) Construction, infrastructure and other related costs for the Germantown Avenue Village Restoration Project
500,000
(R) Acquisition, construction, infrastructure and other related costs to revitalize commercial corridors in the Mt. Airy and Chestnut Hill neighborhood
3,000,000
(S) Acquisition, construction, infrastructure and other related costs for the Lancaster Avenue Corridor Revitalization Project Phase 3
2,500,000
(T) Acquisition, construction, infrastructure and other related costs for the Lancaster Avenue Corridor Revitalization Project Phase 2
2,500,000
(U) Acquisition, construction, infrastructure and other related costs for the Bridge Step-Down Project in the historic Parkside section of West Philadelphia
2,350,000
(V) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(W) Construction, infrastructure and other related costs for the Greater Grays Ferry Project
3,000,000
(X) Construction, infrastructure and other related costs to renovate the Philadelphia Opportunities Industrialization Center
600,000
(Y) Construction, infrastructure and other related costs for the revitalization of the North Broad Street and Susquehanna Avenue corridors
1,000,000
(Z) Construction of Northeastern Hospital parking area, including facility demolition and site preparation
7,500,000
(AA) Acquisition, construction, infrastructure and other related costs to expand the West Philadelphia Regional Center of the Community College of Philadelphia
1,200,000
(BB) Magee Rehabilitation Hospital, construction, renovation and expansion
2,000,000
(CC) Temple University Hospital, Episcopal Campus, construction and infrastructure improvements
4,800,000
(DD) Tarken Recreation Center, renovations and infrastructure improvements to ice rink
750,000
(EE) Scanlon Recreation Center, renovations and infrastructure improvements to ice rink
750,000
(FF) Mantua Haverford Community Center, acquisition, renovations and construction
2,000,000
(GG) Wordsworth Academy, renovations to accommodate residential educational and treatment facility for children and adolescents
2,500,000
(HH) Philadelphia Housing Authority, Ludlow revitalization project, infrastructure, demolition, acquisition and other construction costs associated with the new construction of 75 rental units and 50 homeownership units
2,143,000
(II) Philadelphia Housing Authority, Brewerytown revitalization project, infrastructure, demolition, acquisition and other construction costs associated with the new construction of 40 rental units and 20 homeownership units
5,000,000
(JJ) Philadelphia Housing Authority, Abbottsford revitalization project, infrastructure, demolition and other construction costs associated with the new construction of 100 rental units
5,000,000
(KK) Philadelphia Housing Authority, Warnock Street revitalization project, infrastructure, demolition, acquisition and other construction costs associated with the new construction of 80 infill rental units
5,000,000
(LL) Philadelphia Housing Authority, Mantua revitalization project, infrastructure, demolition, acquisition and other construction costs associated with the new construction of 150 rental units
9,100,000
(MM) Historic Nineteenth Street Baptist Church, construction, abatement, renovations and infrastructure improvements
500,000
(NN) Water Tower Recreation Center, Chestnut Hill, restoration and infrastructure improvements of the water tower and community activity facilities
1,500,000
(OO) Temple University Hospital, Episcopal Campus, acquisition, infrastructure improvements and construction of radiology area
850,000
(PP) Acquisition, renovation, site improvements and new construction to accommodate automobile education center, museum and archive
10,000,000
(QQ) Redevelopment of Essington Commons brownfield site located on Essington Avenue, including infrastructure and site improvements
12,500,000
(RR) Children's Hospital of Philadelphia, South Campus Project, renovations, infrastructure and site improvements and construction of Civic Center Boulevard Research Tower, Phase II lab facility
20,000,000
(SS) PAPA Recreation Complex, recreational facility improvement and construction
600,000
(TT) Reunion Square, housing construction and development
13,000,000
(UU) The Plaza at Enterprise Heights, construction of a mixed-use development site
60,000,000
(VV) Philadelphia Business and Technology Center, renovations and construction
4,000,000
(WW) Croyden Development Project, acquisition, infrastructure improvements and construction
50,000,000
(XX) West Parkside retail complex, acquisition, infrastructure improvements and construction
10,000,000
(YY) Facility improvements to Clef Club
1,000,000
(ZZ) Liberty Landing, infrastructure improvements, development and construction
6,000,000
(AAA) Awbury Arboretum, renovation and restoration
1,000,000
(BBB) Achieve-Ability, demolition, renovations and construction to after-school and community center
2,300,000
(CCC) Renovation, rehabilitation, restoration and expansion of historic Christ Church facility, burial ground and Neighborhood House for community use purposes
5,000,000
(DDD) Ogontz Avenue Revitalization Corporation, acquisition, demolition, renovation and construction of the Erlen Theatre site and adjoining properties on West Cheltenham Avenue
600,000
(EEE) Acquisition, construction, infrastructure and other related costs for the Kroc Center Complex
8,000,000
(FFF) Philadelphia Industrial Development Corporation, supermarket development in 198th District
1,500,000
(GGG) Acquisition, construction, infrastructure and other related costs for the National Center for Rhythm and Blues
500,000
(HHH) Acquisition, construction, infrastructure and other related costs for the development of a business development and support center
4,000,000
(III) Construction, infrastructure and other related costs to expand the Zion Non-Profit Charitable Trust human services building
1,000,000
(JJJ) Construction, infrastructure and other related costs for the renovation of the Metropolitan Opera House on the Avenue of the Arts
1,000,000
(KKK) Acquisition, construction, infrastructure and other related costs for South 60th Street revitalization
500,000
(LLL) Construction, infrastructure and other related costs to expand and renovate the Philadelphia Dance Company Headquarters in West Philadelphia
1,000,000
(MMM) Construction, infrastructure and other related costs for the Kappa Alpha Psi mixed-use project on the Avenue of the Arts
1,000,000
(NNN) Acquisition, construction, infrastructure and other related costs for the West Philadelphia Job Training and Technology Center
500,000
(OOO) Acquisition, construction, infrastructure and other related costs for Community Legal Services in North Philadelphia
1,000,000
(PPP) Acquisition, construction, infrastructure and other related costs for the Asian Arts Initiative Shared Arts Facility
2,000,000
(QQQ) Acquisition, construction, infrastructure and other related costs to renovate the Schuylkill Falls Community Health Center
500,000
(RRR) Construction, infrastructure and other related costs for the Jardel pool
500,000
(SSS) Acquisition, construction, infrastructure and other related costs for a commercial corridors streetscape project in the Stenton Avenue, Wadsworth Avenue, Ogontz Avenue, Germantown Avenue, Vernon Road and Washington Lane area
1,000,000
(TTT) Acquisition, construction, infrastructure and other related costs for the renovation of the former Ada Lewis Middle School
2,000,000
(UUU) Acquisition, construction, infrastructure and other related costs for a Child Care and Education Center in the 1800 Block of Tioga Street
1,000,000
(VVV) Acquisition, construction, infrastructure and other related costs to revitalize Ogontz Avenue
2,000,000
(52) Pike County
(i) County projects (Reserved)
(ii) Milford Borough
(A) Construction, infrastructure and other related costs for the Pike County Public Library
2,000,000
(iii) Westfall Township
(A) Construction, expansion and improvement of water and sewer infrastructure to support existing and new development within the township
2,000,000
(53) Potter County (Reserved)
(54) Schuylkill County
(i) County projects (Reserved)
(ii) City of Pottsville
(A) Preparation and construction of the Union Station site in downtown Pottsville
6,000,000
(iii) Coaldale Borough
(A) Renovation of emergency rooms, radiology labs and surgical center at St. Luke's Miner's Memorial Hospital
5,000,000
(iii.1) Mahanoy Township
(A) Construction of water and sewer lines in the Mahanoy Township Business Park
4,500,000
(iv) McAdoo Borough
(A) Downtown Streetscape improvements
500,000
(v) Orwigsburg Borough
(A) Capital improvements to the Orwigsburg Library, including necessary costs
500,000
(B) Capital improvements to Orwigsburg Memorial Hall, including necessary costs
500,000
(v.1) Rush Township
(A) Expansion of an Air Products Industrial Park
1,200,000
(B) Expansion of the Tidewood East Industrial Park, including infrastructure
1,000,000
(vi) Schuylkill County Economic Development Corporation
(A) Construction of a six-mile pipeline from Commonwealth Environmental Systems to proposed ethanol facility in Porter Township
4,180,000
(vii) Tamaqua Borough
(A) Construction of a river park and river walk
500,000
(55) Snyder County (Reserved)
(56) Somerset County
(i) County projects
(A) Land acquisition, site preparation, infrastructure development, design and construction of a visitors center and memorial for Flight 93
10,000,000
(B) Somerset Hospital for construction and redevelopment of a four-square-block area encompassing the hospital facility and surrounding area as a health care campus
500,000
(C) Quemahoning Township water pipeline project, including Conemaugh, Jenner, Lincoln and Somerset Townships and Boswell and Somerset Boroughs, infrastructure development for the Somerset Industrial Park and the Northstar Business Park
22,000,000
(D) Laurel Highlands Business Park, for acquisition and construction of facilities to accommodate light-industrial and technology-based commerce
5,000,000
(E) Renovations and expansion of Somerset Hospital for a combination rehabilitation facility and medical office building
3,000,000
(F) PBS Coals expansion of coal production facilities, including infrastructure and site improvements
8,000,000
(G) Methane Gas Recovery Project, construction of methane gas recovery and distribution systems
1,000,000
(ii) Indian Lake Borough
(A) Indian Lake Dam, outlet works remediation and siphon system
250,000
(iii) Somerset County Redevelopment Authority
(A) Improvements to property at Route 31 and Gardner Road, including construction and related infrastructure
6,000,000
(iv) Windber Borough
(A) Acquisition, construction, infrastructure and other related costs for a biotechnology center
6,000,000
(B) Acquisition, construction, infrastructure and other related costs for a data fusion and storage center
10,000,000
(57) Sullivan County (Reserved)
(58) Susquehanna County
(i) County projects
(A) Endless Mountains Health System, construction of clinic and inpatient care units, including the installation of necessary equipment
10,000,000
(ii) Montrose Borough
(A) Expansion of The Center for Anti-Slavery Studies
2,000,000
(59) Tioga County
(i) County projects
(A) Environmental remediation for the Tioga River
9,300,000
(B) Construction of a performing arts center in Tioga County
2,000,000
(ii) Mansfield Borough
(A) Development of an industrial park
10,000,000
(iii) Borough of Wellsboro
(A) Expansion and renovation of the emergency department for Soldiers & Sailors Memorial Hospital
7,000,000
(60) Union County
(i) County projects
(A) Development of the Bucknell University-Bull Run Gateway neighborhood development project, including an art center and parking
10,000,000
(ii) Union County Industrial Development Corporation
(A) Redevelopment of the former Pennsylvania House property for a mixed-use destination development
20,000,000
(61) Venango County
(i) County projects
(A) Enviro Biodiesel, construction of an alternative fuel processing plant located on a brownfield site
15,000,000
(B) Venango County Courthouse, facility improvements, including security upgrades, fireproofing and window replacement
500,000
(ii) Rouseville Borough
(A) Construction of an alternative fuel processing plant on the Pennzoil refinery site
15,000,000
(iii) Oil City
(A) Oil City Industrial Park, construction of a manufacturing facility
5,200,000
(B) Oil City Industrial Park, construction of a manufacturing facility
2,500,000
(62) Warren County
(i) County projects
(A) Construction of a facility to house the Warren/Forest Higher Education Council, including necessary costs associated with acquisition and infrastructure
2,000,000
(B) Warren County welcome sign and kiosk enhancement project
350,000
(ii) City of Warren
(A) Construction of the Warren County Geospatial Information Service facility
500,000
(B) Development and expansion of medical campus in Pine Grove Township for Warren General Hospital
1,048,000
(C) Construction of conference center/hotel as part of existing Impact Warren project
4,000,000
(63) Washington County
(i) County projects
(A) Construction and related costs for the renovation of the Meadowcroft Rockshelter and Museum of Rural Life
500,000
(B) Construction, infrastructure and other related costs for the Pony Baseball Field renovation
1,000,000
(C) Acquisition, demolition, construction and other related costs for the construction of a parking garage
5,000,000
(D) Washington and Jefferson College, construction of a recreation center, including facilities for community use
2,000,000
(E) Washington and Jefferson College, redevelop vacant and underutilized upper floor spaces in downtown Washington to provide living space for young professionals, artists, students and others interested in downtown living
3,000,000
(F) Renovations, including infrastructure improvements and construction to Mon Valley Hospital
3,000,000
(G) Acquisition, infrastructure improvements and construction of a day care for medically fragile children for the United Cerebral Palsy Your Child's Place project
2,000,000
(H) Acquisition, infrastructure improvements and construction of additional exhibit areas and other expansion at the Lemoyne House
4,000,000
(I) Renovations to emergency room and other hospital renovations to include infrastructure improvements and construction to Washington Hospital
10,000,000
(J) Acquisition, construction, infrastructure and other related costs for the Center for Creative Play
2,500,000
(K) Acquisition, demolition, construction, infrastructure and other related costs to develop a multipurpose facility at the Fort Pitt Bridge Industrial Park
4,900,000
(L) Construction, infrastructure, abatement of hazardous materials and other related costs to redevelop the Pennsylvania Transformer brownfield site
1,600,000
(M) Construction, infrastructure and other related costs for improvements to county fairgrounds and related facilities
1,500,000
(ii) Burgettstown Borough
(A) Acquisition, construction, infrastructure and other related costs for the revitalization of the business district
750,000
(iii) California Borough
(A) Acquisition, construction, infrastructure and other related costs for the expansion of the California Technology Park
750,000
(iv) Fallowfield Township
(A) Construction, infrastructure and other related costs for improvements to Alta Vista Industrial Park
750,000
(v) Hanover Township
(A) Construction, site development, infrastructure and other related costs to redevelop the Starvaggi Property
5,000,000
(B) Starpointe Business Industrial Park, development of infrastructure and sites and construction
5,000,000
(vi) North Strabane Township
(A) Acquisition, construction and other related costs for the Greater Washington County Food Bank
1,000,000
(vii) Peters Township
(A) Acquisition and construction of a community center, including redevelopment and infrastructure
1,250,000
(B) Expansion of the Peters Township Volunteer Fire Department, including acquisition, construction and related infrastructure
1,500,000
(viii) City of Washington
(A) Washington Hospital, construction of new facilities to accommodate community growth, including the emergency department, operating rooms, surgical beds and a health and wellness institute
3,000,000
(64) Wayne County
(i) County projects
(A) Construction of an EMS headquarters building to serve Greater Wayne and Northern Pike Counties
1,200,000
(65) Westmoreland County
(i) County projects
(A) Acquisition, construction and other related costs for the rehabilitation of Youngwood Railroad Museum
1,000,000
(B) Acquisition, rehabilitation and restoration of the Youngwood Railroad Museum and adjacent property for the creation of a destination spot
1,000,000
(C) WCCC Baseball Stadium, renovate current baseball field, add seating, locker rooms and press box to attract minor league baseball team and State regional college playoffs
1,500,000
(D) Construction of the Westmoreland County Economic Development Center to be located at West Otterman Street in the City of Greensburg
2,200,000
(E) Acquisition and conversion of the former Lenox Plant for reuse as a multitenant facility, including blight removal and environmental remediation
2,600,000
(F) Construction of a more than 50,000-square-foot flex-type building for Westmoreland Distribution Park/Multitenant Business Facility
4,000,000
(G) Develop 225-acre industrial park adjacent to Arnold Palmer Airport in Unity Township
750,000
(H) St. Vincent College Center for Public Service, rehabilitation and preservation of existing machine shop building for community reuse and outreach efforts
5,000,000
(I) Jeannette Industrial Park, redevelopment of the former GGI Glass Plant
500,000
(J) Westmoreland County Community College, Hempfield Township, renovation and rehabilitation of biology laboratory and library in Founders' Hall, including roof replacement/repair and replacement of HVAC units and associated engineering and permitting
1,000,000
(K) Westmoreland County Community College, Hempfield Township, renovate science hall, design, permitting and construction
500,000
(L) Westmoreland County Community College, City of New Kensington, construct new Alle-Kiski Education Center, including design, engineering and permitting
1,500,000
(M) Westmoreland County Community College, Unity Township, relocate Laurel Education Center, including land acquisition, design, construction and permitting
1,500,000
(N) Construction, infrastructure and other related costs for City of Latrobe downtown revitalization
1,000,000
(O) Construction, infrastructure and other related costs for an education center at Historic Hannas Town Fort Site
3,000,000
(ii) City of Greensburg
(A) Construction and other related costs for Phase II of the Seton Hill University downtown project
3,000,000
(B) Renovation of the Palace Theatre's second and third floors and exterior facade and marquis for cultural and performing arts activities
2,000,000
(C) Seton Hill/Harrison Avenue Project, redevelopment, including the demolition of blighted structures and stabilization of the road base and utility relocation
2,000,000
(D) Seton Hill University, National Education Center for Women in Business, development of a new state-of-the-art training and conference center
2,000,000
(E) Westmoreland Museum of Art, construction of new amenities for visitors to the museum as well as an upgraded reinstallation of the permanent collection
2,000,000
(F) Renovation and expansion of the Greensburg YMCA, including pool and gymnasium
2,500,000
(G) Senior housing project and/or infrastructure in support of senior house project
4,000,000
(iii) Hempfield Township
(A) Development and construction of the Westmoreland Office and Technology Park
2,100,000
(B) Westmoreland Conservation District Greenforge Project, renovation and rehabilitation of existing office building, including the installation of a green roof, natural lighting and geothermal source heating and cooling
1,200,000
(C) Construction of an all-age recreation center
4,000,000
(D) Design and construction of a more-than-14,000-square-foot visitor center for Historic Hanna's Town
2,000,000
(iv) City of Irwin
(A) Rehabilitation and renovation of the Lamp Theatre
500,000
(B) Acquisition, rehabilitation and historic renovation of the Thompson Building for mixed-use applications
2,500,000
(C) Acquisition, rehabilitation and restoration of targeted structures along Main Street and Pennsylvania Avenue in conjunction with the overall comprehensive plan of the Irwin Project
2,500,000
(v) City of Jeannette
(A) South Sixth Street revitalization project, construction of 25 new single-family homes, including acquisition and demolition of existing structures, rehabilitation of 20 townhomes for market-rate rentals and renovation and rehabilitation of existing baseball field
4,100,000
(B) Redevelopment of the former glass plant situated in the City of Jeannette, including environmental remediation, demolition and site improvements
5,000,000
(C) Mercy Jeannette Hospital, design, permitting, construction and purchase of equipment for an expanded emergency room
1,250,000
(vi) City of Latrobe
(A) Purchase, rehabilitation and historical renovation of targeted structures in the core downtown area of Latrobe for commercial reuse and development of a downtown destination spot
1,000,000
(vii) Monessen
(A) Renovation of retail space for community-based and health and human services building
1,700,000
(viii) New Kensington
(A) New Kensington River Line District redevelopment
5,000,000
(ix) Rector
(A) Expansion of the Florence Lockhart Nimick Nature Center at Powdermill Nature Reserve, including construction
1,500,000
(x) Westmoreland County Industrial Development Corporation
(A) Development of a 113-acre parcel of county-owned property located along SR 1053 directly opposite the Westmoreland County Industrial Park I in Hempfield Township for future business locations
3,000,000
(66) Wyoming County (Reserved)
(67) York County
(i) County projects
(A) Acquisition, construction, infrastructure improvements and other related costs for an economic and community development project
5,000,000
(B) New buildings for the York County Society for the Prevention of Cruelty to Animals
3,000,000
(C) Construction of a new live burn building for the York County Fire Training Facility located in Emigsville, including demolition of existing structures
1,500,000
(ii) City of York
(A) Construction of a multipurpose recreation facility
8,000,000
(B) Construction, infrastructure and related costs to renovate and expand an existing facility to increase the number of laboratory and general classrooms
5,000,000
(C) Memorial Hospital, acquisition of an automated drug dispensing system
419,000
(D) York Police Department, acquisition of sensor surveillance equipment
500,000
(E) Development of the National Museum and Downtown Visitors Center
5,000,000
(F) Penn and Farquhar Park renovations
4,500,000
(G) Revitalize Broad Street Corridor
3,000,000
(H) Redevelop South George Street
3,000,000
(I) Development and construction associated with the York Commodity Resources Project
5,000,000
(J) Construction and renovation necessary for the expansion of the Logos Academy
1,975,000
(iii) Hopewell Township
(A) Acquisition of land and design and construction of a new township building
3,000,000
(iv) Lower Windsor Township
(A) Construction and design of a recreation building. This authorization includes funds for costs related to land acquisition if necessary.
2,000,000
(B) Acquisition and construction of land related to the Susquehanna Riverlands Preservation Project
14,000,000
(v) Springettsbury Township
(A) Construction of the York Towne Center, including related infrastructure
6,000,000
(vi) Hanover Borough and Penn Township
(A) Construction of a 1.5 mile portion of the York Hanover Trolley line as a recreational pathway, including related costs
500,000
(68) Multicounty projects
(i) Allegheny and Westmoreland Counties
(A) Infrastructure and site development for the Advanced Therapeutic Manufacturing Facility to be located in either Allegheny or Westmoreland Couny
15,000,000